ORANGE IH 10 (0028-14-116)

Items: 37

County: ORANGE
Length: N/A
Highway: IH 10
District: BEAUMONT
Control Number: 0028-14-116
DBE Goal: N/A
Project: BR 2022(535)
Guaranty: N/A
Time: 103 WORKING DAYS
Engineer's Estimate: $6,832,289.00
Date: 02/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
DAVID COLLINS
TAYLOR KANE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$6,832,289.00
$4,742,240.62
Over/Under Est: -30.59% -$2,090,048.38
Over/Under Est: -16.43% -$1,122,317.20
Amt Left: 20.41% $967,731.18
Over/Under Est: -15.37% -$1,050,336.69
Amt Left: 21.92% $1,039,711.69
Delta: -1.26% -$71,980.51
$12,924,574.90
Over/Under Est: 89.17% $6,092,285.90
Amt Left: 172.54% $8,182,334.28
Delta: -123.53% -$7,142,622.59
Subcontractor Percentage Amount
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 8.54% $404,987.35
TRP CONSTRUCTION GROUP, LLC 4.84% $229,524.45
NELSON INDUSTRIAL SERVICES, INC. 2.07% $98,164.38
BUYERS BARRICADES HOUSTON, LLC 0.66% $31,298.79
Total: 16.11% $763,974.97

Bid Items & Bid Tabulations

37 Total 0 of 37
ORANGE  |  IH 10  |  BEAUMONT  |  0028-14-116  |  02/01/2023  |  $6,832,289.00  |  BR 2022(535)  |  BRIDGE MAINT  |  103 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GIBSON & ASSOCIATES, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
RAGLE CONSTRUCTION, INC.
CEKRA INC.
FLOWABLE BACKFILL
CY 5.000 $500.000 $500.000 $450.000 $450.000 $1,250.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 72,696.000 $12.500 $6.130 $10.000 $3.000 $13.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 816.000 $200.000 $93.000 $250.000 $125.000 $750.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 2,872.000 $400.000 $115.000 $350.000 $135.000 $1,200.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 5.000 $785.000 $500.000 $300.000 $300.000 $4,000.000
CONC STR REPAIR (STANDARD)
SF 5.000 $950.000 $500.000 $300.000 $300.000 $4,000.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 57.000 $50.000 $50.000 $75.000 $40.000 $300.000
CLEANING EXISTING JOINTS
LF 57.000 $20.000 $30.000 $75.000 $40.000 $300.000
MOBILIZATION
LS 1.000 $405,000.000 $490,000.000 $500,000.000 $570,000.000 $1,280,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $20,000.000 $11,100.000 $25,000.000 $80,000.000 $25,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,108.000 $5.000 $12.270 $6.000 $2.500 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,108.000 $1.650 $9.350 $2.000 $1.000 $1.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 2)
LF 5,225.000 $45.000 $47.000 $40.000 $125.000 $100.000
PORT CTB (MOVE)(SGL SLP)(TY 2)
LF 15,675.000 $22.000 $10.500 $20.000 $15.000 $15.000
PORT CTB (REMOVE)(SGL SLP)(TY 2)
LF 5,225.000 $15.000 $37.000 $40.000 $15.000 $8.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $1,900.000 $2,500.000 $2,000.000 $2,500.000 $5,000.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,600.000 $2,500.000 $1,500.000 $1,200.000 $5,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $20,000.000 $15,000.000 $10,000.000 $9,500.000 $25,000.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 2,967.000 $3.000 $2.640 $2.500 $0.790 $2.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 41,474.000 $2.000 $1.490 $1.400 $0.790 $1.800
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 36,068.000 $1.200 $1.490 $1.400 $0.790 $1.800
RE PV MRK TY I(BLACK)6"(SHADOW)(090MIL)
LF 1,809.000 $1.500 $3.850 $4.000 $2.000 $5.000
PAVEMENT SEALER 6"
LF 39,805.000 $0.260 $0.400 $0.500 $0.250 $0.500
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 1,809.000 $1.000 $1.050 $1.000 $1.250 $0.800
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 18,093.000 $1.500 $0.900 $1.000 $1.250 $0.800
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 18,093.000 $1.500 $0.900 $1.000 $1.250 $0.800
REFL PAV MRKR TY II-C-R
EA 227.000 $5.200 $9.080 $10.000 $8.000 $8.000
ELIM EXT PAV MRK & MRKS (6")
LF 38,904.000 $0.500 $1.300 $1.250 $0.500 $0.800
PAV SURF PREP FOR MRK (6")
LF 38,896.000 $0.750 $0.360 $0.500 $0.200 $0.100
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 11,491.000 $30.000 $11.200 $10.000 $35.000 $38.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 18.000 $275.000 $200.000 $135.000 $150.000 $800.000
BRIDGE JOINT REPAIR (SEJ)
LF 1,482.000 $100.000 $164.000 $100.000 $200.000 $275.000
PRECAST PANEL SUPPORT
LF 6,484.000 $100.000 $137.500 $100.000 $40.000 $525.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 9,560.000 $200.000 $117.310 $120.000 $187.900 $105.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 37.000 $600.000 $200.000 $150.000 $250.000 $140.000
TMA (STATIONARY)
DAY 37.000 $400.000 $300.000 $200.000 $500.000 $450.000
TMA (MOBILE OPERATION)
DAY 8.000 $1,130.000 $500.000 $200.000 $900.000 $850.000
Totals: $6,832,289.000 $4,742,240.620 $5,709,971.800 $5,781,952.310 $12,924,574.900