Job Info for 0904-00-183

County: POTTER Highway: VA Date: 05/08/2019 (5 years ago) Engineer's Estimate: $2,144,554 Control Number: 0904-00-183
Project: STP 2019(917) District: AMARILLO Time: 124 WORKING DAYS Type: CONSTRUCT CURB RAMPS AT VARIOUS LOCATIONS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,144,553.90
TI-ZACK CONCRETE, INC.   $1,985,312.90 1
-7.43% | -$159,241.00
ENCINO LANDSCAPE, INC.   $2,754,806.00 2
28.46% | $610,252.10
38.76% | $769,493.10
FNH CONSTRUCTION, LLC   $2,842,000.00 3
32.52% | $697,446.10
43.15% | $856,687.10
3.17% | $87,194.00

Bid Items

Items: 58, 0 filtered
POTTER VA  |  AMARILLO  |  0904-00-183  |  05/08/2019  |  $2,144,554  |  STP 2019(917)  |  CONSTRUCT CURB RAMPS AT VARIOUS LOCATIONS  |  124 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TI-ZACK CONCRETE, INC. ENCINO LANDSCAPE, INC. FNH CONSTRUCTION, LLC
104 6017 REMOVING CONC (DRIVEWAYS) SY 3,760.000 $15.000 $25.000 $20.000 $30.000
104 6029 REMOVING CONC (CURB OR CURB & GUTTER) LF 2,426.000 $6.000 $8.000 $10.000 $30.000
104 6036 REMOVING CONC (SIDEWALK OR RAMP) SY 30.000 $25.000 $15.000 $20.000 $30.000
105 6008 REMOVING STAB BASE AND ASPH PAV (6") SY 54.000 $10.000 $15.000 $20.000 $30.000
105 6037 REMOVING STAB BASE AND ASPH PAV(0"-16") SY 929.000 $8.000 $20.000 $20.000 $30.000
110 6003 EXCAVATION (SPECIAL) CY 100.000 $20.000 $1.000 $40.000 $30.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 350.000 $15.000 $1.000 $20.000 $35.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 3,500.000 $1.500 $2.000 $1.000 $8.000
162 6002 BLOCK SODDING SY 3,500.000 $8.500 $4.000 $7.000 $8.000
168 6001 VEGETATIVE WATERING MG 59.900 $21.000 $1.000 $10.000 $50.000
340 6110 D-GR HMA(SQ) TY-D PG64-28 TON 151.000 $200.000 $300.000 $300.000 $200.000
354 6023 PLANE ASPH CONC PAV(0" TO 4") SY 250.000 $16.000 $35.000 $9.000 $20.000
360 6032 CONC PAV (JOINT REINF) (10") SY 250.000 $85.000 $100.000 $200.000 $325.000
400 6009 CEMENT STAB BACKFILL (INLET OR MH) CY 20.000 $150.000 $100.000 $100.000 $350.000
420 6002 CL A CONC (MISC) CY 20.000 $895.000 $1,000.000 $700.000 $1,100.000
420 6007 CL A CONC (FLUME) CY 11.600 $700.000 $1,000.000 $700.000 $1,100.000
420 6074 CL C CONC (MISC) CY 14.400 $900.000 $1,000.000 $700.000 $1,200.000
432 6001 RIPRAP (CONC)(4 IN) CY 44.000 $450.000 $650.000 $500.000 $550.000
465 6233 INLET (COMP) (TY SIDEWALK BRIDGE) EA 4.000 $8,500.000 $1,000.000 $8,000.000 $8,000.000
471 6003 GRATE & FRAME EA 20.000 $2,100.000 $800.000 $800.000 $5,000.000
479 6001 ADJUSTING MANHOLES EA 3.000 $600.000 $150.000 $900.000 $1,500.000
479 6005 ADJUSTING MANHOLES (WATER VALVE BOX) EA 1.000 $600.000 $150.000 $600.000 $750.000
479 6008 ADJUSTING MANHOLES (WATER METER) EA 12.000 $800.000 $150.000 $600.000 $750.000
479 6011 ADJUSTING MANHOLES (IRRIGATION BOX) EA 1.000 $1,000.000 $150.000 $600.000 $750.000
