Job Info for 0648-01-037

County: ROBERTSON Highway: FM 50 Date: 04/07/2022 (2 years ago) Engineer's Estimate: $471,340 Control Number: 0648-01-037
Project: BR 2022(453) District: BRYAN Time: 97 WORKING DAYS Type: BRIDGE MAINTENANCE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $471,340.00
BECK-REIT & SONS, LTD.   $458,096.50 1
-2.81% | -$13,243.50
BOEN LANDSCAPING & IRRIGATION, LLC   $585,445.00 2
24.21% | $114,105.00
27.8% | $127,348.50
FNH CONSTRUCTION, LLC   $799,685.00 3
69.66% | $328,345.00
74.57% | $341,588.50
36.59% | $214,240.00
FORDE CONSTRUCTION COMPANY, INC.   $839,157.00 4
78.04% | $367,817.00
83.18% | $381,060.50
4.94% | $39,472.00

Bid Items

Items: 18, 0 filtered
ROBERTSON FM 50  |  BRYAN  |  0648-01-037  |  04/07/2022  |  $471,340  |  BR 2022(453)  |  BRIDGE MAINT  |  97 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BECK-REIT & SONS, LTD. BOEN LANDSCAPING & IRRIGATION, LLC FNH CONSTRUCTION, LLC FORDE CONSTRUCTION COMPANY, INC.
104 6009 REMOVING CONC (RIPRAP) SY 88.000 $30.000 $100.000 $140.000 $50.000 $130.000
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 277.000 $40.000 $50.000 $60.000 $50.000 $95.000
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 1,400.000 $2.500 $0.500 $5.000 $2.000 $1.200
164 6009 BROADCAST SEED (TEMP) (WARM) SY 700.000 $0.750 $0.200 $4.000 $2.000 $1.200
164 6011 BROADCAST SEED (TEMP) (COOL) SY 700.000 $0.650 $0.200 $4.000 $2.000 $1.200
168 6001 VEGETATIVE WATERING MG 14.000 $40.000 $100.000 $200.000 $1,000.000 $600.000
401 6001 FLOWABLE BACKFILL CY 30.000 $200.000 $255.000 $600.000 $350.000 $1,025.000
403 6006 TEMPORARY SPL SHORING (COFFERDAM) SF 2,249.000 $50.000 $1.000 $5.000 $75.000 $5.000
420 6158 CL C CONC(PILE ENCASEMENT) LF 204.500 $350.000 $755.000 $480.000 $850.000 $600.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 12.000 $130.000 $300.000 $240.000 $100.000 $440.000
432 6002 RIPRAP (CONC)(5 IN) CY 51.000 $420.000 $800.000 $1,100.000 $650.000 $1,235.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 411.000 $175.000 $155.000 $240.000 $185.000 $297.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 586.000 $150.000 $155.000 $280.000 $250.000 $280.000
500 6001 MOBILIZATION LS 1.000 $50,000.000 $60,000.000 $50,000.000 $79,500.000 $85,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $2,500.000 $1,000.000 $4,500.000 $8,500.000 $20,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 700.000 $4.000 $3.000 $5.000 $4.000 $3.800
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 700.000 $1.000 $1.000 $2.000 $2.000 $1.250
6185 6002 TMA (STATIONARY) DAY 35.000 $250.000 $1.000 $160.000 $250.000 $1,200.000
Totals: $471,340.00 $458,096.50 $585,445.00 $799,685.00 $839,157.00