NUECES FM 624 (0989-02-054)

Items: 102

County: NUECES
Length: N/A
Highway: FM 624
District: CORPUS CHRISTI
Control Number: 0989-02-054
DBE Goal: N/A
Project: F 2022(932)
Guaranty: N/A
Time: 255 WORKING DAYS
Engineer's Estimate: $12,650,406.50
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
ERNEST LONGORIA
FIDENCIO LOPEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$12,650,406.50
$10,116,593.44
Over/Under Est: -20.03% -$2,533,813.06
Over/Under Est: -13.34% -$1,687,010.84
Amt Left: 8.37% $846,802.22
$12,344,748.95
Over/Under Est: -2.42% -$305,657.55
Amt Left: 22.02% $2,228,155.51
Delta: -12.60% -$1,381,353.29
$13,123,916.94
Over/Under Est: 3.74% $473,510.44
Amt Left: 29.73% $3,007,323.50
Delta: -6.31% -$779,167.99
$13,930,749.75
Over/Under Est: 10.12% $1,280,343.25
Amt Left: 37.7% $3,814,156.31
Delta: -6.15% -$806,832.81
Subcontractor Percentage Amount
ANDERSON COLUMBIA CO., INC. 30.89% $3,346,413.37
HIGHWAY BARRICADES AND SERVICES, LLC 3.78% $409,499.60
LONE STAR EROSION CONTROL 3.26% $353,166.32
K. L. DURHAM CONSTRUCTION, L.L.C. 1.08% $116,999.88
COLD CREEK CONSTRUCTION, LTD 1.02% $110,499.89
EPIC ENERGY SERVICES LLC 0.20% $21,666.65
WEST TEXAS ROCK RESOURCES, LLC 0.12% $12,999.99
BROOKE PAVING AND CONSTRUCTION LLC 0.07% $7,583.33
CHEROKEE SERVICES 0.06% $6,499.99
Total: 40.48% $4,385,329.02

Bid Items & Bid Tabulations

102 Total 0 of 102
NUECES  |  FM 624  |  CORPUS CHRISTI  |  0989-02-054  |  08/03/2022  |  $12,650,406.50  |  F 2022(932)  |  SURF/ROADWAY RESTOR  |  255 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HAAS-ANDERSON CONSTRUCTION, LTD.
J E CONSTRUCTION SERVICES, LLC
BAY LTD.
CK NEWBERRY, LLC
HUNTER INDUSTRIES, LTD.
PREPARING ROW
STA 329.400 $641.200 $495.000 $94.000 $920.000 $500.000 $2,015.000
EXCAVATION (ROADWAY)
CY 30,201.000 $15.000 $6.600 $10.000 $11.000 $15.000 $21.600
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 14,718.000 $15.000 $9.800 $3.500 $11.000 $13.000 $19.440
BACKFILL (TY A OR B)
STA 225.000 $100.000 $188.000 $90.000 $260.000 $525.000 $175.950
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 21.500 $1,000.000 $1,410.000 $1,400.000 $1,900.000 $1,500.000 $1,200.000
FERTILIZER
TON 6.700 $1,500.000 $2,000.000 $890.000 $1,200.000 $1,200.000 $1,000.000
VEGETATIVE WATERING
MG 1,681.700 $15.000 $24.000 $17.000 $16.000 $18.000 $23.940
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 7,600.000 $75.000 $92.000 $100.000 $111.000 $135.000 $108.860
LIME (HYD, COM OR QK)(SLURRY)
TON 792.000 $200.000 $196.000 $308.000 $290.000 $215.000 $270.000
LIME TRT (SUBGRADE)(8")
SY 35,433.000 $3.250 $6.650 $3.000 $6.500 $5.000 $3.510
PRIME COAT (MC-30)
GAL 6,567.000 $6.000 $5.200 $5.000 $5.000 $5.250 $6.340
ASPH (MULTI OPTION)
GAL 11,495.000 $4.000 $3.700 $4.000 $5.500 $5.500 $4.930
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 2,085.000 $140.000 $160.000 $158.000 $235.000 $160.000 $173.130
ASPH (AC-15P OR AC-20-5TR)
GAL 69,878.000 $4.500 $4.350 $5.000 $5.250 $5.000 $5.490
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 3,775.000 $45.000 $42.000 $55.000 $65.000 $105.000 $61.620
PLANE ASPH CONC PAV(0" TO 2")
SY 166,103.000 $1.500 $1.700 $1.000 $1.350 $3.000 $2.160
CEM STABIL BKFL
CY 1.490 $150.000 $245.000 $134.000 $480.000 $350.000 $1,000.000
FLOWABLE BACKFILL
CY 3.720 $200.000 $310.000 $179.000 $1,450.000 $500.000 $1,000.000
CONC STR REPAIR (STANDARD)
SF 16.500 $162.500 $456.000 $450.000 $1,550.000 $350.000 $725.000
RIPRAP (CONC)(5 IN)
CY 24.000 $471.300 $760.000 $570.000 $775.000 $600.000 $750.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 311.000 $200.000 $210.000 $100.000 $200.000 $225.000 $250.000
RIPRAP (MOW STRIP)(4 IN)
CY 45.000 $550.000 $643.970 $530.000 $565.000 $600.000 $850.000
CLEANING AND SEALING EXISTING JOINTS
LF 88.000 $24.070 $95.000 $44.000 $105.000 $125.000 $129.450
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 24.000 $550.000 $693.000 $448.000 $1,275.000 $600.000 $750.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 124.000 $750.000 $811.000 $555.000 $750.000 $900.000 $1,050.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 300.000 $892.860 $852.000 $747.000 $1,000.000 $850.000 $1,400.000
