Show Job Controls
Bid Cobra

NUECES SH 358 (0617-01-205)

Items: 97

County: NUECES
Length: N/A
Highway: SH 358
District: CORPUS CHRISTI
Control Number: 0617-01-205
DBE Goal: N/A
Project: F 2021(878)
Guaranty: N/A
Time: 276 WORKING DAYS
Engineer's Estimate: $2,939,377.93
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (6)
E
Engineer's Estimate
$2,939,377.93
$2,547,784.79
Over/Under Est: -13.32% -$391,593.14
$3,404,149.99
Over/Under Est: 15.81% $464,772.06
Amt Left: 33.61% $856,365.20
$3,645,746.30
Over/Under Est: 24.03% $706,368.37
Amt Left: 43.09% $1,097,961.51
Delta: -7.10% -$241,596.31
$3,656,904.02
Over/Under Est: 24.41% $717,526.09
Amt Left: 43.53% $1,109,119.23
Delta: -0.31% -$11,157.72
$4,069,678.15
Over/Under Est: 38.45% $1,130,300.22
Amt Left: 59.73% $1,521,893.36
Delta: -11.29% -$412,774.13
$4,249,999.99
Over/Under Est: 44.59% $1,310,622.06
Amt Left: 66.81% $1,702,215.20
Delta: -4.43% -$180,321.84
Subcontractor Percentage Amount
PBJ CONSTRUCTION 12.14% $346,857.15
ABEL'S PAVING & CONSTRUCTION, INC. 12.14% $346,857.15
TRAF-TEX, INC. 9.40% $268,571.44
HIGHWAY BARRICADES AND SERVICES, LLC 6.72% $192,000.00
ONE WAY CONCRETE CONSTRUCTION, LLC 6.21% $177,428.58
AREA WIDE PROTECTIVE, INC. 0.87% $24,857.14
ROBIN STEEL LLC 0.15% $4,285.71
Total: 47.63% $1,360,857.17

Bid Items & Bid Tabulations

97 Total 0 of 97
NUECES  |  SH 358  |  CORPUS CHRISTI  |  0617-01-205  |  08/05/2021  |  $2,939,377.93  |  F 2021(878)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  276 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, INC.
MAKO CONTRACTING, LLC
ENCINO LANDSCAPE, INC.
BAY LTD.
ALTUS CONSTRUCTION LLC
CLORE EQUIPMENT LLC
REMOVING CONC (RIPRAP)
SY 20.000 $8.800 $35.000 $20.000 $20.000 $32.000 $35.960 $50.600
REMOVING CONC (MEDIANS)
SY 6.000 $18.800 $25.000 $72.000 $20.000 $35.000 $143.840 $84.340
REMOVING CONC (DRIVEWAYS)
SY 3,406.000 $15.000 $30.000 $28.000 $30.000 $34.000 $12.890 $6.640
REMOVING CONC (CURB OR CURB & GUTTER)
LF 2,642.000 $8.000 $10.000 $10.000 $20.000 $5.700 $10.860 $3.180
REMOVING CONC (SIDEWALK OR RAMP)
SY 308.000 $20.000 $23.000 $25.000 $20.000 $36.000 $10.980 $9.350
REMOVING CONC (FLUME)
SY 2.000 $16.610 $35.000 $25.000 $20.000 $110.000 $611.330 $127.080
REMOVING STAB BASE AND ASPH PAV(0"-16")
SY 1,944.000 $25.000 $30.000 $14.000 $20.000 $21.000 $11.420 $14.610
EXCAVATION (SPECIAL)
CY 660.000 $25.000 $25.000 $20.000 $20.000 $18.250 $23.850 $23.740
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 295.000 $40.000 $25.000 $30.000 $20.000 $59.000 $11.550 $32.090
FURNISHING AND PLACING TOPSOIL (4")
SY 2,562.000 $1.400 $5.000 $10.000 $2.000 $6.300 $1.180 $11.310
GENERAL USE COMPOST (4")
SY 21.000 $10.000 $10.000 $50.000 $4.000 $13.000 $35.960 $123.330
BLOCK SODDING
SY 2,562.000 $5.000 $5.000 $6.250 $4.000 $7.900 $7.510 $6.060
MULCH SODDING
