County: RUNNELS Highway: CR Date: 10/01/2024 (7 weeks ago) Engineer's Estimate: $1,083,636 Control Number: 0907-13-024
Project: BR 2024(802) District: SAN ANGELO Time: 138 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,083,635.64
STX CIVIL   $1,527,290.16 1
40.94% | $443,654.52
J. H. STRAIN & SONS, INC.   $1,532,426.08 2
41.42% | $448,790.44
0.34% | $5,135.92
DELGADO'S CONTRACTORS, LLC   $1,706,772.20 3
57.5% | $623,136.56
11.75% | $179,482.04
11.38% | $174,346.12
SKYLINE BRIDGE LLC   $1,831,070.54 4
68.97% | $747,434.90
19.89% | $303,780.38
7.28% | $124,298.34
C. E. BARKER, LTD.   $1,974,188.60 5
82.18% | $890,552.96
29.26% | $446,898.44
7.82% | $143,118.06
COPPELL CONSTRUCTION CO., INC.   $1,989,498.00 6
83.59% | $905,862.36
30.26% | $462,207.84
0.78% | $15,309.40
HODGES AND SON CONSTRUCTION COMPANY, INC.   $2,692,626.00 7
148.48% | $1,608,990.36
76.3% | $1,165,335.84
35.34% | $703,128.00

Bid Items

Items: 28, 0 filtered
RUNNELS CR  |  SAN ANGELO  |  0907-13-024  |  10/01/2024  |  $1,083,636  |  BR 2024(802)  |  BRIDGE REPL  |  138 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STX CIVIL J. H. STRAIN & SONS, INC. DELGADO'S CONTRACTORS, LLC SKYLINE BRIDGE LLC C. E. BARKER, LTD. COPPELL CONSTRUCTION CO., INC. HODGES AND SON CONSTRUCTION COMPANY, INC.
100 7002 PREPARING ROW STA 9.000 $2,500.000 $5,000.000 $1,400.000 $750.000 $4,000.000 $22,000.000 $10,000.000 $12,000.000
105 7028 RMV (8") TRT/UNTRT BASE & ASPH PAV SY 721.000 $7.000 $12.000 $12.000 $10.000 $15.000 $25.270 $17.000 $10.000
110 7001 EXCAV (ROADWAY) CY 311.000 $23.000 $25.000 $50.000 $40.000 $16.000 $21.480 $52.000 $50.000
132 7006 EMBANK (FNL)(DC)(TY C) CY 196.000 $26.000 $35.000 $50.000 $65.000 $50.000 $21.480 $61.000 $100.000
247 7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") SY 840.000 $26.000 $40.000 $35.000 $35.000 $40.000 $19.270 $35.000 $100.000
400 7010 CEM STABIL BKFL CY 52.000 $97.000 $225.000 $200.000 $250.000 $382.000 $189.550 $450.000 $325.000
416 7004 DRILL SHAFT (24 IN) LF 885.000 $191.000 $290.000 $241.000 $350.000 $379.000 $335.970 $262.000 $230.000
420 7012 CL C CONC (ABUT) CY 36.600 $950.000 $190.000 $1,000.000 $1,800.000 $1,200.000 $2,094.450 $2,500.000 $2,800.000
420 7022 CL C CONC (CAP) CY 33.900 $1,008.000 $2,000.000 $1,100.000 $1,800.000 $1,617.000 $2,081.450 $2,000.000 $3,000.000
420 7038 CL C CONC (COLUMN) CY 16.400 $916.000 $2,850.000 $1,000.000 $1,800.000 $1,688.000 $2,078.710 $2,500.000 $3,000.000
422 7001 REINF CONC SLAB SF 6,630.000 $19.000 $23.000 $25.000 $30.000 $29.000 $28.630 $30.000 $45.000
422 7013 APPROACH SLAB CY 85.000 $592.000 $630.000 $1,000.000 $1,000.000 $764.000 $966.290 $750.000 $1,600.000
425 7017 PRESTR CONC SLAB BEAM (5SB12) LF 1,257.560 $184.000 $236.000 $243.000 $245.000 $334.000 $296.890 $300.000 $350.000
432 7013 RIPRAP (MOW STRIP)(4 IN) CY 40.000 $705.000 $600.000 $700.000 $650.000 $779.000 $669.750 $750.000 $800.000
432 7044 RIPRAP (STONE PROTECTION)(21 IN) CY 298.000 $200.000 $260.000 $185.000 $250.000 $219.000 $149.960 $345.000 $350.000
450 7008 RAIL (TY T223) LF 558.000 $101.000 $150.000 $140.000 $200.000 $167.000 $183.230 $225.000 $180.000
454 7001 TYPE A JOINT LF 81.000 $32.000 $75.000 $42.000 $200.000 $150.000 $189.550 $165.000 $200.000
454 7004 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 52.000 $103.000 $285.000 $175.000 $250.000 $354.000 $271.690 $380.000 $280.000
496 7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 2.000 $16,565.000 $40,000.000 $85,000.000 $30,000.000 $25,000.000 $37,910.250 $43,000.000 $200,000.000
500 7001 MOBILIZATION LS 1.000 $75,000.000 $130,000.000 $100,000.000 $130,000.000 $150,000.000 $198,000.000 $175,000.000 $250,000.000
502 7001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $5,000.000 $2,500.000 $5,000.000 $2,250.000 $3,060.000 $3,500.380 $15,000.000 $5,000.000
503 7002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $1,000.000 $5,500.000 $8,000.000 $15,000.000 $17,500.000 $5,054.700 $10,000.000 $25,000.000
505 7001 TMA (STATIONARY) DAY 14.000 $200.000 $350.000 $400.000 $350.000 $250.000 $505.470 $350.000 $300.000
506 7039 TEMP SEDMT CONT FENCE (INSTALL) LF 120.000 $5.000 $6.000 $12.000 $7.000 $6.000 $6.320 $6.000 $1.000
506 7041 TEMP SEDMT CONT FENCE (REMOVE) LF 120.000 $1.000 $2.000 $6.000 $1.000 $5.000 $2.530 $1.000 $1.000
540 7002 MTL W-BEAM GD FEN (STEEL POST) LF 200.000 $26.600 $35.000 $44.000 $40.000 $38.000 $40.120 $30.000 $30.000
540 7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 8.000 $3,000.000 $3,850.000 $3,850.000 $1,800.000 $2,800.000 $3,317.150 $2,000.000 $2,500.000
544 7001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $3,650.000 $4,500.000 $4,125.000 $4,250.000 $4,200.000 $4,517.640 $3,000.000 $4,000.000
Totals: $1,083,635.64 $1,527,290.16 $1,532,426.08 $1,706,772.20 $1,831,070.54 $1,974,188.62 $1,989,498.00 $2,692,626.00