REEVES FM 1450 (1639-01-016)

Items: 121

County: REEVES
Length: N/A
Highway: FM 1450
District: ODESSA
Control Number: 1639-01-016
DBE Goal: N/A
Project: F 2023(524)
Guaranty: N/A
Time: 420 WORKING DAYS
Engineer's Estimate: $56,173,945.25
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
PRELETTINGQUESTIONS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$56,173,945.25
$81,336,501.64
Over/Under Est: 44.79% $25,162,556.39
Over/Under Est: 71.57% $40,206,014.18
Amt Left: 18.5% $15,043,457.79
Subcontractor Percentage Amount
WILD WEST TRUCKING, LLC 1.64% $1,317,384.59
A.L. CONSTRUCTION LLC 1.01% $811,316.12
DOUBLE A CONTRACTING, L.P. 0.77% $618,528.13
WILLIS ELECTRIC CO., LP 0.48% $385,575.98
A BROTHERS MILLING, LLC 0.18% $144,590.99
MARCOM'S MOWING SERVICE, LLC 0.18% $144,590.99
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 0.17% $136,558.16
FC TRAFFIC CONTROL, INC. 0.17% $136,558.16
HJC FARMS, INC. 0.02% $16,065.67
Total: 4.62% $3,711,168.79

Bid Items & Bid Tabulations

121 Total 0 of 121
REEVES  |  FM 1450  |  ODESSA  |  1639-01-016  |  03/07/2023  |  $56,173,945.25  |  F 2023(524)  |  ROADWAY REHAB  |  420 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
REMOVING CONC (RIPRAP)
SY 4,409.000 $15.000 $26.000 $17.270
REMOVING CONC (DRIVEWAYS)
SY 229.000 $35.000 $30.000 $34.770
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 26,035.000 $6.000 $10.000 $4.450
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 4,244.000 $6.000 $12.000 $11.290
REMOVING STAB BASE AND ASPH PAV(7"-10")
SY 27,857.000 $3.900 $12.000 $10.100
REMOVING STAB BASE AND ASPH PAV(4"-16")
SY 126,446.000 $5.500 $4.000 $6.000
EXCAVATION (ROADWAY)
CY 110,592.000 $13.000 $15.000 $11.650
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 256,881.000 $20.000 $34.000 $27.300
BLADING
HR 100.000 $170.000 $400.000 $326.220
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 667,809.000 $0.150 $0.200 $0.190
PROOF ROLLING
HR 100.000 $110.000 $105.000 $244.590
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 332,667.000 $12.000 $18.000 $13.930
PRIME COAT (AE-P)
GAL 102,988.000 $3.500 $5.000 $6.330
PRIME COAT (CSS-1H)
GAL 2,807.000 $3.500 $5.000 $6.130
PLANE ASPH CONC PAV(0" TO 2")
SY 189,248.000 $2.000 $2.200 $2.770
CONC PVMT (CONT REINF - CRCP) (6")
SY 320.000 $200.000 $190.000 $147.000
CEM STABIL BKFL
CY 1,302.000 $250.000 $325.000 $282.490
TEMPORARY SPL SHORING
SF 62,773.000 $14.000 $25.000 $30.890
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 120.000 $275.000 $385.000 $433.110
CL A CONC (CHANNEL LINING)
CY 10,543.000 $325.000 $600.000 $791.970
RIPRAP (CONC)(5 IN)
CY 35.000 $600.000 $885.000 $866.220
CONC BOX CULV (5 FT X 2 FT)
LF 378.000 $750.000 $461.000 $989.970
CONC BOX CULV (5 FT X 3 FT)
LF 1,358.000 $500.000 $485.000 $1,051.840
CONC BOX CULV (6 FT X 3 FT)
LF 814.000 $725.000 $550.000 $1,144.650
CONC BOX CULV (8 FT X 4 FT)
LF 2,107.000 $950.000 $934.000 $1,856.190
CONC BOX CULV (6 FT X 2 FT)
LF 2,017.000 $530.000 $535.000 $1,237.460
RC PIPE (CL III)(24 IN)
LF 901.000 $95.000 $129.000 $173.240
RC PIPE (CL III)(36 IN)
LF 234.000 $250.000 $190.000 $321.740
RC PIPE (CL IV)(24 IN)
LF 675.000 $150.000 $124.000 $204.180
RC PIPE (CL IV)(30 IN)
LF 532.000 $180.000 $182.000 $272.240
RC PIPE (CL IV)(36 IN)
LF 222.000 $300.000 $225.000 $352.680
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 12.000 $9,300.000 $9,750.000 $11,137.130
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
