PARKER US 180 (0008-02-073)

Items: 83

County: PARKER
Length: N/A
Highway: US 180
District: FORT WORTH
Control Number: 0008-02-073
DBE Goal: N/A
Project: F 2021(342)
Guaranty: N/A
Time: 216 WORKING DAYS
Engineer's Estimate: $1,962,659.04
Date: 07/02/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (7)
E
Engineer's Estimate
$1,962,659.04
$2,139,284.22
Over/Under Est: 9% $176,625.18
$2,204,598.98
Over/Under Est: 12.33% $241,939.94
Amt Left: 3.05% $65,314.76
Over/Under Est: 14.1% $276,681.04
Amt Left: 4.68% $100,055.86
Delta: -1.58% -$34,741.10
Over/Under Est: 16.66% $326,962.68
Amt Left: 7.03% $150,337.50
Delta: -2.25% -$50,281.64
Over/Under Est: 17.09% $335,451.38
Amt Left: 7.42% $158,826.20
Delta: -0.37% -$8,488.70
Over/Under Est: 20.56% $403,437.26
Amt Left: 10.6% $226,812.08
Delta: -2.96% -$67,985.88
Over/Under Est: 21.69% $425,763.70
Amt Left: 11.65% $249,138.52
Delta: -0.94% -$22,326.44

Bid Items & Bid Tabulations

83 Total 0 of 83
PARKER  |  US 180  |  FORT WORTH  |  0008-02-073  |  07/02/2021  |  $1,962,659.04  |  F 2021(342)  |  BRIDGE REPL  |  216 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NEW WORLD CONTRACTING, LLC
FLUOR HEAVY CIVIL, LLC
SEMA CONSTRUCTION, INC.
RAGLE CONSTRUCTION, INC.
MCMAHON CONTRACTING, L.P.
HODGES AND SON CONSTRUCTION COMPANY, INC.
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 5.000 $3,000.000 $8,976.000 $77,301.250 $44,345.000 $40,000.000 $3,211.150 $13,000.000 $11,550.000
EXCAVATION (ROADWAY)
CY 548.000 $10.000 $22.000 $15.800 $3.000 $23.000 $22.650 $20.000 $25.000
EXCAVATION (CHANNEL)
CY 1,340.000 $15.000 $27.000 $15.120 $15.000 $15.000 $23.950 $20.000 $25.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 450.000 $12.000 $31.000 $17.690 $8.000 $10.000 $17.870 $25.000 $50.000
EROSION CONTROL COMPOST (2")
SY 541.000 $2.500 $13.000 $11.650 $3.600 $3.440 $13.410 $5.000 $12.330
COMPOST MANUF TOPSOIL (4")
SY 15,583.000 $2.000 $1.000 $1.500 $1.600 $1.000 $1.070 $1.250 $0.990
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 16,124.000 $1.000 $0.250 $0.150 $0.220 $0.200 $0.170 $0.250 $0.200
VEGETATIVE WATERING
MG 566.000 $20.000 $17.000 $27.150 $17.500 $26.000 $31.240 $1.000 $51.590
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 541.000 $2.000 $3.000 $2.600 $2.000 $1.800 $2.990 $2.000 $2.770
SLV, HAUL & STKPL RCL APH PV(8" TO 14")
SY 1,510.000 $5.000 $7.000 $4.160 $6.800 $7.000 $6.830 $15.000 $6.330
CEM STABIL BKFL
CY 92.000 $158.640 $185.000 $151.600 $110.000 $100.000 $284.040 $220.000 $256.640
DRILL SHAFT (36 IN)
LF 622.000 $208.460 $234.000 $201.530 $300.000 $150.000 $236.640 $200.000 $230.000
CL C CONC (ABUT)(HPC)
CY 56.100 $1,129.880 $1,015.000 $1,309.440 $850.000 $700.000 $1,112.550 $1,100.000 $1,250.000
CL C CONC (CAP)(HPC)
CY 48.400 $1,032.000 $1,074.000 $1,503.110 $1,100.000 $1,100.000 $1,359.780 $1,200.000 $1,250.000
CL C CONC (COLUMN)(HPC)
CY 40.800 $1,339.000 $981.000 $1,169.870 $950.000 $700.000 $1,359.780 $1,200.000 $1,250.000
CL C CONC (MISC)
CY 8.000 $800.000 $1,004.000 $1,148.350 $750.000 $800.000 $981.450 $800.000 $700.000
REINF CONC SLAB (HPC)
SF 6,900.000 $23.360 $22.000 $23.180 $18.000 $22.000 $30.320 $22.000 $22.500
APPROACH SLAB (HPC)
CY 113.400 $525.000 $524.000 $592.220 $500.000 $500.000 $498.520 $650.000 $500.000
PRESTR CONC GIRDER (TX28)
LF 890.520 $172.400 $236.000 $161.060 $150.000 $350.000 $197.030 $170.000 $300.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 2,457.000 $100.000 $110.000 $66.250 $85.000 $120.000 $125.640 $142.000 $117.260
RIPRAP (MOW STRIP)(5 IN)
CY 47.000 $685.000 $471.000 $645.340 $475.000 $500.000 $581.760 $550.000 $600.000
