ORANGE CS (0920-30-093)

Items: 34

County: ORANGE
Length: N/A
Highway: CS
District: BEAUMONT
Control Number: 0920-30-093
DBE Goal: N/A
Project: BR 2023(124)
Guaranty: N/A
Time: 46 WORKING DAYS
Engineer's Estimate: $611,982.40
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
BRYCE BROUSSARD
JIM GRISSOM
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$611,982.40
$601,425.00
Over/Under Est: -1.73% -$10,557.40
Over/Under Est: 0.58% $3,526.60
Amt Left: 2.34% $14,084.00
$616,956.18
Over/Under Est: 0.81% $4,973.78
Amt Left: 2.58% $15,531.18
Delta: -0.24% -$1,447.18
Over/Under Est: 20.93% $128,116.60
Amt Left: 23.06% $138,674.00
Delta: -19.96% -$123,142.82
$774,158.15
Over/Under Est: 26.5% $162,175.75
Amt Left: 28.72% $172,733.15
Delta: -4.60% -$34,059.15
Subcontractor Percentage Amount
NEXAS SUPPLY LLC 14.41% $86,590.71
COWBOY ASPHALT SERVICES LLC 4.16% $24,997.73
ODUM SERVICES, LLC 2.38% $14,301.59
INTERSTATE BARRICADES & MARKINGS, INC. 2.10% $12,619.05
DCC CONSTRUCTION AND SERVICES, L.L.C. 1.66% $9,975.06
Total: 24.71% $148,484.14

Bid Items & Bid Tabulations

34 Total 0 of 34
ORANGE  |  CS  |  BEAUMONT  |  0920-30-093  |  03/07/2023  |  $611,982.40  |  BR 2023(124)  |  BRIDGE REPL  |  46 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CROSS PLUS CONSTRUCTION, LLC
NORMAN HIGHWAY CONSTRUCTORS, INC.
TREVWAY, INC.
ELITE CONTRACTORS AND EQUIPMENT LTD
ICON GC, LLC
SUBGRADE WIDENING (ORD COMP)
STA 0.400 $1,000.000 $22,000.000 $20,000.000 $30,000.000 $12,500.000 $57,921.500
EMBANKMENT (VEHICLE)(ORD COMP)(TY A)
CY 88.000 $100.000 $55.000 $105.000 $99.000 $50.000 $243.600
BROADCAST SEED (TEMP) (WARM)
SY 316.000 $1.500 $6.000 $1.000 $7.000 $1.500 $3.000
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 316.000 $1.500 $6.000 $5.500 $7.580 $8.000 $10.600
VEGETATIVE WATERING
MG 0.500 $150.000 $1,100.000 $800.000 $4,500.000 $1,000.000 $8,207.300
CEM STABIL BKFL
CY 165.000 $400.000 $193.000 $115.000 $150.000 $145.000 $82.400
TRENCH EXCAVATION PROTECTION
LF 33.000 $1,500.000 $110.000 $170.000 $100.000 $2,000.000 $29.500
CL E CONC (SEAL SLAB)(NON-REINF)
CY 21.000 $600.000 $440.000 $1,000.000 $200.000 $450.000 $624.600
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 48.000 $250.000 $165.000 $262.000 $650.000 $480.000 $320.700
RIPRAP (MOW STRIP)(4 IN)
CY 11.000 $650.000 $440.000 $700.000 $500.000 $650.000 $897.800
RAIL (TY T223)
LF 152.000 $175.000 $138.000 $345.000 $143.000 $200.000 $325.100
CONC BOX CULV (10 FT X 5 FT)
LF 96.000 $1,300.000 $1,604.000 $1,800.000 $1,500.000 $1,700.000 $1,815.500
WINGWALL (PW - 1) (HW=10 FT)
EA 2.000 $30,000.000 $27,500.000 $54,000.000 $50,000.000 $77,000.000 $85,296.300
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $40,000.000 $38,500.000 $26,000.000 $50,000.000 $31,000.000 $34,933.600
MOBILIZATION
LS 1.000 $99,330.400 $55,000.000 $33,000.000 $60,000.000 $78,800.000 $65,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $5,500.000 $1,725.000 $2,000.000 $3,000.000 $5,848.700
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $50.000 $55.000 $49.000 $15.000 $50.000 $113.200
ROCK FILTER DAMS (REMOVE)
LF 100.000 $15.000 $6.000 $12.000 $5.000 $15.000 $77.900
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 310.000 $10.000 $17.000 $6.500 $5.000 $8.000 $23.600
BIODEG EROSN CONT LOGS (REMOVE)
LF 310.000 $3.000 $1.000 $1.000 $1.000 $2.000 $2.400
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $45.000 $55.000 $38.000 $145.800 $40.000 $58.900
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,500.000 $2,750.000 $2,400.000 $3,541.580 $2,500.000 $4,117.800
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,750.000 $4,400.000 $3,500.000 $4,625.370 $3,800.000 $6,470.800
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 2.000 $20,000.000 $44,000.000 $40,000.000 $27,500.000 $38,000.000 $37,648.000
REMOVE SM RD SN SUP&AM
EA 2.000 $200.000 $220.000 $144.000 $200.000 $150.000 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $40.000 $33.000 $20.000 $30.000 $20.000 $35.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 4.000 $60.000 $33.000 $41.000 $30.000 $43.000 $35.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 2.000 $100.000 $33.000 $104.000 $30.000 $110.000 $35.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 152.000 $2.000 $110.000 $4.000 $25.000 $40.000 $6.000
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 20.000 $2.000 $11.000 $6.000 $300.000 $50.000 $6.000
REFL PAV MRKR TY II-A-A
EA 2.000 $40.000 $11.000 $600.000 $500.000 $100.000 $12.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 44.000 $275.000 $550.000 $290.000 $315.000 $250.000 $214.900
TACK COAT
GAL 42.000 $35.000 $165.000 $93.000 $100.000 $20.000 $14.200
D-GR HMA TY-D SAC-A PG70-22 (EXEMPT)
TON 27.000 $275.000 $550.000 $345.000 $911.000 $300.000 $442.800
Totals: $611,982.400 $601,425.000 $615,509.000 $616,956.180 $740,099.000 $774,158.150