PECOS IH0010 (6324-30-001)

Items: 14

County: PECOS
Length: N/A
Highway: IH0010
District: ODESSA
Control Number: 6324-30-001
DBE Goal: N/A
Project: RMC - 632430001
Guaranty: N/A
Time: 60 W
Engineer's Estimate: $271,415.00
Date: 01/09/2018 (8 years ago)
Contract Number: N/A
Type: CULVERT REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$271,415.00
$322,217.50
Over/Under Est: 18.72% $50,802.50
$428,178.00
Over/Under Est: 57.76% $156,763.00
Amt Left: 32.88% $105,960.50
Over/Under Est: 58.24% $158,085.00
Amt Left: 33.3% $107,282.50
Delta: -0.31% -$1,322.00
Over/Under Est: 74.95% $203,415.00
Amt Left: 47.36% $152,612.50
Delta: -10.55% -$45,330.00
Over/Under Est: 108.57% $294,684.39
Amt Left: 75.69% $243,881.89
Delta: -19.22% -$91,269.39

Bid Items & Bid Tabulations

14 Total 0 of 14
PECOS  |  IH0010  |  ODESSA  |  6324-30-001  |  01/09/2018  |  $271,415.00  |  RMC - 632430001  |  CULVERT REPAIR  |  60 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
VIZCAINO, L.P.
RELMCO, INC.
FNH CONSTRUCTION, LLC
CHAMPION INFRASTRUCTURE, LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
REMOVE CONC (WINGWALL)
CY 6.700 $500.000 $325.000 $400.000 $500.000 $800.000 $1,121.110
REMOVING CONC (HEADWALL)
CY 6.000 $500.000 $150.000 $1,500.000 $500.000 $1,200.000 $1,251.840
D-GR HMA(SQ) TY-C SAC-B PG70-22
TON 76.000 $300.000 $200.000 $350.000 $250.000 $450.000 $427.400
STRUCT EXCAV
CY 15.000 $30.000 $30.000 $150.000 $100.000 $85.000 $249.180
FLOWABLE BACKFILL
CY 95.000 $175.000 $250.000 $275.000 $350.000 $325.000 $368.060
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 766.000 $140.000 $90.000 $125.000 $250.000 $220.000 $151.440
RC PIPE (ARCH)(CL III)(DES 4)
LF 240.000 $160.000 $270.000 $375.000 $125.000 $200.000 $351.050
HEADWALL (CH - FW - 0) (DIA= 30 IN)
EA 1.000 $6,500.000 $10,000.000 $7,475.000 $6,500.000 $15,000.000 $20,407.140
HEADWALL (CH - FW - A - 45) (DES= 4)
EA 2.000 $6,500.000 $10,000.000 $7,670.000 $8,500.000 $18,000.000 $25,349.660
WINGWALL (FW - S) (HW=3 FT)
EA 3.000 $6,500.000 $10,000.000 $9,100.000 $9,500.000 $16,000.000 $11,300.200
SET (TY II) (30 IN) (CMP) (3: 1) (C)
EA 1.000 $1,750.000 $5,000.000 $6,058.000 $10,000.000 $4,500.000 $5,656.330
REMOV STR (PIPE)
LF 240.000 $20.000 $25.000 $40.000 $35.000 $110.000 $45.020
MOBILIZATION
LS 1.000 $25,000.000 $30,000.000 $35,000.000 $40,000.000 $30,000.000 $53,651.070
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $15,000.000 $25,000.000 $12,500.000 $6,500.000 $34,838.940
Totals: $271,415.000 $322,217.500 $428,178.000 $429,500.000 $474,830.000 $566,099.397