SY 21.000 $5.000 $10.000 $100.000 $50.000 $7.900 $71.920 $10.630
VEGETATIVE WATERING
MG 43.600 $21.440 $1.000 $800.000 $5.000 $80.000 $44.210 $333.280
D-GR HMA (SQ) TY-D PG 70-22(LEVEL-UP)
TON 163.600 $250.000 $225.000 $241.500 $100.000 $250.000 $296.980 $106.890
TACK COAT
GAL 117.000 $6.690 $5.000 $9.600 $8.000 $12.000 $8.940 $14.750
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,469.000 $4.000 $20.000 $57.500 $2.000 $40.000 $5.320 $1.300
CUT & RESTORE ASPH PAVING
SY 1,326.000 $95.000 $95.000 $253.000 $150.000 $110.000 $116.700 $178.530
CL A CONC (MISC)
CY 20.000 $990.900 $650.000 $350.000 $800.000 $700.000 $1,182.130 $464.700
CL A CONC (FLUME)
CY 1.000 $1,600.570 $650.000 $500.000 $1,000.000 $1,000.000 $1,726.120 $464.700
RAIL (HANDRAIL)(TY E)
LF 72.000 $135.000 $150.000 $130.000 $500.000 $400.000 $202.780 $93.300
GRATE & FRAME
EA 9.000 $1,500.000 $1,500.000 $3,500.000 $4,500.000 $3,000.000 $1,134.880 $2,455.340
ADJUSTING MANHOLES
EA 2.000 $790.000 $700.000 $3,500.000 $800.000 $1,500.000 $1,575.750 $1,930.770
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 3.000 $390.000 $500.000 $3,000.000 $800.000 $1,500.000 $909.480 $467.070
REMOV STR (SMALL FENCE)
LF 83.000 $3.880 $17.000 $8.000 $6.000 $10.000 $18.110 $7.190
REMOVE STR (RAIL)
LF 19.000 $27.230 $25.000 $100.000 $25.000 $100.000 $54.360 $15.710
MOBILIZATION
LS 1.000 $217,454.000 $180,000.000 $120,000.000 $300,000.000 $120,000.000 $395,568.240 $414,533.550
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $7,500.000 $1,000.000 $2,823.000 $7,000.000 $14,500.000 $35,960.750 $1,975.470
SANDBAGS FOR EROSION CONTROL
EA 2,060.000 $5.000 $0.100 $15.000 $10.000 $4.000 $8.060 $5.060
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,060.000 $5.000 $0.100 $3.750 $3.000 $5.000 $2.960 $3.820
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,060.000 $1.500 $0.100 $2.500 $1.000 $2.250 $0.920 $0.570
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,060.000 $5.070 $0.100 $5.500 $6.000 $7.000 $4.950 $7.330
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,060.000 $1.680 $0.100 $1.000 $2.000 $1.500 $1.440 $1.120
CONC CURB (TY II)
LF 1,014.000 $25.000 $35.000 $25.000 $20.000 $30.000 $21.460 $21.630
CONC CURB & GUTTER (TY I)
LF 3,392.000 $23.420 $35.000 $25.000 $25.000 $33.000 $29.850 $32.030
CONC CURB & GUTTER (TY II)
LF 2,084.000 $30.000 $35.000 $25.000 $30.000 $37.000 $29.700 $36.670
DRIVEWAYS (CONC)
SY 3,359.000 $95.000 $95.000 $75.000 $100.000 $140.000 $75.140 $143.650
CONC SIDEWALKS (4")
SY 4,547.000 $65.000 $80.000 $75.000 $100.000 $97.000 $64.520 $76.800
CONC SIDEWALKS (5")
SY 289.000 $77.160 $95.000 $75.000 $100.000 $110.000 $83.060 $80.520
CURB RAMPS (TY 1)
SY 819.000 $100.000 $115.000 $225.000 $100.000 $180.000 $263.430 $641.680
CURB RAMPS (TY 2)
SY 119.000 $120.000 $115.000 $225.000 $100.000 $300.000 $165.600 $374.270
