Bid Cobra

PALO PINTO IH0020 (6502-02-001)

Items: 17

County: PALO PINTO
Length: 0.0100 MILES
Highway: IH0020
District: FORT WORTH
Control Number: 6502-02-001
DBE Goal: 0.0%
Project: RMC - A00221639
Guaranty: $34,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,707,467.00
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7264004
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00221639
Project Description: 6502-02-001, GUARDRAIL REPAIR, FY27, PALO PINTO AND PARKER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CHADWICK DABBS
ELIJAH S ZELENOV
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$1,707,467.00
$974,892.00
Over/Under Est: -42.9% -$732,575.00
Over/Under Est: -39.61% -$676,245.00
Amt Left: 5.78% $56,330.00
Over/Under Est: -34.16% -$583,250.00
Amt Left: 15.32% $149,325.00
Delta: -9.02% -$92,995.00
$1,258,042.00
Over/Under Est: -26.32% -$449,425.00
Amt Left: 29.04% $283,150.00
Delta: -11.90% -$133,825.00
$1,301,462.00
Over/Under Est: -23.78% -$406,005.00
Amt Left: 33.5% $326,570.00
Delta: -3.45% -$43,420.00

Bid Items & Bid Tabulations

17 Total 0 of 17
PALO PINTO  |  IH0020  |  FORT WORTH  |  6502-02-001  |  07/01/2026 1:00 PM CDT  |  $1,707,467.00  |  RMC - A00221639  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SHORT-LINE, LLC
T&L CLEANING SERVICES LLC
AUSTIN BARRICADE COMPANY, L.L.C.
E.V.G. ENTERPRISE
RHINO EQUITY, LLC
MOBILIZATION (CALLOUT)
EA 12.000 $1,000.000 $1.000 $1.000 $1.000 $1.000 $1.000
MOBILIZATION (EMERGENCY)
EA 5.000 $1,500.000 $1.000 $1,000.000 $1.000 $1.000 $750.000
TMA (STATIONARY)
DAY 100.000 $217.000 $1.000 $1.000 $1.000 $100.000 $1,200.000
MTL W-BEAM GD FEN (TIM POST)
LF 9,000.000 $27.970 $15.000 $28.000 $28.000 $46.000 $25.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 10.000 $1,200.000 $500.000 $500.000 $200.000 $300.000 $1,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,450.000 $1.000 $1,000.000 $200.000 $1,000.000 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 32.000 $3,349.500 $3,000.000 $3,000.000 $4,000.000 $4,500.000 $3,600.000
REPLACE DOWNSTREAM ANCHOR TERMINAL
EA 10.000 $800.000 $1.000 $1,000.000 $200.000 $1,000.000 $1,500.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
EA 10.000 $1.000 $5,000.000 $1,500.000 $1,000.000 $500.000 $200.000
REPLACE W-BEAM RAIL
LF 2,500.000 $45.000 $20.000 $28.000 $35.000 $17.000 $25.000
REPLACE GUARDRAIL END TREATMENT SYSTEM
EA 100.000 $4,228.430 $2,500.000 $4,000.000 $4,000.000 $4,500.000 $3,600.000
REPLACE CURVED RAIL
LF 500.000 $50.000 $10.000 $25.000 $30.000 $30.000 $27.000
REMOVE RAIL
LF 10,000.000 $50.000 $15.000 $0.010 $0.010 $0.001 $5.000
REPLACE LINE OR TERMINAL POST (GIBRAL)
EA 1,000.000 $185.000 $200.000 $150.000 $210.000 $150.000 $300.000
REPLACE CABLE RELEASE POST
EA 15.000 $1,000.000 $250.000 $300.000 $200.000 $1.000 $600.000
CHECK AND RE-TENSION CABLE SYSTEM
EA 10.000 $500.000 $3,000.000 $1.000 $1,000.000 $300.000 $500.000
SPLICE CABLE
EA 5.000 $1,500.000 $1.000 $200.000 $500.000 $300.000 $100.000
Totals: $1,707,467.000 $974,892.000 $1,031,222.000 $1,124,217.000 $1,258,042.000 $1,301,462.000