RUNNELS SH 153 (0650-03-036)

Items: 109

County: RUNNELS
Length: N/A
Highway: SH 153
District: SAN ANGELO
Control Number: 0650-03-036
DBE Goal: N/A
Project: F 2B23(225)
Guaranty: N/A
Time: 460 WORKING DAYS
Engineer's Estimate: $22,151,442.77
Date: 09/07/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY / BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JORDAN SEFCIK
ALFREDO LUERA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$22,151,442.77
1
$21,350,244.52
Over/Under Est: -3.62% -$801,198.25
$23,896,190.28
Over/Under Est: 7.88% $1,744,747.51
Amt Left: 11.92% $2,545,945.76
$26,586,451.03
Over/Under Est: 20.02% $4,435,008.26
Amt Left: 24.53% $5,236,206.51
Delta: -11.26% -$2,690,260.75
Subcontractor Percentage Amount
COPPELL CONSTRUCTION CO., INC. 8.04% $1,728,790.37
HJC FARMS, INC. 2.69% $578,413.69
J. H. ODEN CONTRACTING COMPANY 1.54% $331,136.46
TRP CONSTRUCTION GROUP, LLC 0.95% $204,272.49
CONTRACTORS SERVICE, LTD. 0.66% $141,915.63
HODGES AND SON CONSTRUCTION COMPANY, INC. 0.46% $98,910.89
DUSTROL, INC. 0.18% $38,704.26
SURFACE PREPARATION TECHNOLOGIES, LLC 0.12% $25,802.84
TORO BRAVO CONSTRUCTION, LLC 0.03% $6,450.71
PENHALL COMPANY 0.02% $4,300.47
Total: 14.69% $3,158,697.81

Bid Items & Bid Tabulations

109 Total 0 of 109
RUNNELS  |  SH 153  |  SAN ANGELO  |  0650-03-036  |  09/07/2023  |  $22,151,442.77  |  F 2B23(225)  |  REHAB EXIST ROADWAY / BRIDGE REPL  |  460 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
A. L. HELMCAMP, INC.
GILVIN-TERRILL, LTD.
PREPARING ROW
STA 11.000 $5,000.000 $8,944.000 $3,000.000 $220,000.000
EXCAVATION (ROADWAY)
CY 2,277.000 $25.000 $35.750 $70.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 75.000 $30.000 $219.060 $60.000 $150.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 2,104.000 $20.000 $43.630 $60.000 $30.000
BACKFILL (TY A OR B)
STA 662.000 $250.000 $168.010 $380.000 $250.000
FURNISHING AND PLACING TOPSOIL (4")
SY 20,452.000 $2.000 $2.950 $5.000 $5.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 14,306.000 $0.300 $0.550 $0.520 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 3,054.000 $0.300 $0.550 $0.520 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 3,054.000 $0.300 $0.550 $0.520 $1.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 182.000 $1,000.000 $1,098.900 $1,050.000 $1,050.000
VEGETATIVE WATERING
MG 347.000 $12.000 $56.010 $50.000 $55.100
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 19,327.000 $1.900 $1.420 $1.400 $2.000
SOIL RETENTION BLANKETS (CL 2) (TY E)
SY 545.000 $2.100 $3.300 $3.400 $3.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(10")
SY 4,779.000 $15.000 $31.800 $40.000 $25.000
FL BS (CMP IN PLACE) (TY D GR 1-2)(10")
SY 3,345.000 $80.000 $37.780 $40.000 $25.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 100.000 $240.000 $374.240 $385.000 $400.000
LIME TRT (SUBGRADE)(8")
SY 4,779.000 $5.000 $17.720 $10.000 $15.000
PRIME COAT (MC-30)
GAL 670.000 $6.500 $10.380 $15.000 $8.000
PRIME COAT(MC-30 OR AE-P)
GAL 911.000 $5.000 $8.970 $15.000 $8.000
EMULS ASPH (EROSN CONT)(MULTI)
GAL 2,220.000 $6.500 $6.290 $8.000 $6.000
FOG SEAL (CSS-1H)
GAL 21,334.000 $7.060 $8.970 $8.000 $6.000
AGGR(TY-PB GR-4 SAC-B)
CY 2,803.000 $225.000 $189.180 $260.000 $175.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,685.000 $6.000 $8.350 $7.000 $6.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 127,630.000 $3.930 $4.970 $6.000 $6.000