CURB RAMPS (TY 3)
SY 497.000 $150.000 $115.000 $225.000 $100.000 $200.000 $172.790 $577.080
CURB RAMPS (TY 5)
SY 15.000 $150.000 $115.000 $225.000 $100.000 $220.000 $259.820 $441.830
CURB RAMPS (TY 6)
SY 84.000 $120.000 $115.000 $225.000 $100.000 $150.000 $190.060 $390.660
CURB RAMPS (TY 7)
SY 582.000 $110.000 $115.000 $225.000 $100.000 $190.000 $201.360 $503.380
CURB RAMPS (TY 20)
SY 73.000 $120.000 $115.000 $225.000 $100.000 $200.000 $190.060 $704.710
CURB RAMPS (TY 21)
SY 125.000 $120.000 $115.000 $225.000 $100.000 $230.000 $228.900 $1,022.720
CURB RAMPS (TY 22)
SY 249.000 $150.000 $115.000 $225.000 $100.000 $200.000 $169.430 $464.170
CONC SIDEWALKS (SPECIAL) (TYPE B)
SY 119.000 $150.000 $250.000 $200.000 $150.000 $200.000 $223.020 $48.460
CONCRETE SIDEWALK (STEPS)
SY 11.000 $410.860 $200.000 $225.000 $500.000 $700.000 $458.810 $37.700
CONC DIRECTIONAL ISLAND
SY 1,077.000 $100.000 $75.000 $85.000 $150.000 $200.000 $95.400 $61.790
CONDT (PVC) (SCH 40) (2")
LF 688.000 $15.000 $32.000 $23.000 $15.000 $38.000 $41.340 $28.740
CONDT (PVC) (SCH 40) (2") (BORE)
LF 172.000 $35.000 $36.000 $36.800 $20.000 $43.000 $47.140 $32.770
CONDT (PVC) (SCH 80) (2")
LF 57.000 $10.100 $32.000 $24.730 $20.000 $38.000 $41.710 $29.000
ELEC CONDR (NO.8) BARE
LF 807.000 $1.200 $1.500 $4.600 $2.000 $2.000 $1.900 $1.320
GROUND BOX TY D (162922)
EA 9.000 $1,200.000 $900.000 $1,288.000 $900.000 $1,200.000 $1,160.810 $807.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 6.000 $575.000 $500.000 $1,620.000 $700.000 $1,800.000 $1,294.590 $1,128.180
RELOCATE SM RD SN SUP&AM TY S80
EA 20.000 $700.000 $500.000 $1,140.000 $600.000 $1,200.000 $791.140 $573.810
PAVEMENT SEALER 4"
LF 157.000 $0.500 $0.300 $0.300 $0.500 $0.400 $0.220 $0.250
PAVEMENT SEALER 8"
LF 4,505.000 $1.000 $0.500 $0.600 $0.500 $0.700 $0.500 $0.500
PAVEMENT SEALER 12"
LF 837.000 $2.000 $0.800 $0.900 $2.000 $1.000 $0.860 $0.750
PAVEMENT SEALER 24"
LF 10,114.000 $3.000 $1.500 $1.800 $5.000 $1.950 $1.730 $1.500
PAVEMENT SEALER (YLD TRI)
EA 27.000 $80.000 $10.000 $12.000 $30.000 $13.000 $21.580 $10.000
PREFAB PAV MRK TY C (W) (4") (BRK)
LF 157.000 $2.000 $2.000 $2.400 $2.000 $2.600 $5.640 $2.000
PREFAB PAV MRK TY C (W) (8") (SLD)
LF 4,505.000 $4.000 $3.000 $3.600 $16.000 $3.900 $8.990 $3.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 837.000 $6.000 $6.000 $7.200 $6.000 $7.900 $10.070 $6.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 10,114.000 $12.000 $13.000 $14.400 $12.000 $15.750 $16.180 $12.000
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 6.000 $30.000 $30.000 $30.000 $30.000 $33.000 $20.140 $25.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 21.000 $40.600 $40.000 $42.000 $35.000 $46.000 $41.710 $35.000
ELIM EXT PAV MRK & MRKS (4")
LF 967.000 $0.810 $0.500 $0.600 $1.000 $3.700 $2.230 $0.500
