POTTER IH 40 (0275-01-221)

Items: 62

County: POTTER
Length: N/A
Highway: IH 40
District: AMARILLO
Control Number: 0275-01-221
DBE Goal: N/A
Project: F 2022(166)
Guaranty: N/A
Time: 145 WORKING DAYS
Engineer's Estimate: $11,234,135.00
Date: 12/01/2021 (4 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$11,234,135.00
$13,120,890.35
Over/Under Est: 16.79% $1,886,755.35
$14,176,711.61
Over/Under Est: 26.19% $2,942,576.61
Amt Left: 8.05% $1,055,821.26
$16,824,762.67
Over/Under Est: 49.76% $5,590,627.67
Amt Left: 28.23% $3,703,872.32
Delta: -18.68% -$2,648,051.06

Bid Items & Bid Tabulations

62 Total 0 of 62
POTTER  |  IH 40  |  AMARILLO  |  0275-01-221  |  12/01/2021  |  $11,234,135.00  |  F 2022(166)  |  PREVENT MAINT  |  145 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
GILVIN-TERRILL, LTD.
RK HALL, LLC
PREPARING ROW
STA 12.000 $20,000.000 $22,000.000 $2,500.000 $1,647.730
REMOVING CONC (RIPRAP)
SY 1,357.000 $20.000 $38.500 $100.000 $52.800
BLADING
HR 90.000 $280.000 $450.000 $250.000 $274.490
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 2,574.000 $1.000 $1.150 $2.000 $1.200
DRILL SEED (TEMP)(WARM OR COOL)
SY 2,574.000 $1.000 $0.900 $1.500 $0.960
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
TON 30,835.000 $148.000 $187.000 $150.000 $240.110
TACK COAT
GAL 29,152.000 $5.000 $6.400 $4.000 $9.180
PLANE ASPH CONC PAV (2 1/2")
SY 224,252.000 $4.000 $3.100 $3.000 $4.200
CURB (TYPE I)
LF 1,275.000 $30.000 $22.450 $30.000 $52.800
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 115.000 $500.000 $1,840.000 $1,000.000 $1,980.000
CUT & RESTORING PAV
SY 689.000 $300.000 $91.000 $200.000 $264.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 1,038.000 $250.000 $190.000 $100.000 $204.000
RIPRAP (CONC)(5 IN)
CY 2,810.000 $600.000 $445.000 $1,000.000 $792.000
RIPRAP (MOW STRIP)(4 IN)
CY 471.000 $600.000 $545.000 $1,100.000 $792.000
RIPRAP (MOW STRIP)(5 IN)
CY 37.000 $600.000 $550.000 $1,100.000 $990.000
JOINT SEALANT
LF 716.000 $75.000 $151.500 $100.000 $163.200
RC PIPE (CL III)(18 IN)
LF 88.000 $150.000 $330.000 $310.000 $569.600
RC PIPE (CL III)(24 IN)
LF 344.000 $175.000 $385.000 $320.000 $330.000
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
EA 45.000 $5,200.000 $8,950.000 $15,000.000 $12,540.000
INLET (COMPL)(TY H)
EA 18.000 $7,200.000 $6,900.000 $10,000.000 $7,920.000
ADJUSTING INLETS
EA 1.000 $2,000.000 $3,600.000 $15,000.000 $6,600.000
ADJUSTING INLET (CAP)
EA 85.000 $3,300.000 $3,600.000 $5,000.000 $4,620.000
REMOV STR (PIPE)
LF 196.000 $20.000 $245.000 $100.000 $33.000
MOBILIZATION
LS 1.000 $950,000.000 $1,290,000.000 $1,400,000.000 $1,682,476.260
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $20,000.000 $66,000.000 $120,000.000 $71,537.800
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 480.000 $35.000 $45.500 $50.000 $90.000
CONSTRUCTION EXITS (REMOVE)
SY 480.000 $6.000 $8.000 $15.000 $18.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 171.000 $6.000 $10.000 $4.500 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 171.000 $2.000 $5.000 $1.000 $1.200
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 2,825.000 $5.000 $8.100 $5.000 $2.940
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 250.000 $6.500 $15.000 $5.500 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,075.000 $2.000 $5.000 $1.000 $1.200
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 509.000 $150.000 $154.000 $150.000 $165.240
PERM CTB (SGL SLOPE) (TY 3) (42 )
LF 28.000 $200.000 $230.000 $210.000 $249.360
PERM CTB (SSCB)(TY 1)(MOD)
LF 80.000 $225.000 $180.000 $165.000 $191.840
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
LF 28.000 $300.000 $235.000 $250.000 $251.280
MTL W-BEAM GD FEN (STEEL POST)
LF 8,109.000 $30.000 $40.650 $31.000 $43.800
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 21.000 $1,900.000 $3,065.000 $2,175.000 $3,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 17.000 $1,600.000 $1,800.000 $1,475.000 $1,950.000
REMOVE METAL BEAM GUARD FENCE
LF 8,638.000 $5.000 $3.650 $2.000 $3.900
REMOVE TERMINAL ANCHOR SECTION
EA 16.000 $330.000 $365.000 $350.000 $390.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $450.000 $365.000 $350.000 $390.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 19.000 $315.000 $365.000 $350.000 $390.000
GUARDRAIL END TREATMENT (INSTALL)
EA 24.000 $3,000.000 $4,100.000 $3,079.000 $4,410.000
GUARDRAIL END TREATMENT (REMOVE)
EA 23.000 $500.000 $365.000 $350.000 $390.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $20.000 $20.000 $32.000 $21.600
REMOVE DELIN & OBJECT MARKER ASSMS
EA 36.000 $25.000 $15.000 $10.000 $12.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 54.000 $40.000 $40.000 $39.000 $42.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $30.000 $39.000 $40.000 $42.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 22.000 $35.000 $39.000 $39.000 $42.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 84.000 $150.000 $165.000 $150.000 $180.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 15,540.000 $1.500 $1.300 $1.000 $1.530
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 582.000 $1.500 $1.100 $1.000 $1.200
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 14,074.000 $1.500 $1.050 $0.920 $1.100
REFL PAV MRK TY I (W)12"(LNDP)(090MIL)
LF 156.000 $3.000 $3.350 $3.000 $3.600
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 4,515.000 $3.000 $2.800 $2.500 $3.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 32,310.000 $0.500 $0.500 $0.460 $0.550
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 73,543.000 $0.500 $0.500 $0.460 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 76,365.000 $0.500 $0.600 $0.510 $0.610
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $24,000.000 $15,500.000 $11,081.580
TMA (STATIONARY)
DAY 145.000 $300.000 $542.030 $710.000 $470.820
TMA (MOBILE OPERATION)
HR 210.000 $90.000 $85.700 $95.000 $125.790
Totals: $11,234,135.000 $13,120,890.350 $14,176,711.610 $16,824,762.670