ORANGE FM1135 (6403-74-001)

Items: 30

County: ORANGE
Length: N/A
Highway: FM1135
District: BEAUMONT
Control Number: 6403-74-001
DBE Goal: N/A
Project: RMC - 640374001
Guaranty: N/A
Time: 180 W
Engineer's Estimate: $1,170,807.44
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: ACP OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (2)
E
Engineer's Estimate
$1,170,807.44
$1,387,550.10
Over/Under Est: 18.51% $216,742.66
Over/Under Est: 21.94% $256,908.10
Amt Left: 2.89% $40,165.44

Bid Items & Bid Tabulations

30 Total 0 of 30
ORANGE  |  FM1135  |  BEAUMONT  |  6403-74-001  |  08/04/2022  |  $1,170,807.44  |  RMC - 640374001  |  ACP OVERLAY  |  180 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
BACKFILL (TY A)
STA 212.000 $180.000 $222.000 $250.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 2,102.000 $75.000 $88.000 $75.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,300.000 $4.000 $4.250 $3.100
RIPRAP (MOW STRIP)(4 IN)
CY 16.000 $1,200.000 $830.000 $800.000
MOBILIZATION
LS 1.000 $106,437.040 $43,610.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $2,190.000 $2,000.000
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 21,049.000 $1.000 $0.420 $0.500
MTL W-BEAM GD FEN (STEEL POST)
LF 72.000 $25.000 $94.000 $50.000
TRANSITION ADJUSTMENT
EA 4.000 $300.000 $510.000 $500.000
SHORT RADIUS
LF 92.000 $40.000 $985.000 $900.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $2,000.000 $1,460.000 $1,400.000
MTL BEAM GD FEN TRANS(THRIE BEAM)28"
EA 4.000 $2,500.000 $2,625.000 $2,475.000
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $300.000 $253.000 $175.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,000.000 $3,025.000 $3,400.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $40.000 $36.250 $35.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 24.000 $25.000 $36.250 $35.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 14.000 $0.600 $5.800 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 557.000 $0.600 $2.100 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 108.000 $0.600 $1.030 $0.940
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 42,193.000 $0.600 $0.530 $0.520
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 5,320.000 $0.600 $0.520 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 13,927.000 $0.600 $0.520 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 124.000 $12.500 $19.950 $19.840
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $600.000 $860.000 $855.000
REFL PAV MRKR TY I-C
EA 7.000 $5.000 $10.150 $10.000
REFL PAV MRKR TY II-A-A
EA 400.000 $5.000 $5.150 $5.100
SP MIXES SP-C SAC-B PG70-22
TON 6,303.000 $110.000 $139.000 $145.000
TACK COAT
GAL 3,347.000 $5.000 $4.400 $5.500
TMA (STATIONARY)
DAY 43.000 $300.000 $302.000 $250.000
TMA (MOBILE OPERATION)
DAY 9.000 $250.000 $302.000 $250.000
Totals: $1,170,807.440 $1,387,550.100 $1,427,715.540