EA 16.000 $12,000.000 $10,900.000 $13,612.040
SET (TY I)(S= 5 FT)(HW= 5 FT)(4:1) (C)
EA 6.000 $9,000.000 $11,500.000 $15,468.230
SET (TY I)(S= 5 FT)(HW= 6 FT)(3:1) (C)
EA 26.000 $13,500.000 $10,780.000 $16,705.690
SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C)
EA 42.000 $8,677.000 $10,930.000 $18,561.880
SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C)
EA 38.000 $12,500.000 $11,095.000 $19,799.330
SET (TY I)(S= 8 FT)(HW= 6 FT)(3:1) (C)
EA 58.000 $18,550.000 $12,650.000 $22,274.250
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 64.000 $1,200.000 $2,700.000 $1,484.950
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 6.000 $1,750.000 $2,600.000 $2,227.430
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 16.000 $1,650.000 $3,150.000 $2,227.430
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 18.000 $1,875.000 $3,175.000 $2,474.920
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 14.000 $2,500.000 $3,850.000 $3,712.380
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 9.000 $3,500.000 $5,360.000 $4,331.100
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 3.000 $7,000.000 $7,785.000 $4,331.100
REMOV STR (SET)
EA 16.000 $1,500.000 $850.000 $1,484.950
REMOV STR (HEADWALL)
EA 2.000 $1,100.000 $2,000.000 $3,093.650
REMOV STR (BOX CULVERT)
LF 54.000 $70.000 $81.000 $494.980
REMOV STR (PIPE)
EA 8.000 $500.000 $1,980.000 $3,093.650
MOBILIZATION
LS 1.000 $700,000.000 $8,100,000.000 $16,759,207.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $15,000.000 $40,000.000 $150,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 2,361.000 $33.000 $20.000 $66.250
CONSTRUCTION EXITS (REMOVE)
SY 2,361.000 $9.500 $3.000 $16.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 138.000 $2.650 $7.000 $11.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 138.000 $0.800 $1.200 $3.180
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 5,104.000 $5.200 $7.000 $7.610
BIODEG EROSN CONT LOGS (REMOVE)
LF 5,104.000 $2.200 $1.500 $1.600
CONSTRUCTING DETOURS
SY 27,857.000 $80.000 $65.000 $60.570
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 3,696.000 $90.000 $120.000 $54.410
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
DAY 462.000 $315.000 $550.000 $687.880
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 37,830.000 $45.000 $65.000 $60.000
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 36,323.000 $10.000 $15.000 $2.880
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 36,998.000 $10.000 $15.000 $1.470
DRIVEWAYS (CONC)
SY 320.000 $90.000 $133.990 $142.000
DRIVEWAYS (ACP)
SY 14,035.000 $52.000 $59.040 $44.000
RUMBLE STRIPS (SHOULDER)
LF 178,380.000 $0.220 $0.220 $0.070
RUMBLE STRIPS (CENTERLINE)
LF 154,510.000 $0.200 $0.240 $0.070
CRASH CUSH ATTEN (MOVE & RESET)
EA 32.000 $1,475.000 $3,000.000 $4,331.100
CRASH CUSH ATTEN (REMOVE)
EA 33.000 $920.000 $3,000.000 $2,474.920
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 33.000 $35,000.000 $15,000.000 $9,280.940
IN RD IL (TY SA) 50T-12 (400W EQ) LED
EA 12.000 $6,500.000 $7,810.000 $8,785.950
IN RD IL (TY AL) 50T-12 (400W EQ) LED
EA 12.000 $400.000 $7,810.000 $8,785.950
CONDT (PVC) (SCH 80) (2")
LF 1,120.000 $11.000 $11.000 $12.370
CONDT (PVC) (SCH 80) (2") (BORE)
LF 410.000 $30.000 $33.000 $37.120
ELEC CONDR (NO.6) BARE
LF 1,530.000 $2.500 $2.480 $2.780
ELEC CONDR (NO.6) INSULATED
LF 3,060.000 $2.500 $2.750 $3.090
GROUND BOX TY A (122311)W/APRON
