PECOS IH 10 (0140-02-050)

Items: 19

County: PECOS
Length: N/A
Highway: IH 10
District: ODESSA
Control Number: 0140-02-050
DBE Goal: N/A
Project: STP 2023(306)HES
Guaranty: N/A
Time: 124 WORKING DAYS
Engineer's Estimate: $2,084,199.70
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
ODA-PRELETTINGQUESTIONS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$2,084,199.70
$1,938,518.00
Over/Under Est: -6.99% -$145,681.70
Over/Under Est: -3.84% -$80,067.41
Amt Left: 3.38% $65,614.29
Over/Under Est: 2.13% $44,488.25
Amt Left: 9.81% $190,169.95
Delta: -6.21% -$124,555.66
Over/Under Est: 16.95% $353,313.42
Amt Left: 25.74% $498,995.12
Delta: -14.51% -$308,825.17
Subcontractor Percentage Amount
FC TRAFFIC CONTROL, INC. 0.82% $15,895.85
Total: 0.82% $15,895.85

Bid Items & Bid Tabulations

19 Total 0 of 19
PECOS  |  IH 10  |  ODESSA  |  0140-02-050  |  09/06/2023  |  $2,084,199.70  |  STP 2023(306)HES  |  INSTL MEDIAN BARRIER  |  124 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HJC FARMS, INC.
GRATIOT CONSTRUCTION, LTD.
ROADWAY SPECIALTIES, INC.
SCR CIVIL CONSTRUCTION, LLC
EXCAVATION (ROADWAY)
CY 158.000 $20.000 $32.000 $85.230 $20.160 $200.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 219.000 $35.000 $35.000 $100.000 $20.160 $45.000
BLADING
HR 40.000 $150.000 $250.000 $113.640 $100.800 $368.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 27,424.000 $0.250 $1.000 $0.570 $0.660 $0.580
AGGR(TY-A GR-1 SAC-A)
CY 96.000 $200.000 $200.000 $113.640 $1,472.520 $720.000
RIPRAP (MOW STRIP)(4 IN)
CY 1,530.000 $580.000 $500.000 $408.700 $525.830 $775.000
MOBILIZATION
LS 1.000 $189,472.700 $275,000.000 $222,727.270 $304,972.610 $156,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $20,000.000 $1,500.000 $1,687.500 $2,788.740 $6,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,440.000 $15.500 $8.000 $14.770 $15.780 $13.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,440.000 $4.150 $2.000 $5.680 $1.350 $4.600
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $44.000 $37.500 $45.450 $43.460 $46.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,945.000 $1,750.000 $2,272.730 $1,346.560 $2,300.000
CABLE BARRIER SYSTEM (TL-4)
LF 40,166.000 $15.000 $15.500 $23.550 $16.310 $17.700
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 12.000 $2,900.000 $4,350.000 $4,931.820 $3,379.810 $4,200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $4,385.000 $3,450.000 $4,545.450 $3,267.420 $1,600.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $1,270.000 $1,250.000 $454.550 $1,223.440 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 8.000 $1,600.000 $1,175.000 $568.180 $1,141.010 $2,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $15,000.000 $3,409.090 $15,000.000 $7,500.000
TMA (STATIONARY)
DAY 248.000 $240.000 $150.000 $2.270 $65.750 $225.000
Totals: $2,084,199.700 $1,938,518.000 $2,004,132.290 $2,128,687.950 $2,437,513.120