NUECES FM 70 (1558-01-019)
Items: 75
County: NUECES
Length: N/A
Highway: FM 70
District: CORPUS CHRISTI
Control Number: 1558-01-019
DBE Goal: N/A
Project: C 1558-1-19
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $4,218,584.65
Date: 05/07/2019 (7 years ago)
Contract Number: N/A
Type: RESTORATION OF EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,218,584.65 | |||
| $4,592,254.65 |
8.86%
$373,670.00
|
|||
| $4,799,565.34 |
13.77%
$580,980.69
|
4.51%
$207,310.69
|
||
| $4,896,368.59 |
16.07%
$677,783.94
|
6.62%
$304,113.94
|
-2.02%
-$96,803.25
|
|
|
4
|
$5,121,169.50 |
21.4%
$902,584.85
|
11.52%
$528,914.85
|
-4.59%
-$224,800.91
|
| $5,391,400.30 |
27.8%
$1,172,815.65
|
17.4%
$799,145.65
|
-5.28%
-$270,230.80
|
|
| $6,408,238.66 |
51.9%
$2,189,654.01
|
39.54%
$1,815,984.01
|
-18.86%
-$1,016,838.36
|
E
Engineer's Estimate
$4,218,584.65
1
Awarded
$4,592,254.65
Over/Under Est:
8.86%
$373,670.00
$4,799,565.34
Over/Under Est:
13.77%
$580,980.69
Amt Left:
4.51%
$207,310.69
$4,896,368.59
Over/Under Est:
16.07%
$677,783.94
Amt Left:
6.62%
$304,113.94
Delta:
-2.02%
-$96,803.25
4
$5,121,169.50
Over/Under Est:
21.4%
$902,584.85
Amt Left:
11.52%
$528,914.85
Delta:
-4.59%
-$224,800.91
$5,391,400.30
Over/Under Est:
27.8%
$1,172,815.65
Amt Left:
17.4%
$799,145.65
Delta:
-5.28%
-$270,230.80
$6,408,238.66
Over/Under Est:
51.9%
$2,189,654.01
Amt Left:
39.54%
$1,815,984.01
Delta:
-18.86%
-$1,016,838.36
Bid Items & Bid Tabulations
75
Total
0 of 75