RAIL (TY T223)(HPC)
LF 340.000 $100.000 $162.000 $147.180 $120.000 $100.000 $128.410 $120.000 $150.000
ARMOR JOINT (SEALED)
LF 97.000 $95.700 $61.000 $124.410 $100.000 $100.000 $110.620 $85.000 $75.000
GABIONS (GALV)
CY 218.000 $209.790 $330.000 $187.270 $225.000 $250.000 $356.640 $325.000 $342.900
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $65,000.000 $56,100.000 $42,844.030 $154,200.000 $50,000.000 $95,772.000 $50,000.000 $35,000.000
MOBILIZATION
LS 1.000 $178,423.000 $200,000.000 $209,660.000 $223,000.000 $230,000.000 $225,000.000 $210,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $6,800.000 $3,927.000 $1,892.040 $4,250.000 $4,500.000 $2,685.300 $2,500.000 $7,350.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 239.000 $32.000 $63.000 $56.860 $60.000 $45.000 $65.420 $5.000 $40.850
ROCK FILTER DAMS (REMOVE)
LF 239.000 $10.000 $10.000 $8.940 $9.000 $10.000 $10.290 $5.000 $17.200
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 468.000 $26.000 $29.000 $26.430 $25.000 $23.000 $30.420 $1.000 $23.650
CONSTRUCTION EXITS (REMOVE)
SY 468.000 $10.000 $8.000 $7.020 $7.000 $7.500 $8.070 $1.000 $12.900
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,732.000 $3.000 $2.000 $2.000 $2.000 $1.900 $2.300 $1.000 $1.610
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,732.000 $0.500 $0.500 $0.430 $0.750 $0.800 $0.500 $1.000 $0.160
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 245.000 $4.000 $4.000 $3.370 $3.150 $3.000 $3.870 $8.000 $2.960
BIODEG EROSN CONT LOGS (REMOVE)
LF 245.000 $1.000 $1.000 $0.560 $1.000 $1.000 $0.650 $2.000 $1.080
CONSTRUCTING DETOURS
SY 1,196.000 $80.000 $67.000 $89.940 $115.000 $120.000 $118.350 $108.000 $164.520
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 2,640.000 $12.000 $11.000 $10.950 $11.500 $8.000 $9.820 $80.000 $10.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 4,560.000 $5.000 $6.000 $2.420 $2.500 $6.000 $5.230 $5.000 $5.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 2,640.000 $5.000 $11.000 $4.820 $9.500 $7.000 $9.820 $10.000 $10.000
RUMBLE STRIPS (SHOULDER)
LF 1,460.000 $0.500 $4.000 $2.770 $3.400 $2.750 $5.450 $4.000 $1.290
MTL W-BEAM GD FEN (TIM POST)
LF 487.500 $25.000 $22.000 $20.160 $24.000 $20.000 $23.200 $25.000 $23.650
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,850.000 $1,795.000 $1,612.960 $1,800.000 $1,600.000 $1,856.000 $1,600.000 $2,238.190
TRANSITION ADJUSTMENT
EA 2.000 $400.000 $561.000 $504.050 $850.000 $500.000 $580.000 $700.000 $913.750
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,170.000 $1,234.000 $1,108.910 $1,300.000 $1,100.000 $1,276.000 $1,200.000 $1,064.250
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $860.000 $561.000 $504.050 $650.000 $500.000 $580.000 $600.000 $698.750
REMOVE METAL BEAM GUARD FENCE
LF 575.000 $5.000 $3.000 $2.520 $3.100 $2.500 $2.900 $4.000 $2.150
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $215.000 $140.000 $126.010 $315.000 $125.000 $145.000 $500.000 $322.500
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,660.000 $2,861.000 $2,570.650 $3,000.000 $2,550.000 $2,958.000 $2,800.000 $2,795.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $260.000 $281.000 $252.030 $325.000 $250.000 $290.000 $500.000 $322.500
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,680.000 $1,010.000 $907.290 $750.000 $800.000 $1,044.000 $3,000.000 $1,786.130
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,200.000 $785.000 $705.670 $750.000 $700.000 $812.000 $1,000.000 $893.060
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $9,910.000 $8,191.000 $7,359.110 $7,500.000 $8,000.000 $8,468.000 $10,000.000 $12,688.590
