County: ROBERTSON Highway: SH 14 Date: 10/04/2017 (7 years ago) Engineer's Estimate: $1,317,446 Control Number: 0049-15-013
Project: STP 2018(131)HES District: BRYAN Time: 93 WORKING DAYS Type: TEXTURIZE SHOULDERS AND CENTERLINE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,317,446.02
STRIPE-A-ZONE, INC.   $918,845.69 1
-30.26% | -$398,600.33
D. I. J. CONSTRUCTION, INC.   $934,894.83 2
-29.04% | -$382,551.19
1.75% | $16,049.14
TOTAL HIGHWAY MAINTENANCE, LLC   $1,024,404.41 3
-22.24% | -$293,041.61
11.49% | $105,558.72
9.57% | $89,509.58
L&L COMPANY   $1,079,202.28 4
-18.08% | -$238,243.74
17.45% | $160,356.59
5.35% | $54,797.87
BATTERSON, LLP   $1,093,479.57 5
-17% | -$223,966.45
19.01% | $174,633.88
1.32% | $14,277.29
TRP CONSTRUCTION GROUP, LLC   $1,134,976.84 6
-13.85% | -$182,469.18
23.52% | $216,131.15
3.79% | $41,497.27

Bid Items

Items: 12, 0 filtered
ROBERTSON SH 14  |  BRYAN  |  0049-15-013  |  10/04/2017  |  $1,317,446  |  STP 2018(131)HES  |  TEXTURIZE SHOULDERS AND CENTERLINE  |  93 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, INC. D. I. J. CONSTRUCTION, INC. TOTAL HIGHWAY MAINTENANCE, LLC L&L COMPANY BATTERSON, LLP TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $135,000.000 $1.000 $9,500.000 $37,000.000 $1.000 $14,800.000 $55,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $2,500.000 $1.000 $100.000 $1,700.000 $1.000 $1,300.000 $1,000.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 1,028,196.000 $0.150 $0.115 $0.115 $0.120 $0.140 $0.160 $0.090
533 6002 RUMBLE STRIPS (CENTERLINE) LF 601,910.000 $0.190 $0.145 $0.150 $0.140 $0.160 $0.180 $0.250
666 6282 REF PROF PAV MRK TY I(W)4"(SLD)(060MIL) LF 588,339.000 $0.480 $0.350 $0.390 $0.450 $0.500 $0.430 $0.440
666 6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL) LF 243,154.000 $0.500 $0.400 $0.460 $0.450 $0.600 $0.450 $0.600
666 6291 REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL) LF 50,011.000 $0.550 $0.400 $0.500 $0.500 $0.600 $0.450 $1.000
666 6301 RE PM W/RET REQ TY I (W)4"(SLD)(060MIL) LF 261,847.000 $0.200 $0.175 $0.160 $0.180 $0.180 $0.190 $0.170
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 212,937.000 $0.350 $0.300 $0.230 $0.280 $0.220 $0.240 $0.270
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 683,762.000 $0.300 $0.265 $0.230 $0.260 $0.220 $0.240 $0.230
672 6009 REFL PAV MRKR TY II-A-A EA 21,749.000 $3.000 $2.500 $2.200 $2.400 $2.500 $2.300 $2.430
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 14,019.000 $5.000 $3.200 $3.850 $2.400 $5.000 $7.000 $4.570
Totals: $1,317,446.02 $918,845.70 $934,894.83 $1,024,404.41 $1,079,202.28 $1,093,479.57 $1,134,976.84