Job Info for 0902-39-035

County: PALO PINTO Highway: VA Date: 12/03/2020 (3 years ago) Engineer's Estimate: $3,578,993 Control Number: 0902-39-035
Project: C 902-39-35 District: FORT WORTH Time: 93 WORKING DAYS Type: STATE PARK IMPROVEMENTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,578,993.13
JAY MILLS CONTRACTING, INCORPORATED   $3,292,351.10 1
-8.01% | -$286,642.03
ZACHRY CONSTRUCTION CORPORATION   $3,443,797.91 2
-3.78% | -$135,195.22
4.6% | $151,446.81
INTEGRITY SERVICES, LLC   $3,812,697.09 3
6.53% | $233,703.96
15.8% | $520,345.99
10.71% | $368,899.18
A. L. HELMCAMP, INC.   $3,862,545.82 4
7.92% | $283,552.69
17.32% | $570,194.72
1.31% | $49,848.73
ACCELERATED CRITICAL PATH, INC.   $3,879,464.05 5
8.4% | $300,470.92
17.83% | $587,112.95
0.44% | $16,918.23
KIEWIT INFRASTRUCTURE SOUTH CO.   $5,434,600.96 6
51.85% | $1,855,607.83
65.07% | $2,142,249.86
40.09% | $1,555,136.91