EA 10.000 $1,700.000 $1,980.000 $2,227.430
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 2.000 $11,000.000 $9,900.000 $11,137.130
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 32.000 $775.000 $742.500 $1,175.590
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $925.000 $797.500 $1,361.200
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $3,000.000 $1,375.000 $1,454.010
IN SM RD SN SUP&AM TYFRP(1)UB(P)
EA 1.000 $90.000 $1,375.000 $235.120
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $1,100.000 $1,375.000 $1,577.760
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 4.000 $1,100.000 $1,375.000 $1,763.380
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 5.000 $1,200.000 $1,375.000 $1,800.500
REMOVE SM RD SN SUP&AM
EA 75.000 $175.000 $192.500 $136.120
INSTL OM ASSM (OM-2X)(WC)GND
EA 3.000 $65.000 $84.700 $185.620
REMOVE DELIN & OBJECT MARKER ASSMS
EA 5.000 $80.000 $26.400 $18.560
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 47.000 $80.000 $92.400 $185.620
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 36.000 $90.000 $107.800 $185.620
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 169,490.000 $0.200 $0.280 $0.310
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 339,064.000 $0.800 $0.580 $0.890
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 834.000 $1.250 $2.310 $1.670
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 18,238.000 $0.700 $0.870 $0.930
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 456.000 $1.250 $1.100 $1.240
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 10,250.000 $1.150 $1.100 $1.240
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 182,970.000 $0.680 $0.730 $0.820
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 14,870.000 $0.750 $0.730 $0.820
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 124,560.000 $0.750 $0.730 $0.820
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 98.000 $35.000 $27.500 $30.940
PREFAB PAV MRK TY B (W)(ARROW)
EA 23.000 $650.000 $412.500 $464.050
PREFAB PAV MRK TY B (W)(WORD)
EA 23.000 $800.000 $467.500 $525.920
PREFAB PAV MRK TY B (W)(36")(YLD TRI)
EA 34.000 $57.200 $93.500 $105.180
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 98.000 $19.000 $16.500 $18.560
PREFAB PAV MRK TY C (W) (ARROW)
EA 20.000 $255.000 $236.500 $266.050
PREFAB PAV MRK TY C (W) (WORD)
EA 23.000 $350.000 $291.500 $327.930
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 24.000 $28.000 $42.900 $48.260
REFL PAV MRKR TY I-C
EA 452.000 $4.250 $4.400 $4.950
REFL PAV MRKR TY II-A-A
EA 4,170.000 $3.500 $4.400 $4.950
ELIM EXT PAV MRK & MRKS (4")
LF 189,838.000 $0.500 $0.610 $0.680
ELIM EXT PAV MRK & MRKS (8")
LF 834.000 $0.900 $0.950 $1.060
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 6.000 $10,000.000 $13,750.000 $15,468.230
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 3.000 $750.000 $550.000 $618.730
SP MIXES SP-B SAC-B PG70-22
TON 115,504.000 $100.000 $155.000 $138.520
SP MIXES SP-C SAC-B PG70-22
TON 1,544.000 $120.000 $100.000 $302.000
STONE-MTRX-ASPH SMAR-F SAC-A
TON 56,643.000 $160.000 $170.000 $198.110
BONDING COURSE
GAL 102,988.000 $2.500 $4.460 $5.250
EMULSION
GAL 95,264.000 $2.250 $4.290 $3.750
TMA (MOBILE OPERATION)
HR 260.000 $160.000 $97.190 $117.640
1
RC PIPE (CL III)(18 IN)
LF 2,827.000 $110.000 $82.000 $80.430
1A
THERMO PIPE(24")(PP)(TY D)(TY II)
LF 2,827.000 $110.000 $0.000 $0.000
Totals: $56,484,915.250 $81,336,501.640 $96,379,959.430