Job Info for 0314-07-080

County: PARKER Highway: IH 20 Date: 08/04/2022 (2 years ago) Engineer's Estimate: $395,689 Control Number: 0314-07-080
Project: F 2022(848) District: FORT WORTH Time: 85 WORKING DAYS Type: LANDSCAPE DEVELOPMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $395,689.00
CENTRAL NORTH CONSTRUCTION, LLC   $365,891.50 1
-7.53% | -$29,797.50
ENCINO LANDSCAPE, INC.   $416,430.00 2
5.24% | $20,741.00
13.81% | $50,538.50
APEX LANDSCAPE & IRRIGATION, LLC   $489,046.00 3
23.59% | $93,357.00
33.66% | $123,154.50
17.44% | $72,616.00

Bid Items

Items: 19, 0 filtered
PARKER IH 20  |  FORT WORTH  |  0314-07-080  |  08/04/2022  |  $395,689  |  F 2022(848)  |  LANDSCAPE DEVELOPMENT  |  85 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CENTRAL NORTH CONSTRUCTION, LLC ENCINO LANDSCAPE, INC. APEX LANDSCAPE & IRRIGATION, LLC
100 6001 PREPARING ROW AC 0.400 $34,170.000 $35,000.000 $10,000.000 $7,500.000
170 6002 IRRIGATION SYSTEM (TY I) LS 1.000 $62,500.000 $85,000.000 $50,000.000 $55,000.000
170 6003 IRRIGATION SYSTEM (TY II) LS 1.000 $60,000.000 $85,000.000 $20,000.000 $60,000.000
170 6004 IRRIGATION SYSTEM (TY III) LS 1.000 $11,000.000 $7,852.500 $20,000.000 $50,000.000
170 6005 IRRIGATION SYSTEM (TY IV) LS 1.000 $16,000.000 $5,160.000 $20,000.000 $50,000.000
192 6002 PLANT MATERIAL (1-GAL) EA 1,132.000 $18.000 $8.000 $15.000 $12.500
192 6013 MULCH SY 1,804.000 $4.500 $5.000 $5.000 $4.000
192 6025 PLANT MATERIAL (45 GAL) (TREE) EA 242.000 $451.000 $315.000 $500.000 $410.000
193 6001 PLANT MAINTENANCE MO 12.000 $1,250.000 $1,800.000 $2,000.000 $2,000.000
193 6014 IRRIG SYS OPER AND MAINT (SCH A) MO 12.000 $750.000 $750.000 $1,000.000 $1,000.000
500 6001 MOBILIZATION LS 1.000 $36,000.000 $17,653.000 $60,000.000 $49,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $4,000.000 $1,800.000 $3,000.000 $5,500.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 120.000 $22.000 $1.000 $50.000 $35.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 120.000 $9.000 $1.000 $1.000 $5.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 290.000 $3.500 $1.000 $8.000 $3.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 290.000 $1.000 $1.000 $1.000 $1.000
618 6024 CONDT (PVC) (SCH 40) (2") (BORE) LF 120.000 $28.000 $35.000 $25.000 $30.000
618 6034 CONDT (PVC) (SCH 40) (4") (BORE) LF 120.000 $38.000 $35.000 $50.000 $35.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 99.000 $60.000 $100.000 $300.000 $300.000
Totals: $395,689.00 $365,891.50 $416,430.00 $489,046.00