Bid Items

Items: 38, 0 filtered
PALO PINTO VA  |  FORT WORTH  |  0902-39-035  |  12/03/2020  |  $3,578,993  |  C 902-39-35  |  STATE PARK IMPRVS  |  93 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate JAY MILLS CONTRACTING, INCORPORATED ZACHRY CONSTRUCTION CORPORATION INTEGRITY SERVICES, LLC A. L. HELMCAMP, INC. ACCELERATED CRITICAL PATH, INC. KIEWIT INFRASTRUCTURE SOUTH CO.
100 6001 PREPARING ROW AC 23.980 $7,300.000 $5,400.000 $13,782.000 $5,760.340 $16,180.000 $18,000.000 $20,000.000
105 6043 REMOVING STAB BASE & ASPH PAV (0-6") SY 7,387.000 $2.600 $4.700 $6.000 $3.270 $4.000 $7.000 $4.000
106 6002 OBLITERATING ABANDONED ROAD SY 7,387.000 $5.800 $6.250 $3.000 $5.170 $2.000 $3.000 $6.000
110 6001 EXCAVATION (ROADWAY) CY 23,573.000 $10.000 $12.000 $13.500 $22.450 $16.000 $9.000 $19.000
132 6007 EMBANKMENT (FINAL)(ORD COMP)(TY D) CY 13,672.000 $15.000 $5.000 $5.000 $7.970 $10.000 $4.000 $9.000
161 6017 COMPOST MANUF TOPSOIL (4") SY 46,222.000 $1.700 $1.150 $2.000 $3.410 $1.100 $3.000 $1.450
164 6002 BROADCAST SEED (PERM) (RURAL) (SANDY) AC 9.550 $1,200.000 $880.000 $650.000 $880.000 $500.000 $850.000 $1,158.370
164 6010 BROADCAST SEED (TEMP) (WARM) AC 9.550 $400.000 $550.000 $550.000 $556.600 $250.000 $520.000 $723.980
164 6012 BROADCAST SEED (TEMP) (COOL) AC 9.550 $400.000 $550.000 $550.000 $556.600 $300.000 $520.000 $723.980
168 6001 VEGETATIVE WATERING MG 1,618.000 $20.000 $17.000 $28.000 $27.500 $10.000 $29.000 $36.200
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 6,294.790 $55.000 $56.000 $21.000 $51.210 $40.000 $64.000 $75.870
260 6005 LIME (QUICKLIME (SLURRY)) TON 1,439.000 $162.680 $192.500 $170.000 $216.000 $205.000 $145.000 $174.180
260 6073 LIME TRT (SUBGRADE)(8") SY 78,331.000 $3.800 $3.000 $5.150 $2.760 $3.900 $3.000 $6.590
275 6001 CEMENT TON 1,200.000 $170.000 $152.000 $160.000 $152.670 $100.000 $180.000 $210.000
275 6010 CEMENT TREAT (SUBGRADE) (8") SY 19,583.000 $5.900 $2.500 $5.100 $1.760 $3.000 $4.800 $5.000
276 6152 CEM TRT(PLNT MX) (CL N)(TY A)(GR 4) TON 407.970 $60.000 $100.000 $145.000 $35.000 $70.000 $193.000 $126.220
310 6009 PRIME COAT (MC-30) GAL 22,661.000 $4.500 $4.000 $4.000 $4.400 $3.500 $4.000 $4.920
316 6024 ASPH (CRS-2P) GAL 30,445.000 $4.100 $3.500 $3.500 $3.470 $3.000 $3.000 $3.810
316 6078 AGGR(TY-B GR-4 SAC-A) CY 403.000 $250.000 $120.000 $165.000 $241.500 $175.000 $240.000 $220.000
403 6001 TEMPORARY SPL SHORING SF 25,510.000 $20.000 $20.400 $12.000 $20.350 $28.500 $23.000 $31.190
432 6014 RIPRAP (STONE TY R)(DRY)(6 IN) CY 300.000 $100.000 $120.000 $145.000 $110.000 $95.000 $120.000 $199.660
460 6002 CMP (GAL STL 18 IN) LF 460.000 $70.000 $45.000 $80.000 $57.200 $80.000 $39.000 $100.000
460 6003 CMP (GAL STL 24 IN) LF 320.000 $80.000 $50.000 $100.000 $115.500 $81.000 $49.000 $125.000
467 6348 SET (TY II) (18 IN) (CMP) (6: 1) (P) EA 4.000 $1,100.000 $1,000.000 $3,000.000 $1,100.000 $900.000 $690.000 $3,000.000
500 6001 MOBILIZATION LS 1.000 $351,190.640 $320,000.000 $336,276.000 $422,133.350 $350,000.000 $420,000.000 $710,816.850
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $9,700.000 $3,000.000 $3,500.000 $700.000 $8,500.000 $1,000.000 $20,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 50.000 $28.000 $55.000 $35.000 $55.000 $35.000 $33.000 $72.400
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 35.000 $30.000 $55.000 $46.000 $55.000 $45.000 $35.000 $72.400
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 50.000 $60.000 $82.500 $55.000 $82.500 $65.000 $48.000 $108.600
506 6011 ROCK FILTER DAMS (REMOVE) LF 135.000 $10.000 $22.000 $10.000 $22.000 $15.000 $17.000 $28.960
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 166.660 $23.000 $27.500 $15.000 $27.500 $22.000 $28.000 $36.200
506 6024 CONSTRUCTION EXITS (REMOVE) SY 166.660 $9.000 $11.000 $5.250 $11.000 $5.000 $15.000 $14.480
506 6025 EXCAV (EROSN & SEDMT CONT, IN PLACE) CY 30.000 $25.000 $50.000 $200.000 $25.000 $35.000 $80.000 $398.030
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 350.000 $2.500 $3.300 $3.000 $3.300 $4.500 $2.500 $4.340
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 350.000 $0.650 $1.100 $1.600 $1.100 $1.500 $1.000 $1.450
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 100.000 $5.200 $6.600 $7.000 $6.600 $6.500 $3.000 $8.690
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 100.000 $1.600 $1.100 $3.500 $1.100 $1.500 $1.000 $1.450
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 4,095.000 $50.000 $72.000 $75.000 $73.800 $75.000 $70.000 $96.320
Totals: $3,578,993.13 $3,292,351.10 $3,443,797.91 $3,812,697.10 $3,862,545.82 $3,879,464.05 $5,434,601.00