Job Info for 0206-07-059

County: RUSK Highway: US 79 Date: 01/04/2024 (10 months ago) Engineer's Estimate: $4,458,301 Control Number: 0206-07-059
Project: C 206-7-59 District: TYLER Time: 62 WORKING DAYS Type: PVMNT REPAIR, PLANING, OCST, PFC SURF, MBGF, PV MK
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,458,300.68
MADDEN CONTRACTING COMPANY, LLC.   $3,202,956.86 1
-28.16% | -$1,255,343.82
REYNOLDS & KAY, LTD.   $3,307,282.90 2
-25.82% | -$1,151,017.78
3.26% | $104,326.04
LONGVIEW BRIDGE AND ROAD, LTD.   $3,999,109.95 3
-10.3% | -$459,190.73
24.86% | $796,153.09
20.92% | $691,827.05
DREWERY CONSTRUCTION COMPANY, INCORPORATED   $4,388,257.29 4
-1.57% | -$70,043.39
37.01% | $1,185,300.43
9.73% | $389,147.34
EAST TEXAS BRIDGE, INC.   $4,433,211.25 5
-0.56% | -$25,089.43
38.41% | $1,230,254.39
1.02% | $44,953.96
FNH CONSTRUCTION, LLC   $6,250,859.40 6
40.21% | $1,792,558.72
95.16% | $3,047,902.54
41.00% | $1,817,648.15
Subcontractor Percentage Amount
TRUE ROADS, LLC 15.41% $493,575.65
REYNOLDS & KAY, LTD. 9.46% $302,999.72
DREWERY CONSTRUCTION COMPANY, INCORPORATED 7.35% $235,417.33
SOUTHWEST ENVIRONMENT SERVICES LLC 7.08% $226,769.35
KENT TREE SERVICE LLC 4.60% $147,336.02
ISAACS CONSTRUCTION SERVICES LLC 3.06% $98,010.48
STRIPING TECHNOLOGY, L.P. 1.96% $62,777.95
MORRIS COUNTY CONTRACTORS, L.L.C. 0.91% $29,146.91
PANOLA SIGN & BARRICADE, INC. 0.29% $9,288.57
WEST TEXAS ROCK RESOURCES, LLC 0.23% $7,366.80
Total: 50.35% $1,612,688.78