LRA PAV TY-I GR-C
TON 523.000 $100.000 $198.670 $360.000 $150.000
PLANE ASPH CONC PAV(0" TO 2")
SY 8,820.000 $5.000 $6.290 $5.000 $5.000
PLANE ASPH CONC PAV(0" TO 3")
SY 12,934.000 $5.000 $5.900 $7.500 $5.000
CEM STABIL BKFL
CY 112.000 $300.000 $363.000 $360.000 $500.000
DRILL SHAFT (36 IN)
LF 350.000 $300.000 $458.700 $460.000 $400.400
CL C CONC (ABUT)
CY 54.200 $1,500.000 $1,446.500 $1,320.000 $2,000.000
CL C CONC (CURB)
CY 4.000 $450.000 $5,632.530 $1,400.000 $2,000.000
REINF CONC SLAB (BOX BEAM)
SF 5,290.000 $16.000 $35.750 $33.000 $35.000
APPROACH SLAB
CY 70.600 $750.000 $1,045.000 $1,000.000 $2,000.000
RETAINING WALL (TEMP WALL)
SF 1,593.000 $25.000 $170.500 $165.000 $50.000
PRESTR CONC BOX BEAM (5B40)
LF 1,030.500 $338.000 $528.000 $600.000 $600.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 77.000 $415.000 $709.500 $700.000 $1,000.000
RIPRAP (MOW STRIP)(4 IN)
CY 282.000 $500.000 $715.000 $1,300.000 $800.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 270.000 $115.000 $159.500 $160.000 $120.000
RETROFIT RAIL (TY T131RC)
LF 424.000 $225.000 $247.500 $220.000 $250.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 90.000 $200.000 $302.500 $300.000 $250.000
CONC BOX CULV (7 FT X 5 FT)
LF 66.000 $975.000 $2,200.000 $2,100.000 $950.000
REMOV STR (BOX CULVERT)
LF 66.000 $91.000 $544.500 $500.000 $100.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $75,000.000 $70,331.000 $65,000.000 $1,000,000.000
MOBILIZATION
LS 1.000 $2,014,513.000 $1,500,000.000 $2,350,000.000 $2,600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 30.000 $8,000.000 $24,698.000 $71,500.000 $50,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 200.000 $42.000 $62.080 $54.000 $50.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 32.000 $130.000 $127.380 $105.000 $100.000
ROCK FILTER DAMS (REMOVE)
LF 232.000 $20.500 $36.700 $26.000 $30.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $30.500 $47.130 $40.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $7.750 $43.530 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 11,268.000 $5.600 $5.750 $4.600 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,268.000 $1.200 $2.720 $1.000 $1.500
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 3,060.000 $5.000 $8.160 $9.100 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,060.000 $2.000 $1.960 $1.000 $1.000
CONSTRUCTING DETOURS (EBSS)
SY 3,172.000 $20.000 $25.990 $16.000 $100.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 24.000 $6,000.000 $4,514.400 $5,000.000 $3,200.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 3,270.000 $30.000 $105.710 $90.000 $70.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 3,270.000 $15.000 $20.900 $30.000 $25.000
DRIVEWAYS (SURF TREAT)
SY 3,686.000 $50.000 $121.350 $80.000 $70.000
RUMBLE STRIPS (SHOULDER)
LF 125,511.000 $0.250 $0.110 $0.270 $0.300
RUMBLE STRIPS (CENTERLINE)
LF 61,568.000 $0.250 $0.110 $0.370 $0.400
MTL W-BEAM GD FEN (STEEL POST)
LF 2,200.000 $35.000 $37.130 $32.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,300.000 $3,867.010 $2,400.000 $2,800.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 506.000 $72.000 $60.500 $90.000 $55.000
REMOVE METAL BEAM GUARD FENCE
