Show Job Controls
Bid Cobra

ROCKWALL SH 205 (0451-04-026)

Items: 66

County: ROCKWALL
Length: 3.2940 MILES
Highway: SH 205
District: DALLAS
Control Number: 0451-04-026
DBE Goal: 6.0%
Project: F 2025(013)
Guaranty: $93,000.00
Time: 86 WORKING DAYS
Engineer's Estimate: $4,628,600.70
Date: 09/05/2024 (1 year ago)
Contract Number: 9243018
Type: PREVENTIVE MAINTENANCE
Project ID: A00196060
Project Description: BASE REPAIR, MILL AND INLAY, AND PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
LANE SELMAN
NICHOLAS WADLINGTON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$4,628,600.70
$4,169,539.20
Over/Under Est: -9.92% -$459,061.50
Over/Under Est: -8.07% -$373,676.29
Amt Left: 2.05% $85,385.21
Over/Under Est: -1.46% -$67,467.12
Amt Left: 9.39% $391,594.38
Delta: -7.20% -$306,209.17
Over/Under Est: -0.08% -$3,914.41
Amt Left: 10.92% $455,147.09
Delta: -1.39% -$63,552.71
$5,722,988.35
Over/Under Est: 23.64% $1,094,387.65
Amt Left: 37.26% $1,553,449.15
Delta: -23.75% -$1,098,302.06
Subcontractor Percentage Amount
DUSTROL, INC. 6.32% $265,565.20
FORTSON CONTRACTING, INC. 4.03% $169,339.84
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 3.65% $153,372.31
TRP CONSTRUCTION GROUP, LLC 3.61% $151,691.51
JR WEST TEXAS CONCRETE LLC 2.30% $96,645.56
MARCOMS CONSTRUCTION LLC 1.01% $42,440.01
COLD CREEK CONSTRUCTION, LTD 0.71% $29,834.07
TEXAS TRAFFIC AND BARRICADE, LLC 0.31% $13,026.14
ABESCAPE GROUP LLC 0.06% $2,521.19
Total: 22.00% $924,435.83

