County: ROBERTSON Highway: FM 46 Date: 10/01/2020 (4 years ago) Engineer's Estimate: $11,411,211 Control Number: 0049-14-013
Project: STP 2021(066) District: BRYAN Time: 112 WORKING DAYS Type: SEAL COAT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $11,411,210.54
D. I. J. CONSTRUCTION, INC.   $9,071,397.84 1
-20.5% | -$2,339,812.70
F. N. PLOCH CONSTRUCTION COMPANY, INC.   $9,403,942.65 2
-17.59% | -$2,007,267.89
3.67% | $332,544.81
BRANNAN PAVING CO., LTD.   $9,994,189.84 3
-12.42% | -$1,417,020.70
10.17% | $922,792.00
6.28% | $590,247.19
CLARK CONSTRUCTION OF TEXAS, INC.   $10,167,704.24 4
-10.9% | -$1,243,506.30
12.09% | $1,096,306.40
1.74% | $173,514.40
RONALD R. WAGNER & CO., LP   $12,677,858.04 5
11.1% | $1,266,647.50
39.76% | $3,606,460.20
24.69% | $2,510,153.80

Bid Items

Items: 29, 0 filtered
ROBERTSON FM 46  |  BRYAN  |  0049-14-013  |  10/01/2020  |  $11,411,211  |  STP 2021(066)  |  SEAL COAT  |  112 WORKING DAYS
Alt Item code Description Unit Quantity Engineer's Estimate D. I. J. CONSTRUCTION, INC. F. N. PLOCH CONSTRUCTION COMPANY, INC. BRANNAN PAVING CO., LTD. CLARK CONSTRUCTION OF TEXAS, INC. RONALD R. WAGNER & CO., LP
316 6017 ASPH (AC-20-5TR) GAL 1,750,378.000 $2.950 $2.350 $2.300 $2.270 $2.750 $3.350
316 6157 AGGR(TY-PL GR-3LW SAC-A) CY 2,873.000 $100.000 $0.000 $0.000 $0.000 $0.000 $0.000
316 6404 AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A) CY 33,672.000 $105.000 $92.000 $89.000 $99.830 $92.000 $101.480
500 6001 MOBILIZATION LS 1.000 $750,000.000 $470,000.000 $850,000.000 $1,291,700.000 $750,000.000 $1,380,755.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $10,000.000 $16,500.000 $7,500.000 $15,000.000 $7,500.000 $32,464.000
530 6003 INTERSECTIONS (SURF TREAT) SY 37,497.000 $2.660 $1.500 $1.850 $1.500 $2.750 $2.000
530 6006 DRIVEWAYS (SURF TREAT) SY 46,953.000 $2.380 $0.900 $1.850 $1.000 $2.750 $2.000
530 6009 TURNOUTS (SURF TREAT) SY 31,715.000 $3.030 $0.900 $1.850 $0.500 $2.750 $2.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 757.000 $0.730 $0.010 $1.000 $0.010 $0.010 $1.500
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 162,046.000 $0.730 $0.010 $1.000 $0.010 $0.010 $1.500
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 8,688.000 $0.950 $1.600 $2.650 $2.650 $2.650 $2.650
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 4,261.000 $6.900 $6.850 $5.700 $5.700 $5.700 $5.700
666 6102 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 16.000 $3.030 $30.000 $36.600 $36.600 $36.600 $36.600
666 6167 REFL PAV MRK TY II (W) 4" (BRK) LF 31.000 $0.170 $1.000 $0.250 $0.250 $0.250 $0.250
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 2,760,724.000 $0.120 $0.100 $0.100 $0.100 $0.100 $0.100
666 6205 REFL PAV MRK TY II (Y) 4" (BRK) LF 228,332.000 $0.130 $0.120 $0.120 $0.120 $0.120 $0.120
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 1,868,982.000 $0.120 $0.110 $0.100 $0.100 $0.105 $0.105
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 15.000 $232.000 $200.000 $245.750 $245.750 $245.750 $245.750
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 3.000 $415.000 $350.000 $395.250 $395.250 $395.250 $395.250
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 47.000 $312.000 $275.000 $350.400 $350.400 $350.400 $350.400
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 15.000 $700.000 $600.000 $900.000 $900.000 $900.000 $900.000
672 6007 REFL PAV MRKR TY I-C EA 439.000 $3.370 $2.500 $2.600 $2.600 $2.600 $2.600
672 6009 REFL PAV MRKR TY II-A-A EA 34,914.000 $3.170 $2.600 $2.600 $2.600 $2.600 $2.600
672 6010 REFL PAV MRKR TY II-C-R EA 439.000 $3.000 $2.500 $2.600 $2.600 $2.600 $2.600
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 937,782.000 $0.350 $0.250 $0.205 $0.205 $0.220 $0.220
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 280.000 $27.000 $20.000 $20.000 $20.000 $20.000 $20.000
6185 6002 TMA (STATIONARY) DAY 64.000 $300.000 $10.000 $1.000 $120.000 $0.010 $500.000
6185 6005 TMA (MOBILE OPERATION) DAY 268.000 $250.000 $1.000 $1.000 $50.000 $0.010 $500.000
1 316 6124 AGGR(TY-PB GR-3 SAC-A) CY 2,873.000 $100.000 $87.000 $85.000 $94.630 $88.000 $101.480
Totals: $11,698,510.54 $9,071,397.84 $9,403,942.65 $9,994,189.84 $10,167,704.24 $12,677,858.04