RC PIPE (CL III)(18 IN)
LF 237.000 $70.000 $100.120 $89.000 $80.000 $100.000 $120.000
RC PIPE (CL III)(24 IN)
LF 352.000 $83.750 $130.000 $100.000 $95.000 $135.000 $260.000
SET (REPLACE PIPE RUNNER)
EA 2.000 $1,518.000 $2,290.000 $1,530.000 $1,350.000 $7,500.000 $4,200.000
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(C)
EA 2.000 $8,500.000 $8,350.000 $10,000.000 $9,000.000 $11,000.000 $8,200.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
EA 14.000 $10,500.000 $10,600.000 $6,000.000 $10,500.000 $11,500.000 $7,400.000
SET (TY I)(S= 6 FT)(HW= 6 FT)(4:1) (C)
EA 17.000 $6,760.290 $15,100.000 $10,000.000 $16,850.000 $14,000.000 $14,000.000
SET (TY I)(S= 6 FT)(HW= 6 FT)(6:1) (C)
EA 17.000 $7,414.040 $16,800.000 $13,600.000 $19,885.000 $16,000.000 $22,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 14.000 $1,200.000 $2,050.000 $2,000.000 $1,900.000 $2,300.000 $3,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 3.000 $2,145.500 $2,100.000 $2,400.000 $1,750.000 $3,000.000 $4,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 52.000 $1,800.000 $2,100.000 $2,400.000 $1,785.000 $2,500.000 $4,200.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 32.000 $2,500.000 $5,110.000 $4,700.000 $4,400.000 $4,000.000 $5,500.000
REMOV & RE - LAY PIPE (30 IN)
LF 344.000 $60.000 $109.000 $65.000 $200.000 $100.000 $150.000
CLEAN EXIST CULVERTS
EA 11.000 $2,500.000 $2,450.000 $733.000 $12,400.000 $3,500.000 $2,500.000
REMOV STR (SET)
EA 92.000 $350.000 $368.000 $1,557.000 $340.000 $500.000 $500.000
REMOV STR (PIPE)
LF 1,186.000 $20.000 $19.000 $25.000 $34.000 $30.000 $16.000
MOBILIZATION
LS 1.000 $1,000,000.000 $575,000.000 $542,000.000 $208,025.000 $950,000.000 $1,316,092.630
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $10,000.000 $8,830.000 $1,700.000 $9,000.000 $12,000.000 $5,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,946.000 $3.000 $3.600 $4.000 $6.000 $4.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,946.000 $1.000 $1.100 $1.000 $1.750 $1.500 $2.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 14,550.000 $40.000 $31.000 $83.000 $16.000 $75.000 $88.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 6,420.000 $15.000 $11.000 $11.000 $13.000 $20.000 $15.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 14,550.000 $25.000 $13.000 $12.000 $15.000 $15.000 $15.000
DRIVEWAYS (CONC)
SY 132.000 $100.210 $101.000 $110.000 $160.000 $206.820 $150.000
DRIVEWAYS (ACP)(TYPE 1)
SY 4,102.000 $40.000 $73.000 $47.000 $92.000 $50.000 $75.240
DRIVEWAYS (ACP) (TYPE 2)
SY 1,310.000 $40.000 $49.000 $39.000 $143.000 $45.000 $75.240
RUMBLE STRIPS (SHOULDER)
LF 65,874.000 $0.180 $0.200 $0.120 $0.300 $0.100 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 32,937.000 $0.180 $0.300 $0.120 $0.350 $0.150 $0.200
MTL W-BEAM GD FEN (TIM POST)
LF 375.000 $30.000 $30.000 $35.000 $35.000 $35.000 $32.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $1,840.000 $1,800.000 $2,200.000 $2,500.000 $2,150.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 4.000 $850.000 $1,050.000 $1,000.000 $1,075.000 $1,700.000 $950.000
REMOVE METAL BEAM GUARD FENCE
LF 2,590.000 $2.000 $2.200 $3.000 $8.000 $3.000 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,250.000 $3,440.000 $4,000.000 $3,600.000 $4,250.000 $3,600.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 26.000 $2,000.000 $832.000 $1,600.000 $3,350.000 $1,100.000 $1,450.000
CRASH CUSH ATTEN (REMOVE)
EA 30.000 $1,000.000 $388.000 $830.000 $620.000 $1,200.000 $750.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 30.000 $12,000.000 $8,760.000 $8,800.000 $11,430.000 $12,000.000 $7,950.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 7.000 $250.000 $249.000 $250.000 $245.000 $500.000 $225.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $638.260 $748.000 $750.000 $940.000 $1,000.000 $675.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 39.000 $750.000 $804.000 $807.000 $775.000 $850.000 $725.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 16.000 $1,000.000 $943.000 $945.000 $810.000 $900.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 19.000 $1,000.000 $1,010.000 $1,000.000 $958.000 $1,250.000 $915.000