ELIM EXT PAV MRK & MRKS (8")
LF 2,627.000 $1.070 $1.000 $1.200 $1.000 $1.300 $4.600 $1.000
ELIM EXT PAV MRK & MRKS (12")
LF 10,865.000 $2.590 $1.500 $1.800 $3.000 $1.950 $7.120 $1.500
ELIM EXT PAV MRK & MRKS (24")
LF 4,117.000 $4.800 $3.000 $3.600 $6.000 $3.900 $14.020 $3.000
ELIM EXT PAV MRK & MRKS (18")(YLD TRI)
EA 9.000 $2.750 $5.000 $60.000 $3.000 $6.600 $35.960 $5.000
PAV SURF PREP FOR MRK (4")
LF 157.000 $1.000 $0.010 $0.010 $0.150 $0.020 $3.600 $0.010
PAV SURF PREP FOR MRK (8")
LF 4,505.000 $1.000 $0.020 $0.020 $0.150 $0.070 $0.680 $0.020
PAV SURF PREP FOR MRK (12")
LF 837.000 $1.000 $0.030 $0.040 $1.000 $0.060 $0.930 $0.030
PAV SURF PREP FOR MRK (24")
LF 10,114.000 $1.000 $0.070 $0.070 $1.000 $0.100 $1.940 $0.060
PAV SURF PREP FOR MRK (18")(YLD TRI)
EA 6.000 $2.500 $0.060 $100.000 $5.000 $0.070 $6.470 $0.050
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 21.000 $5.660 $0.170 $100.000 $5.000 $0.240 $10.790 $0.180
PED SIG SEC (LED)(COUNTDOWN)
EA 71.000 $560.440 $500.000 $546.250 $1,000.000 $580.000 $638.660 $444.000
TRF SIG CBL (TY A)(14 AWG)(2 CONDR)
LF 9,388.000 $1.000 $1.700 $1.960 $1.000 $2.000 $2.220 $1.540
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 7,443.000 $2.000 $2.400 $2.190 $2.000 $2.900 $3.190 $2.220
PED POLE ASSEMBLY
EA 38.000 $2,000.000 $1,400.000 $2,587.500 $3,500.000 $1,700.000 $1,819.610 $1,265.000
RELOCATE PED POLE ASSEMBLY
EA 9.000 $2,000.000 $1,600.000 $1,667.500 $2,500.000 $2,000.000 $2,190.730 $1,523.000
PED DETECT PUSH BUTTON (APS)
EA 72.000 $664.370 $700.000 $1,445.000 $800.000 $840.000 $917.720 $638.000
PED DETECTOR CONTROLLER UNIT
EA 7.000 $3,005.850 $4,500.000 $4,347.000 $4,800.000 $5,300.000 $5,827.080 $4,051.000
INSTALL OF VEHICLE DETECTORS
LF 1,030.000 $2.590 $13.000 $13.800 $20.000 $14.750 $16.080 $11.180
REPLACE OF GROUND BOXES
EA 12.000 $2,000.000 $1,000.000 $1,288.000 $900.000 $1,200.000 $1,324.790 $921.000
REMOVAL OF TIMBER POLES
EA 1.000 $292.150 $400.000 $747.500 $500.000 $460.000 $506.330 $352.000
REMOVAL OF PEDESTRIAN PUSH BUTTONS
EA 61.000 $133.130 $70.000 $86.250 $200.000 $79.000 $86.310 $60.000
REMOV PED SIG LED TRAF SIG LAMP UNIT
EA 55.000 $100.000 $130.000 $143.750 $80.000 $150.000 $166.860 $116.000
RELOCATE OF PEDESTRIAN PUSH BUTTON
EA 15.000 $413.250 $130.000 $86.250 $1,000.000 $160.000 $171.170 $119.000
CONC SIDEWALKS (5")(HISTORIC AREAS)
SY 34.000 $100.000 $285.000 $100.000 $500.000 $160.000 $224.060 $119.380
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1,020.000 $117.500 $1.000 $54.000 $100.000 $64.000 $71.800 $32.460
TMA (STATIONARY)
DAY 510.000 $200.000 $1.000 $175.000 $300.000 $30.000 $287.690 $172.910
TMA (MOBILE OPERATION)
DAY 510.000 $240.000 $1.000 $200.000 $300.000 $50.000 $251.730 $172.910
Totals: $2,939,377.934 $2,547,784.790 $3,404,149.990 $3,645,746.300 $3,656,904.020 $4,069,678.164 $4,250,000.002