500 6001 MOBILIZATION LS 1.000 $211,000.000 $100,000.000 $300,000.000 $265,000.000
502 6025 BARR, SIGNS, TRAFFIC HANDLING EA 4.000 $25,000.000 $1,000.000 $7,500.000 $8,500.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 1,000.000 $4.000 $0.100 $4.000 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,000.000 $1.000 $0.100 $1.000 $9.000
528 6006 REMOVE AND RELAY PAVERS SY 50.000 $100.000 $100.000 $100.000 $200.000
529 6001 CONC CURB (TY I) LF 274.000 $20.000 $40.000 $30.000 $25.000
529 6002 CONC CURB (TY II) LF 493.000 $20.000 $40.000 $35.000 $30.000
529 6008 CONC CURB & GUTTER (TY II) LF 2,760.000 $30.000 $40.000 $40.000 $35.000
529 6020 CONC CURB & GUTTER (ARMOR CURB) LF 39.000 $300.000 $150.000 $400.000 $150.000
529 6032 CONCRETE GUTTER (MODIFIED) LF 89.000 $200.000 $45.000 $40.000 $50.000
530 6004 DRIVEWAYS (CONC) SY 4,593.000 $80.000 $75.000 $80.000 $85.000
531 6001 CONC SIDEWALKS (4") SY 9,137.000 $55.000 $80.000 $80.000 $65.000
531 6003 CONC SIDEWALKS (6") SY 300.000 $90.000 $100.000 $80.000 $80.000
531 6018 CURB RAMPS (TY 1) SY 339.000 $125.000 $100.000 $150.000 $200.000
531 6019 CURB RAMPS (TY 2) SY 210.000 $125.000 $100.000 $150.000 $200.000
531 6020 CURB RAMPS (TY 3) SY 416.000 $125.000 $100.000 $150.000 $200.000
531 6022 CURB RAMPS (TY 5) SY 29.000 $125.000 $100.000 $150.000 $200.000
531 6027 CURB RAMPS (TY 10) SY 244.000 $125.000 $100.000 $150.000 $200.000
531 6033 CONC SIDEWALKS (SPECIAL) (TYPE B) SY 891.000 $95.000 $125.000 $400.000 $75.000
624 6009 GROUND BOX TY D (162922) EA 5.000 $900.000 $750.000 $750.000 $950.000
624 6028 REMOVE GROUND BOX EA 5.000 $300.000 $50.000 $100.000 $200.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 61.000 $700.000 $150.000 $500.000 $850.000
644 6070 RELOCATE SM RD SN SUP&AM TY S80 EA 25.000 $700.000 $150.000 $500.000 $850.000
644 6076 REMOVE SM RD SN SUP&AM EA 3.000 $110.000 $150.000 $500.000 $150.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 816.000 $6.000 $10.000 $10.000 $20.000
666 6230 PAVEMENT SEALER 24" LF 816.000 $3.000 $3.000 $3.000 $20.000
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 568.000 $4.000 $10.000 $10.000 $20.000
678 6008 PAV SURF PREP FOR MRK (24") LF 816.000 $2.000 $7.000 $4.000 $20.000
688 6002 PED DETECT PUSH BUTTON (STANDARD) EA 10.000 $395.000 $250.000 $500.000 $1,850.000
690 6005 INSTALL OF VEHICLE DETECTORS LF 10,000.000 $3.800 $0.010 $1.000 $11.000
690 6030 REMOVAL OF PEDESTRIAN PUSH BUTTONS EA 10.000 $200.000 $50.000 $100.000 $500.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $17,000.000 $1,000.000 $16,000.000 $10,000.000
6185 6002 TMA (STATIONARY) DAY 178.000 $200.000 $20.000 $400.000 $550.000
6185 6003 TMA (MOBILE OPERATION) HR 80.000 $60.000 $20.000 $45.000 $85.000
Totals: $2,144,553.90 $1,985,312.90 $2,754,806.00 $2,842,000.00