LF 2,500.000 $3.610 $3.300 $2.100 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 28.000 $3,100.000 $3,685.000 $3,200.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 20.000 $250.000 $330.000 $280.000 $300.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $870.000 $1,585.240 $1,200.000 $1,250.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $10,000.000 $13,188.640 $11,000.000 $7,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $800.000 $935.000 $940.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $700.000 $1,045.000 $1,100.000 $950.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $1,100.000 $687.500 $690.000 $625.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 47.000 $45.000 $33.000 $25.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 22.000 $30.000 $33.000 $26.000 $30.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 3,139.000 $1.000 $1.650 $1.000 $1.500
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 96.000 $5.000 $12.100 $12.000 $11.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 1,960.000 $1.000 $1.930 $2.000 $1.750
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $10.000 $27.500 $28.000 $25.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 3,840.000 $1.000 $1.930 $2.000 $1.750
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 120.000 $5.500 $10.450 $1.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,941.000 $1.630 $6.390 $1.000 $2.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 5,161.000 $1.000 $0.610 $0.620 $0.550
REFL PAV MRK TY II (Y) 6" (SLD)
LF 8,170.000 $1.000 $0.610 $0.620 $0.550
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 214.000 $0.750 $5.500 $5.600 $5.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 134,486.000 $0.750 $0.690 $0.700 $0.630
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 3,227.000 $0.750 $0.830 $0.850 $0.750
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 43,253.000 $0.750 $0.690 $0.700 $0.630
RE PM W/RET REQ TY II (W) 6" (BRK)
LF 214.000 $0.250 $5.500 $5.600 $5.000
RE PM W/RET REQ TY II (W) 6" (SLD)
LF 129,325.000 $0.250 $0.250 $0.300 $0.230
RE PM W/RET REQ TY II (Y) 6" (BRK)
LF 3,227.000 $0.250 $0.550 $0.850 $0.500
RE PM W/RET REQ TY II (Y) 6" (SLD)
LF 35,083.000 $0.250 $0.240 $0.250 $0.220
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 292.000 $2.100 $22.000 $25.000 $20.000
PREFAB PAV MRK TY B (W)(36")(YLD TRI)
EA 14.000 $35.000 $110.000 $105.000 $100.000
REFL PAV MRKR TY I-C
EA 11.000 $6.150 $22.000 $25.000 $20.000
REFL PAV MRKR TY II-A-A
EA 926.000 $3.680 $4.950 $5.000 $4.500
ELIM EXT PAV MRK & MRKS (4")
LF 4,439.000 $1.000 $1.710 $1.700 $1.550
PAV SURF PREP FOR MRK (6")
LF 8,886.000 $1.000 $0.830 $0.850 $0.750
FULL - WIDTH MOWING
AC 229.000 $45.000 $150.660 $145.000 $75.000
LITTER REMOVAL
AC 229.000 $100.000 $122.390 $60.000 $50.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 146,084.000 $15.000 $2.700 $2.000 $1.000
SP MIXES SP-C SAC-B PG70-22
TON 46,274.000 $145.000 $142.040 $146.000 $140.000
TACK COAT
GAL 27,277.000 $5.000 $6.430 $5.000 $6.000
CEMENT
TON 1,188.000 $388.000 $424.570 $250.000 $300.000
ASPHALT BINDER (PG 64-22)
TON 3,091.000 $1,250.370 $911.560 $800.000 $725.000
FOAMED ASPHALT TREAT (8") (DC)
SY 304,663.000 $4.800 $5.500 $6.800 $10.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $500.000 $550.000 $600.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 852.000 $70.000 $142.570 $100.000 $90.000
TMA (STATIONARY)
DAY 344.000 $155.000 $250.000 $200.000 $320.000
TMA (MOBILE OPERATION)
DAY 308.000 $155.000 $250.000 $10.000 $950.000
Totals: $22,151,442.770 $21,350,244.520 $23,896,190.280 $26,586,451.030