REMOVE SM RD SN SUP&AM
EA 65.000 $75.000 $78.000 $78.000 $56.000 $150.000 $70.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 10.000 $200.000 $249.000 $250.000 $860.000 $1,000.000 $225.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 74.000 $125.000 $83.000 $83.000 $64.000 $100.000 $75.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $35.000 $31.000 $31.000 $50.000 $50.000 $28.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 80,000.000 $0.250 $0.500 $0.500 $0.500 $0.500 $0.430
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 80,000.000 $0.250 $0.500 $0.500 $0.500 $0.500 $0.430
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 61.000 $4.000 $3.350 $3.300 $3.500 $3.500 $3.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 755.000 $4.000 $3.350 $3.300 $3.500 $3.500 $3.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 55,727.000 $1.000 $0.500 $0.500 $0.500 $0.600 $0.450
WK ZN PAV MRK REMOV (W)8"(DOT)
LF 1,100.000 $2.500 $1.000 $1.000 $1.000 $1.100 $0.900
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 1,205.000 $2.000 $1.000 $1.000 $1.000 $1.100 $0.900
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 59,714.000 $1.000 $0.500 $0.500 $0.500 $0.750 $0.450
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,793.000 $2.000 $1.500 $1.000 $3.000 $5.000 $1.970
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,000.000 $2.000 $1.500 $1.000 $3.000 $5.000 $1.970
REFL PAV MRK TY I (W)4"(LNDP)(090MIL)
LF 187.000 $0.680 $0.500 $0.500 $0.500 $0.500 $0.450
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 7,926.000 $1.000 $1.000 $1.000 $1.000 $1.000 $0.900
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 148.000 $10.000 $18.000 $17.000 $17.500 $20.000 $16.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 912.000 $0.390 $0.550 $0.500 $0.550 $0.600 $0.480
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 64,523.000 $3.000 $0.500 $0.500 $0.500 $0.500 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 4,521.000 $0.300 $0.500 $0.500 $0.500 $0.500 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 74,795.000 $0.300 $0.500 $0.500 $0.500 $0.500 $0.450
PREFAB PAV MRK TY C (W) (ARROW)
EA 26.000 $200.000 $222.000 $222.000 $225.000 $250.000 $200.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 2.000 $466.770 $388.000 $389.000 $360.000 $400.000 $350.000
PREFAB PAV MRK TY C (W) (WORD)
EA 26.000 $250.000 $305.000 $300.000 $300.000 $350.000 $275.000
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 19.000 $23.670 $13.000 $13.000 $13.000 $14.000 $12.000
REFL PAV MRKR TY I-C
EA 490.000 $3.000 $3.900 $4.000 $3.500 $4.000 $3.500
REFL PAV MRKR TY II-A-A
EA 2,056.000 $4.000 $3.350 $4.000 $3.500 $4.000 $3.000
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
EA 5.000 $1,274.320 $9,170.000 $9,000.000 $9,000.000 $10,000.000 $8,270.000
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 5.000 $737.060 $721.000 $720.000 $700.000 $1,000.000 $650.000
TREE AND BRUSH REMOVAL
AC 78.000 $20,000.000 $500.000 $1,900.000 $6,400.000 $750.000 $540.000
D-GR HMA TY-D SAC-B PG70-22
TON 23,229.000 $140.000 $113.000 $145.000 $153.000 $138.000 $126.000
TACK COAT
GAL 15,621.000 $4.000 $4.050 $5.000 $3.250 $6.000 $4.550
BIRD EXCLUSION METHOD
SF 6,184.000 $5.000 $6.400 $3.000 $11.000 $6.000 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $22,500.000 $6,000.000 $22,000.000 $30,000.000 $7,500.000
TMA (STATIONARY)
DAY 68.000 $215.000 $205.000 $156.000 $348.000 $300.000 $350.000
TMA (MOBILE OPERATION)
DAY 204.000 $450.000 $686.000 $417.000 $315.000 $100.000 $750.000
Totals: $12,650,406.520 $10,116,593.440 $10,963,395.660 $12,344,748.950 $13,123,916.940 $13,930,749.758