Bid Items

Items: 61, 0 filtered
RUSK US 79  |  TYLER  |  0206-07-059  |  01/04/2024  |  $4,458,301  |  C 206-7-59  |  PVMNT REPAIR, PLANING, OCST, PFC SURF, MBGF, PV MK  |  62 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MADDEN CONTRACTING COMPANY, LLC. REYNOLDS & KAY, LTD. LONGVIEW BRIDGE AND ROAD, LTD. DREWERY CONSTRUCTION COMPANY, INCORPORATED EAST TEXAS BRIDGE, INC. FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 81.200 $7,000.000 $2,850.000 $2,100.000 $4,900.000 $4,100.000 $9,500.000 $6,157.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 61.000 $40.000 $55.000 $25.000 $35.000 $61.000 $50.000 $100.000
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 270.000 $94.160 $60.000 $33.000 $35.000 $66.500 $40.000 $100.000
134 6002 BACKFILL (TY B) STA 148.000 $450.000 $275.000 $220.000 $1,800.000 $925.000 $475.000 $650.000
150 6001 BLADING STA 39.000 $350.000 $160.000 $300.000 $250.000 $875.000 $400.000 $450.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 133,757.000 $2.500 $1.000 $0.500 $0.250 $4.000 $3.000 $9.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 146,565.000 $0.800 $0.580 $0.650 $0.600 $0.640 $0.650 $0.500
164 6055 BONDED FBR MTRX SEED (TEMP)(WARM) SY 133,757.000 $0.800 $0.550 $0.600 $0.550 $0.600 $0.600 $0.500
164 6056 BONDED FBR MTRX SEED (TEMP)(COOL) SY 133,757.000 $0.800 $0.530 $0.600 $0.550 $0.580 $0.600 $0.500
168 6001 VEGETATIVE WATERING MG 1,612.000 $15.000 $21.250 $20.000 $30.000 $15.000 $9.000 $50.000
316 6406 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) GAL 32,571.000 $7.310 $4.500 $4.500 $4.850 $4.250 $4.850 $10.000
316 6407 AGGR (TY-PD GR-3 OR TY-PL GR-3) CY 775.000 $200.000 $190.000 $190.000 $215.000 $225.000 $140.000 $500.000
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 1,500.000 $120.000 $100.000 $95.000 $150.000 $106.000 $110.000 $88.000
354 6051 PLANE ASPH CONC PAV (0" TO 1 1/2") SY 1,600.000 $9.630 $10.000 $10.000 $11.150 $9.000 $15.000 $20.000
420 6071 CL C CONC (COLLAR) EA 5.000 $1,350.000 $2,200.000 $950.000 $1,500.000 $2,500.000 $2,000.000 $1,500.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 40.000 $700.000 $850.000 $900.000 $1,000.000 $950.000 $750.000 $550.000
464 6003 RC PIPE (CL III)(18 IN) LF 366.000 $74.250 $74.000 $60.000 $150.000 $82.000 $75.000 $85.000
464 6005 RC PIPE (CL III)(24 IN) LF 56.000 $92.000 $105.000 $80.000 $200.000 $115.000 $100.000 $105.000
464 6010 RC PIPE (CL III)(48 IN) LF 32.000 $400.000 $285.000 $200.000 $335.000 $315.000 $300.000 $450.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 72.000 $1,150.000 $865.000 $1,050.000 $840.000 $960.000 $1,000.000 $1,850.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 4.000 $1,583.330 $1,400.000 $1,500.000 $1,875.000 $1,550.000 $1,350.000 $2,500.000
467 6480 SET (TY II) (48 IN) (RCP) (6: 1) (P) EA 2.000 $16,500.140 $9,500.000 $10,000.000 $10,275.000 $10,500.000 $11,000.000 $15,000.000
496 6016 REMOV STR (PIPE) EA 16.000 $900.000 $500.000 $650.000 $600.000 $555.000 $650.000 $500.000
500 6001 MOBILIZATION LS 1.000 $400,000.000 $300,000.000 $430,000.000 $390,000.000 $550,000.000 $450,000.000 $600,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $10,000.000 $10,000.000 $25,000.000 $15,000.000 $4,500.000 $25,000.000 $8,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 1,660.000 $36.000 $36.000 $40.000 $47.500 $40.000 $40.000 $35.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 1,660.000 $7.590 $11.000 $12.000 $14.500 $12.500 $12.000 $15.000
506 6029 EARTHWORK (EROSN & SEDMT CONT, IN VEH) CY 702.000 $45.500 $24.000 $19.000 $50.000 $50.000 $30.000 $50.000
506 6030 BACKHOE WORK (EROSION & SEDMT CONT) HR 47.000 $141.500 $225.000 $55.000 $180.000 $155.000 $100.000 $100.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 4,740.000 $3.810 $3.500 $4.000 $4.600 $3.750 $4.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 4,740.000 $1.400 $0.750 $0.800 $1.000 $1.000 $0.850 $2.000
506 6046 TRACKHOE WORK (EROSION & SEDMT CONT) HR 47.000 $176.430 $225.000 $91.000 $290.000 $315.000 $150.000 $100.000
530 6002 INTERSECTIONS (ACP) SY 135.000 $85.000 $100.000 $75.000 $142.000 $95.500 $65.000 $55.000
530 6005 DRIVEWAYS (ACP) SY 1,167.000 $140.000 $75.000 $60.000 $100.000 $75.000 $65.000 $55.000
530 6017 DRIVEWAYS (CONC) (HES) SY 61.000 $180.000 $175.000 $175.000 $189.000 $200.000 $225.000 $150.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 29,496.000 $0.400 $0.550 $0.350 $0.350 $0.500 $0.500 $0.500
533 6002 RUMBLE STRIPS (CENTERLINE) LF 14,748.000 $0.400 $0.550 $0.350 $0.350 $0.750 $0.500 $0.500
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 400.000 $35.000 $36.500 $43.000 $50.000 $40.500 $40.000 $35.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,500.000 $2,825.000 $3,300.000 $4,225.000 $3,125.000 $3,200.000 $3,250.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 16.000 $40.000 $25.000 $29.000 $33.000 $28.000 $30.000 $100.000
662 6005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 1,180.000 $0.480 $0.500 $0.550 $0.700 $0.560 $0.550 $1.000
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 24,496.000 $0.940 $0.350 $0.400 $0.500 $0.390 $0.400 $1.000
662 6035 WK ZN PAV MRK NON-REMOV (Y)6"(BRK) LF 2,090.000 $0.550 $0.500 $0.550 $0.700 $0.560 $0.550 $1.000
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 19,159.000 $0.550 $0.350 $0.400 $0.500 $0.390 $0.400 $1.000
662 6064 WK ZN PAV MRK REMOV (W)6"(BRK) LF 531.000 $3.000 $1.850 $1.400 $2.200 $2.250 $4.000 $2.250
662 6096 WK ZN PAV MRK REMOV (Y)6"(BRK) LF 941.000 $15.000 $1.850 $1.400 $2.200 $2.250 $4.000 $1.000
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 4,311.000 $15.000 $1.850 $1.400 $2.200 $2.250 $4.000 $1.250
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 354.000 $2.000 $1.150 $1.100 $1.750 $1.500 $2.000 $6.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 1,585.000 $4.000 $1.150 $1.100 $1.750 $1.500 $2.000 $6.000
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 1,180.000 $3.500 $1.000 $1.100 $1.350 $1.110 $1.100 $1.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 29,496.000 $0.980 $0.750 $0.850 $1.000 $0.830 $0.850 $1.000
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 2,090.000 $1.150 $1.000 $1.100 $1.350 $1.110 $1.100 $1.000
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 19,159.000 $1.150 $0.750 $0.850 $1.000 $0.830 $0.850 $1.000
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 37.000 $15.000 $15.000 $17.000 $20.000 $16.670 $20.000 $22.000
668 6083 PREFAB PAV MRK TY C (W) (LNDP ARROW) EA 2.000 $354.740 $350.000 $400.000 $465.000 $388.950 $400.000 $500.000
672 6007 REFL PAV MRKR TY I-C EA 58.000 $10.000 $5.000 $5.750 $6.600 $5.560 $5.500 $6.000
672 6009 REFL PAV MRKR TY II-A-A EA 396.000 $7.000 $5.000 $5.750 $6.600 $5.560 $5.500 $6.000
3079 6011 PFC-C PG76-22 SAC-A TON 5,694.000 $220.000 $200.000 $210.000 $220.000 $236.500 $225.000 $335.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 14.000 $350.000 $100.000 $150.000 $200.000 $660.000 $300.000 $150.000
6185 6002 TMA (STATIONARY) DAY 62.000 $400.130 $225.000 $250.000 $250.000 $300.000 $300.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 5.000 $750.000 $1.000 $200.000 $165.000 $750.000 $300.000 $850.000
Totals: $4,458,300.68 $3,202,956.86 $3,307,282.90 $3,999,109.95 $4,388,257.29 $4,433,211.25 $6,250,859.40