Bid Cobra

OCHILTREE CR (0904-04-007)

Items: 32

County: OCHILTREE
Length: N/A
Highway: CR
District: AMARILLO
Control Number: 0904-04-007
DBE Goal: N/A
Project: BR 2021(971)
Guaranty: N/A
Time: 70 WORKING DAYS
Engineer's Estimate: $737,379.00
Date: 03/08/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ZACHARY MAYER
KENNETH PETR
THOMAS NAGEL
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$737,379.00
$809,347.54
Over/Under Est: 9.76% $71,968.54
Over/Under Est: 34.85% $256,964.15
Amt Left: 22.86% $184,995.61
Over/Under Est: 51.36% $378,691.00
Amt Left: 37.9% $306,722.46
Delta: -12.24% -$121,726.85
$1,246,365.00
Over/Under Est: 69.03% $508,986.00
Amt Left: 54% $437,017.46
Delta: -11.67% -$130,295.00
$1,327,338.80
Over/Under Est: 80.01% $589,959.80
Amt Left: 64% $517,991.26
Delta: -6.50% -$80,973.80

Bid Items & Bid Tabulations

32 Total 0 of 32
OCHILTREE  |  CR  |  AMARILLO  |  0904-04-007  |  03/08/2023  |  $737,379.00  |  BR 2021(971)  |  BRIDGE REPL  |  70 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
J. LEE MILLIGAN, INC.
L A FULLER & SONS CONSTRUCTION, LTD.
EARTH BUILDERS, L.P.
DIGG COMMERCIAL, LLC
PREPARING ROW (TREE) (0" TO 6" DIA)
EA 6.000 $150.000 $500.000 $265.000 $1,520.000 $1,500.000 $2,449.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 1.000 $400.000 $2,500.000 $1,275.000 $2,475.000 $3,500.000 $4,225.000
REMOVING STAB BASE & ASPH PAV(16")
SY 790.000 $20.000 $20.000 $19.500 $23.700 $25.000 $17.000
EXCAVATION (ROADWAY)
CY 760.000 $20.000 $25.000 $38.000 $23.200 $25.000 $47.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 807.000 $40.000 $25.000 $60.000 $41.400 $45.000 $72.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 0.530 $700.000 $5,500.000 $5,280.000 $2,010.000 $4,000.000 $6,930.000
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 0.530 $600.000 $5,390.000 $5,175.000 $1,000.000 $4,000.000 $6,930.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 1,560.000 $2.000 $2.200 $2.150 $2.500 $6.000 $15.000
FL BS(CMP IN PLC)(TY A,B OR D GR4)(12")
SY 1,210.000 $48.000 $47.000 $33.000 $51.200 $85.000 $94.000
PRIME COAT (MC-30)
GAL 303.000 $10.000 $40.000 $12.000 $9.400 $25.000 $15.000
FLOWABLE BACKFILL
CY 75.000 $175.000 $340.000 $295.000 $328.000 $350.000 $544.000
TEMPORARY SPL SHORING
SF 1,588.000 $50.000 $30.000 $12.500 $25.900 $5.000 $48.000
RIPRAP (CONC)(5 IN)
CY 40.000 $725.000 $650.000 $630.000 $1,150.000 $900.000 $817.000
RIPRAP (MOW STRIP)(4 IN)
CY 36.000 $725.000 $600.000 $690.000 $1,280.000 $900.000 $848.000
GABION MATTRESSES (GALV)(12 IN)
SY 258.000 $80.000 $240.000 $130.000 $183.000 $200.000 $180.000
GABION MATTRESSES (GALV) (24 IN)
SY 65.000 $200.000 $240.000 $260.000 $392.000 $300.000 $361.000
CMP (GAL STL 24 IN)
LF 10.000 $100.000 $200.000 $275.000 $243.000 $150.000 $182.000
CONC BOX CULV (7 FT X 7 FT)
LF 96.000 $850.000 $1,822.540 $1,300.000 $2,000.000 $2,500.000 $1,303.000
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $60,000.000 $40,000.000 $115,000.000 $125,060.000 $165,000.000 $118,800.000
REMOV STR (PIPE)
LF 10.000 $20.000 $20.000 $115.000 $26.900 $20.000 $122.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $21,000.000 $20,000.000 $25,000.000 $47,825.000 $35,000.000 $37,961.000
MOBILIZATION
LS 1.000 $62,000.000 $70,000.000 $99,000.000 $111,345.200 $125,000.000 $177,270.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $9,000.000 $4,000.000 $30,000.000 $6,000.000 $2,500.000 $7,345.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 650.000 $7.500 $10.000 $7.500 $3.000 $8.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 650.000 $2.000 $1.000 $2.000 $1.400 $2.000 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $30.000 $38.500 $38.000 $51.600 $45.000 $57.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,350.000 $1,540.000 $1,600.000 $2,185.000 $2,000.000 $4,960.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,300.000 $3,630.000 $3,600.000 $4,870.000 $3,500.000 $6,950.000
REMOVE SM RD SN SUP&AM
EA 2.000 $105.000 $500.000 $110.000 $287.000 $100.000 $464.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $80.000 $50.000 $27.000 $36.000 $65.000 $176.000
SP MIXES SP-D SAC-A PG70-28
TON 266.000 $280.000 $275.000 $255.000 $249.000 $300.000 $500.000
TACK COAT
GAL 157.000 $10.000 $15.000 $10.000 $11.900 $35.000 $15.000
Totals: $737,379.000 $809,347.540 $994,343.150 $1,116,070.000 $1,246,365.000 $1,327,338.800