PARKER IH 20 (0314-07-075)
Items: 62
County: PARKER
Length: N/A
Highway: IH 20
District: FORT WORTH
Control Number: 0314-07-075
DBE Goal: N/A
Project: F 2022(170)
Guaranty: N/A
Time: 182 WORKING DAYS
Engineer's Estimate: $7,785,695.80
Date: 12/01/2021 (4 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,785,695.80 | |||
| $7,251,017.34 |
-6.87%
-$534,678.46
|
|||
| $8,485,348.03 |
8.99%
$699,652.23
|
17.02%
$1,234,330.69
|
||
| $8,696,203.02 |
11.69%
$910,507.22
|
19.93%
$1,445,185.68
|
-2.48%
-$210,854.99
|
|
| $8,916,909.05 |
14.53%
$1,131,213.25
|
22.97%
$1,665,891.71
|
-2.54%
-$220,706.03
|
|
| $9,333,648.06 |
19.88%
$1,547,952.26
|
28.72%
$2,082,630.72
|
-4.67%
-$416,739.01
|
|
| $9,359,977.32 |
20.22%
$1,574,281.52
|
29.09%
$2,108,959.98
|
-0.28%
-$26,329.26
|
|
| $10,510,602.10 |
35%
$2,724,906.30
|
44.95%
$3,259,584.76
|
-12.29%
-$1,150,624.78
|
E
Engineer's Estimate
$7,785,695.80
1
$7,251,017.34
Over/Under Est:
-6.87%
-$534,678.46
$8,485,348.03
Over/Under Est:
8.99%
$699,652.23
Amt Left:
17.02%
$1,234,330.69
$8,696,203.02
Over/Under Est:
11.69%
$910,507.22
Amt Left:
19.93%
$1,445,185.68
Delta:
-2.48%
-$210,854.99
$8,916,909.05
Over/Under Est:
14.53%
$1,131,213.25
Amt Left:
22.97%
$1,665,891.71
Delta:
-2.54%
-$220,706.03
$9,333,648.06
Over/Under Est:
19.88%
$1,547,952.26
Amt Left:
28.72%
$2,082,630.72
Delta:
-4.67%
-$416,739.01
$9,359,977.32
Over/Under Est:
20.22%
$1,574,281.52
Amt Left:
29.09%
$2,108,959.98
Delta:
-0.28%
-$26,329.26
$10,510,602.10
Over/Under Est:
35%
$2,724,906.30
Amt Left:
44.95%
$3,259,584.76
Delta:
-12.29%
-$1,150,624.78
Bid Items & Bid Tabulations
62
Total
0 of 62