Bid Items & Bid Tabulations

66 Total 0 of 66
ROCKWALL  |  SH 205  |  DALLAS  |  0451-04-026  |  09/05/2024  |  $4,628,600.70  |  F 2025(013)  |  PREVENT MAINT  |  86 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
FOUTSCO PAVING COMPANY, LLC
PEACHTREE CONSTRUCTION, LTD.
AUSTIN BRIDGE & ROAD SERVICES, LP
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 173.940 $2,000.000 $700.000 $750.000 $1,150.000 $2,658.780 $2,840.000
BACKFILL (TY A OR B)
STA 172.590 $300.000 $300.000 $400.000 $600.000 $226.650 $450.000
FURN & PLACE TOPSOIL (4")
SY 16,379.000 $1.000 $1.050 $1.000 $7.500 $7.220 $10.000
BLOCK SODDING
SY 16,379.000 $4.000 $5.000 $4.000 $6.100 $7.930 $10.000
DRILL SEED (TEMP_WARM_COOL)
SY 5,461.000 $0.250 $0.350 $0.010 $0.720 $2.780 $2.000
VEGETATIVE WATERING
TGL 3,258.000 $8.000 $0.100 $0.010 $15.000 $0.750 $25.000
SP MIXES SP-C SAC-B PG70-22
TON 10,542.000 $150.000 $151.000 $162.000 $164.400 $134.250 $170.000
TACK COAT
GAL 10,542.000 $3.750 $4.500 $0.010 $1.000 $0.250 $10.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 9,484.000 $100.000 $82.000 $85.000 $87.500 $79.180 $85.000
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 94,825.000 $3.000 $2.730 $1.700 $2.850 $2.350 $6.000
RIPRAP (MOW STRIP)(4 IN)
CY 142.000 $700.000 $700.000 $900.000 $725.000 $1,167.710 $550.000
MOBILIZATION
LS 1.000 $409,860.000 $410,296.000 $420,000.000 $410,000.000 $508,715.540 $550,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $20,000.000 $25,000.000 $60,000.000 $20,000.000 $50,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $7,500.000 $8,000.000 $15,000.000 $15,500.000 $7,500.000 $16,500.000
TMA (STATIONARY)
DAY 86.000 $275.000 $900.000 $0.010 $125.000 $433.000 $250.000
TMA (MOBILE OPERATION)
DAY 15.000 $350.000 $0.100 $0.010 $250.000 $866.000 $550.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $30.000 $63.000 $50.000 $79.400 $79.400 $50.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $12.000 $24.000 $10.000 $50.000 $50.000 $30.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,788.000 $3.000 $4.550 $1.000 $2.940 $2.940 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,788.000 $1.000 $1.530 $0.100 $1.950 $1.950 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,995.000 $5.000 $6.650 $1.000 $5.250 $5.250 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,995.000 $1.000 $1.550 $0.100 $1.850 $1.850 $9.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,892.000 $22.000 $27.000 $22.000 $24.900 $22.500 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $2,100.000 $1,700.000 $2,000.000 $1,310.000 $2,180.900 $1,850.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 8.000 $100.000 $95.000 $190.000 $86.500 $80.000 $50.000
MTL BM GD FEN TRANS (31"-28")
EA 1.000 $600.000 $615.000 $1,415.000 $610.000 $562.500 $2,500.000
TL-2 31" SHORT RADIUS (COMPLETE)
EA 1.000 $20,000.000 $28,000.000 $16,000.000 $31,000.000 $28,000.000 $25,000.000
REMOVE METAL BEAM GUARD FENCE
LF 2,975.000 $3.000 $2.850 $2.000 $2.700 $2.500 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $200.000 $145.000 $200.000 $134.000 $125.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $250.000 $285.000 $200.000 $272.000 $250.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $3,000.000 $3,350.000 $3,000.000 $3,100.000 $2,877.500 $3,250.000
GUARDRAIL END TREATMENT (REMOVE)
EA 18.000 $215.000 $285.000 $200.000 $272.000 $250.000 $1,500.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 22.500 $50.000 $34.000 $30.000 $30.000 $30.000 $50.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 48.000 $640.000 $700.000 $625.000 $650.000 $625.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $845.000 $785.000 $700.000 $725.000 $700.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,500.000 $895.000 $800.000 $825.000 $800.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,325.000 $995.000 $900.000 $925.000 $900.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 3.000 $1,500.000 $1,050.000 $950.000 $975.000 $950.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 4.000 $15.000 $22.000 $20.000 $20.500 $20.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 56.000 $30.000 $27.000 $25.000 $26.000 $25.000 $100.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 19.000 $120.000 $49.000 $60.000 $63.000 $60.000 $100.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 32,961.000 $1.250 $0.420 $0.320 $0.400 $0.410 $0.750
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 5,540.000 $1.250 $0.750 $0.590 $0.700 $0.730 $1.250
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 1,447.000 $2.000 $7.820 $4.000 $7.500 $7.650 $6.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 45,387.000 $2.000 $0.420 $0.300 $0.400 $0.410 $0.750
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 280.000 $1.500 $1.150 $1.000 $3.000 $0.500 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,740.000 $1.500 $1.150 $1.000 $3.000 $0.500 $6.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,540.000 $3.000 $1.100 $0.850 $1.100 $1.000 $1.350
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,447.000 $10.000 $8.400 $6.500 $8.400 $7.650 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 51.000 $250.000 $162.000 $150.000 $165.000 $150.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 47.000 $250.000 $196.000 $180.000 $199.000 $181.000 $250.000
PAVEMENT SLER 6"
LF 571.000 $2.000 $0.200 $1.000 $0.210 $0.190 $1.250
PAVEMENT SLER 8"
LF 54.000 $2.000 $0.280 $0.600 $0.300 $0.270 $2.250
PAVEMENT SLER 24"
LF 818.000 $2.000 $1.680 $1.000 $1.700 $1.550 $6.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 32,961.000 $1.200 $0.710 $0.600 $0.720 $0.660 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 45,387.000 $1.500 $0.710 $0.590 $0.720 $0.660 $1.000
REFL PAV MRKR TY I-C
EA 280.000 $5.000 $4.100 $4.000 $4.200 $3.850 $7.000
REFL PAV MRKR TY II-A-A
EA 1,798.000 $5.000 $4.750 $3.880 $4.900 $4.450 $7.000
ELIM EXT PM & MRKS (4")
LF 571.000 $1.500 $0.420 $1.000 $0.420 $0.390 $3.000
ELIM EXT PM & MRKS (8")
LF 54.000 $2.000 $0.810 $1.600 $0.820 $0.750 $3.000
ELIM EXT PM & MRKS (12")
LF 503.000 $2.000 $5.000 $2.000 $5.100 $4.700 $4.000
ELIM EXT PM & MRKS (24")
LF 1,038.000 $3.500 $6.450 $3.500 $6.700 $6.250 $6.000
PAV SURF PREP FOR MRK (6")
LF 571.000 $1.500 $0.042 $0.200 $0.040 $0.040 $3.000
PAV SURF PREP FOR MRK (8")
LF 54.000 $1.500 $0.120 $0.400 $0.120 $0.110 $3.000
PAV SURF PREP FOR MRK (24")
LF 818.000 $2.000 $0.600 $0.750 $0.600 $0.550 $6.000
FULL - WIDTH MOWING
CYC 1.000 $5,500.000 $2,600.000 $4,000.000 $5,700.000 $5,000.000 $5,000.000
Totals: $4,628,600.700 $4,169,539.202 $4,254,924.410 $4,561,133.580 $4,624,686.297 $5,722,988.350