ORANGE IH 10 (0028-14-120)

Items: 26

County: ORANGE
Length: N/A
Highway: IH 10
District: BEAUMONT
Control Number: 0028-14-120
DBE Goal: N/A
Project: C 28-14-120
Guaranty: N/A
Time: 92 WORKING DAYS
Engineer's Estimate: $2,609,891.42
Date: 05/04/2022 (4 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$2,609,891.42
$2,592,503.75
Over/Under Est: -0.67% -$17,387.67
Over/Under Est: 3.44% $89,859.34
Amt Left: 4.14% $107,247.01
Over/Under Est: 7.13% $186,137.33
Amt Left: 7.85% $203,525.00
Delta: -3.57% -$96,277.99
Over/Under Est: 14.43% $376,567.73
Amt Left: 15.2% $393,955.40
Delta: -6.81% -$190,430.40

Bid Items & Bid Tabulations

26 Total 0 of 26
ORANGE  |  IH 10  |  BEAUMONT  |  0028-14-120  |  05/04/2022  |  $2,609,891.42  |  C 28-14-120  |  SURF/ROADWAY RESTOR  |  92 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
O. TREVINO CONSTRUCTION, LLC
WINDING ROAD CONSTRUCTION, INC.
SELECT MAINTENANCE, L.L.C.
MAIN LANE INDUSTRIES LTD.
FULL - DEPTH REPAIR CPJR (9")
SY 2,831.000 $480.000 $327.000 $326.500 $280.000 $375.000
FULL - DEPTH REPAIR CPCD (8"-14")
SY 2,693.000 $235.000 $322.000 $316.500 $335.000 $370.000
CLEANING AND SEALING EXISTING JOINTS
LF 21,426.000 $2.650 $2.400 $4.740 $3.000 $2.000
MOBILIZATION
LS 1.000 $109,000.000 $259,000.000 $224,000.000 $278,000.000 $280,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,000.000 $6,300.000 $14,285.000 $46,000.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 442.000 $4.000 $6.000 $15.000 $1.500 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 442.000 $1.510 $1.000 $5.000 $0.500 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 80.000 $9.400 $6.000 $15.000 $6.000 $20.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 80.000 $3.900 $1.000 $7.500 $1.000 $1.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 1,290.000 $1.550 $4.000 $5.060 $0.400 $3.750
WK ZN PAV MRK REMOV (W)8"(DOT)
LF 126.000 $1.500 $6.500 $8.100 $1.000 $6.000
WK ZN PAV MRK REMOV (W)(RR XING)
EA 2.000 $480.000 $1,100.000 $1,350.000 $150.000 $1,000.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 169.000 $1.500 $4.000 $4.730 $1.950 $3.500
PAVEMENT SEALER 4"
LF 2,027.000 $0.500 $0.400 $0.470 $0.200 $0.350
PAVEMENT SEALER 8"
LF 126.000 $0.500 $0.800 $0.950 $0.500 $0.700
PAVEMENT SEALER (RR XING)
EA 2.000 $35.000 $62.000 $74.250 $75.000 $55.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 1,290.000 $0.480 $2.750 $3.380 $1.500 $2.500
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 737.000 $1.700 $2.750 $3.380 $1.500 $2.500
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $546.000 $1,600.000 $2,025.000 $250.000 $1,500.000
REFL PAV MRKR TY II-C-R
EA 74.000 $5.000 $11.000 $13.500 $6.000 $10.000
TRAFFIC BUTTON TY W
EA 338.000 $2.000 $11.000 $13.500 $0.850 $10.000
SPALLING REPAIR (HYDRAULIC CEMENT)
CF 200.000 $400.000 $200.000 $150.000 $350.000 $190.000
CONTINUOUS DIAMOND GRINDING CONC PVMT
SY 14,695.000 $14.500 $16.500 $19.000 $18.000 $20.000
DOWEL BAR RETROFIT
EA 758.000 $115.000 $160.000 $158.000 $100.000 $175.000
TMA (STATIONARY)
DAY 68.000 $360.000 $200.000 $400.000 $250.000 $600.000
TMA (MOBILE OPERATION)
DAY 2.000 $296.000 $450.000 $1,000.000 $1,000.000 $1,200.000
Totals: $2,609,891.420 $2,592,503.750 $2,699,750.760 $2,796,028.750 $2,986,459.150