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 4.000 $22.000 $20.000 $18.150 $18.500 $18.000 $20.880 $30.000 $25.800
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 3.000 $20.000 $20.000 $18.150 $18.500 $18.000 $20.880 $30.000 $25.800
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 5.000 $38.000 $28.000 $25.200 $21.500 $25.000 $29.000 $30.000 $31.180
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 7.000 $31.000 $28.000 $25.200 $21.500 $25.000 $29.000 $30.000 $31.180
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,137.000 $0.750 $2.000 $1.110 $1.300 $1.650 $2.200 $1.150 $1.180
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 2,299.000 $0.750 $2.000 $1.110 $1.300 $1.650 $1.280 $1.150 $1.180
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 247.000 $1.000 $1.000 $1.210 $1.400 $2.220 $1.390 $1.250 $1.290
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $200.000 $151.000 $120.970 $140.000 $155.100 $139.200 $150.000 $129.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $215.000 $185.000 $226.820 $260.000 $159.530 $261.000 $250.000 $241.880
REFL PAV MRK TY II (W) 4" (BRK)
LF 864.000 $1.000 $1.000 $0.550 $0.650 $0.820 $0.640 $0.750 $0.590
REFL PAV MRK TY II (W) 4" (SLD)
LF 215.000 $1.000 $1.000 $0.400 $0.600 $0.830 $0.460 $1.000 $0.430
REFL PAV MRK TY II (Y) 4" (SLD)
LF 2,907.000 $1.000 $1.000 $0.400 $0.600 $0.780 $1.600 $0.500 $0.430
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,221.000 $1.000 $1.000 $1.010 $1.150 $1.110 $1.160 $1.000 $1.080
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 495.000 $1.000 $1.000 $1.010 $1.150 $1.110 $1.160 $1.000 $1.080
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 3,186.000 $1.000 $1.000 $1.010 $1.150 $1.110 $1.160 $1.000 $1.080
REFL PAV MRKR TY II-C-R
EA 88.000 $3.000 $11.000 $8.060 $9.250 $5.540 $9.280 $10.000 $8.600
ELIM EXT PAV MRK & MRKS (4")
LF 1,901.000 $1.000 $1.000 $0.760 $0.900 $1.110 $0.870 $1.000 $0.810
ELIM EXT PAV MRK & MRKS (8")
LF 247.000 $1.000 $1.000 $1.510 $1.750 $2.220 $1.740 $2.000 $1.610
ELIM EXT PAV MRK & MRKS (ARROW)
EA 2.000 $50.000 $112.000 $100.810 $115.000 $99.710 $116.000 $200.000 $107.500
ELIM EXT PAV MRK & MRKS (WORD)
EA 2.000 $60.000 $112.000 $100.810 $115.000 $99.710 $116.000 $200.000 $107.500
PAV SURF PREP FOR MRK (4")
LF 3,986.000 $0.100 $1.000 $0.450 $0.550 $0.750 $0.520 $0.500 $0.480
PAV SURF PREP FOR MRK (8")
LF 247.000 $0.200 $1.000 $1.510 $1.750 $0.780 $1.740 $2.000 $1.610
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $21.000 $84.000 $50.410 $60.000 $55.400 $58.000 $100.000 $53.750
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $26.000 $84.000 $65.530 $75.000 $55.400 $75.400 $100.000 $69.880
D-GR HMA TY-B PG64-22
TON 756.000 $100.000 $103.000 $92.740 $96.000 $92.000 $106.720 $115.000 $99.000
TACK COAT
GAL 545.000 $3.000 $3.000 $6.050 $6.250 $6.000 $6.960 $8.000 $6.000
SP MIXES SP-C SAC-A PG70-28
TON 191.000 $120.000 $184.000 $151.210 $156.000 $150.000 $174.000 $200.000 $160.000
BAT HOUSE (LARGE)
EA 6.000 $2,500.000 $2,805.000 $1,168.040 $3,750.000 $1,500.000 $2,581.980 $2,500.000 $800.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $5,950.000 $17,840.000 $10,174.510 $14,000.000 $10,000.000 $3,480.000 $15,000.000 $10,000.000
TMA (STATIONARY)
DAY 12.000 $250.000 $393.000 $110.850 $250.000 $275.000 $290.000 $200.000 $210.000
TMA (MOBILE OPERATION)
HR 112.000 $60.000 $90.000 $54.530 $60.000 $100.000 $87.000 $25.000 $52.500
Totals: $1,962,659.036 $2,139,284.220 $2,204,599.003 $2,239,340.080 $2,289,621.720 $2,298,110.445 $2,366,096.300 $2,388,422.745