Show Job Controls
Bid Cobra

PARKER CS (0902-38-129)

Items: 48

County: PARKER
Length: N/A
Highway: CS
District: FORT WORTH
Control Number: 0902-38-129
DBE Goal: N/A
Project: BR 2019(266)
Guaranty: N/A
Time: 98 WORKING DAYS
Engineer's Estimate: $804,134.43
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$804,134.43
$919,705.10
Over/Under Est: 14.37% $115,570.67
Over/Under Est: 22.56% $181,429.22
Amt Left: 7.16% $65,858.55
$1,023,081.66
Over/Under Est: 27.23% $218,947.23
Amt Left: 11.24% $103,376.56
Delta: -3.81% -$37,518.01
Over/Under Est: 65.8% $529,130.47
Amt Left: 44.97% $413,559.80
Delta: -30.32% -$310,183.24

Bid Items & Bid Tabulations

48 Total 0 of 48
PARKER  |  CS  |  FORT WORTH  |  0902-38-129  |  08/05/2021  |  $804,134.43  |  BR 2019(266)  |  BRIDGE REPL  |  98 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
HODGES AND SON CONSTRUCTION COMPANY, INC.
FLUOR HEAVY CIVIL, LLC
ARANDA BROTHERS CONSTRUCTION CO., INC.
PREPARING ROW
STA 5.000 $2,200.000 $13,650.000 $10,000.000 $20,430.000 $26,000.000
REMOVING STAB BASE AND ASPH PAV (0-4")
SY 903.000 $15.000 $2.000 $15.000 $6.030 $17.000
EXCAVATION (ROADWAY)
CY 489.000 $10.000 $25.000 $20.000 $24.880 $16.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 85.000 $6.000 $25.000 $50.000 $86.840 $18.000
COMPOST MANUF TOPSOIL (4")
SY 1,137.000 $2.500 $3.960 $5.000 $4.900 $21.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,137.000 $1.000 $2.400 $2.000 $1.470 $0.500
BROADCAST SEED (TEMP) (WARM)
SY 568.500 $1.000 $1.950 $2.000 $1.780 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 568.500 $1.000 $2.400 $2.000 $1.780 $0.700
VEGETATIVE WATERING
MG 39.800 $25.000 $235.660 $1.000 $27.170 $80.000
FL BS (CMP IN PLC)(TYA GR1-2) (6")
SY 917.000 $25.000 $12.000 $15.000 $9.960 $31.500
LIME (HYDRATED LIME (SLURRY))
TON 16.000 $200.000 $200.000 $250.000 $231.410 $210.000
LIME TRT (SUBGRADE)(8")
SY 917.000 $10.000 $8.500 $15.000 $14.720 $6.500
PRIME COAT (MULTI OPTION)
GAL 183.400 $5.000 $15.000 $30.000 $14.120 $13.500
CEM STABIL BKFL
CY 71.000 $130.000 $275.000 $250.000 $178.800 $95.000
DRILL SHAFT (18 IN)
LF 44.000 $150.000 $130.000 $120.000 $129.230 $250.000
DRILL SHAFT (36 IN)
LF 165.000 $180.000 $315.000 $230.000 $275.110 $450.000
CL C CONC (ABUT)(HPC)
CY 42.800 $850.000 $1,000.000 $1,200.000 $1,376.500 $1,200.000
CL C CONC (CAP)(HPC)
CY 13.000 $1,000.000 $1,350.000 $1,200.000 $1,308.230 $1,500.000
REINF CONC SLAB (HPC)
SF 4,800.000 $20.000 $21.000 $22.000 $21.750 $21.000
APPROACH SLAB (HPC)
CY 57.200 $600.000 $500.000 $650.000 $480.000 $675.000
SHEAR KEY
CY 2.850 $700.000 $500.000 $600.000 $1,785.520 $700.000
PRESTR CONC GIRDER (TX28)
LF 954.000 $150.000 $200.000 $210.000 $172.450 $246.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 445.510 $130.000 $125.000 $135.000 $83.690 $230.000
RIPRAP (MOW STRIP)(4 IN)
CY 25.000 $550.000 $630.000 $550.000 $629.170 $650.000
RAIL (TY T223)(HPC)
LF 380.000 $125.000 $150.000 $120.000 $238.610 $180.000
ARMOR JOINT (SEALED)
LF 56.000 $90.000 $100.000 $85.000 $173.000 $130.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $33,000.000 $10,000.000 $35,000.000 $34,500.000 $40,000.000
MOBILIZATION
LS 1.000 $73,103.130 $90,000.000 $85,000.000 $102,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $6,300.000 $2,000.000 $4,000.000 $690.580 $6,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 182.000 $20.000 $10.000 $1.000 $22.180 $22.000
CONSTRUCTION EXITS (REMOVE)
SY 182.000 $7.000 $5.000 $1.000 $7.060 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 918.000 $2.500 $3.000 $1.000 $2.770 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 918.000 $0.750 $0.100 $1.000 $1.010 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 60.000 $7.000 $4.000 $10.000 $5.040 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 60.000 $1.000 $1.000 $5.000 $1.010 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 225.000 $20.000 $27.500 $26.000 $23.690 $55.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,500.000 $1,000.000 $1,200.000 $857.030 $3,250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,600.000 $3,150.000 $2,800.000 $2,671.920 $4,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $1,000.000 $700.000 $800.000 $574.720 $550.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $45.000 $44.000 $30.000 $20.170 $450.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $45.000 $48.000 $30.000 $22.180 $450.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 1,000.000 $1.000 $3.000 $5.000 $2.020 $6.000
REFL PAV MRK TY II (Y) 4" (BRK)
LF 500.000 $1.000 $3.750 $5.000 $2.520 $7.000
REFL PAV MRKR TY II-A-A
EA 6.000 $10.000 $20.000 $25.000 $8.070 $150.000
PAV SURF PREP FOR MRK (4")
LF 480.000 $0.500 $1.550 $1.000 $1.410 $3.000
PAV SURF PREP FOR MRK (RPM)
EA 2.000 $2.000 $3.000 $50.000 $2.020 $50.000
SP MIXES SP-C SAC-B PG70-28
TON 160.000 $130.000 $203.500 $200.000 $186.530 $180.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $5,200.000 $4,000.000 $10,000.000 $11,357.890 $15,000.000
Totals: $804,134.430 $919,705.113 $985,563.650 $1,023,081.678 $1,333,264.900