Job Info for 0983-03-030

County: NOLAN Highway: FM 419 Date: 10/06/2023 (1 year ago) Engineer's Estimate: $3,041,695 Control Number: 0983-03-030
Project: F 2024(170) District: ABILENE Time: 94 WORKING DAYS Type: PREVENTIVE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8
Plans: Plans | Rev 1 | Rev 2 | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,041,695.00
REECE ALBERT, INC.   $3,360,261.38 1
10.47% | $318,566.38
DUININCK, INC.   $3,538,299.19 2
16.33% | $496,604.19
5.3% | $178,037.81
J. H. STRAIN & SONS, INC.   $3,658,542.30 3
20.28% | $616,847.30
8.88% | $298,280.92
3.40% | $120,243.11
BONTKE BROTHERS CONSTRUCTION COMPANY   $3,760,472.50 4
23.63% | $718,777.50
11.91% | $400,211.12
2.79% | $101,930.20
RK HALL, LLC   $3,933,568.59 5
29.32% | $891,873.59
17.06% | $573,307.21
4.60% | $173,096.09
Subcontractor Percentage Amount
CLEARFIELD CONSTRUCTION, LLC 7.91% $265,796.68
DOUBLE A CONTRACTING, L.P. 4.08% $137,098.66
HJC FARMS, INC. 3.14% $105,512.21
K. L. DURHAM CONSTRUCTION, L.L.C. 1.45% $48,723.79
FC TRAFFIC CONTROL, INC. 0.53% $17,809.39
PRIMATE CONSTRUCTION, LP 0.51% $17,137.33
PROFESSIONAL TRAFFIC CONTROL LLC 0.33% $11,088.86
WEST TEXAS ROCK RESOURCES, LLC 0.06% $2,016.16
Total: 18.01% $605,183.08

Bid Items

Items: 55, 0 filtered
NOLAN FM 419  |  ABILENE  |  0983-03-030  |  10/06/2023  |  $3,041,695  |  F 2024(170)  |  PREVENT MAINT  |  94 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate REECE ALBERT, INC. DUININCK, INC. J. H. STRAIN & SONS, INC. BONTKE BROTHERS CONSTRUCTION COMPANY RK HALL, LLC
134 6001 BACKFILL (TY A) STA 121.030 $300.000 $591.400 $345.000 $400.000 $850.000 $100.000
310 6009 PRIME COAT (MC-30) GAL 2,032.000 $8.000 $7.650 $8.600 $8.000 $11.000 $10.950
351 6013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 6,465.000 $60.000 $67.240 $46.000 $75.000 $40.000 $59.650
354 6021 PLANE ASPH CONC PAV(0" TO 2") SY 10,632.000 $6.000 $8.980 $12.500 $7.000 $12.000 $34.270
432 6002 RIPRAP (CONC)(5 IN) CY 14.400 $900.000 $671.420 $980.000 $1,021.000 $925.000 $900.000
438 6004 CLEANING AND SEALING EXIST JOINTS(CL7) LF 264.000 $75.000 $55.120 $64.500 $85.000 $30.000 $67.200
450 6018 RAIL (TY T631) LF 186.000 $200.000 $106.070 $110.000 $113.000 $420.000 $112.800
462 6054 CONC BOX CULV (6 FT X 3 FT)(EXTEND) LF 7.000 $1,000.000 $1,072.020 $1,500.000 $1,570.000 $1,500.000 $1,680.000
462 6057 CONC BOX CULV (6 FT X 6 FT)(EXTEND) LF 56.000 $1,000.000 $1,156.650 $1,300.000 $1,375.000 $1,600.000 $2,520.000
462 6109 CONC BOX CULV (8 FT X 3 FT)(EXTEND) LF 20.000 $1,000.000 $1,354.130 $1,500.000 $1,610.000 $2,000.000 $2,160.000
464 6018 RC PIPE (CL IV)(24 IN) LF 12.000 $300.000 $265.180 $235.000 $245.000 $2,200.000 $300.000
464 6020 RC PIPE (CL IV)(36 IN) LF 12.000 $300.000 $428.810 $490.000 $515.000 $500.000 $360.000
466 6179 WINGWALL (PW - 1) (HW=4 FT) EA 2.000 $14,000.000 $16,057.730 $27,500.000 $28,600.000 $42,000.000 $12,000.000
466 6182 WINGWALL (PW - 1) (HW=7 FT) EA 2.000 $26,200.000 $26,179.850 $40,500.000 $42,500.000 $60,000.000 $14,400.000
467 6006 SET (TY I) (24 IN) (4: 1) (C) EA 2.000 $2,500.000 $5,416.520 $12,500.000 $13,055.000 $2,500.000 $2,160.000
467 6015 SET (TY I) (36 IN) (4: 1) (C) EA 2.000 $6,000.000 $6,150.010 $17,000.000 $18,000.000 $5,000.000 $2,880.000
467 6205 SET (TY I)(S= 6 FT)(HW= 3 FT)(4:1) (C) EA 2.000 $15,000.000 $9,230.650 $19,000.000 $20,065.000 $6,500.000 $5,400.000
467 6270 SET (TY I)(S= 8 FT)(HW= 4 FT)(4:1) (C) EA 2.000 $15,000.000 $16,023.870 $30,500.000 $31,810.000 $10,000.000 $10,200.000
500 6001 MOBILIZATION LS 1.000 $267,327.000 $293,938.020 $340,000.000 $365,000.000 $300,000.000 $393,020.860
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $10,000.000 $3,691.150 $23,000.000 $27,000.000 $17,000.000 $43,073.470
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 226.000 $25.000 $9.030 $9.200 $10.000 $15.000 $14.320
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 226.000 $4.000 $2.260 $2.300 $5.000 $3.000 $3.330
533 6001 RUMBLE STRIPS (SHOULDER) LF 24,448.000 $0.250 $0.090 $0.140 $0.750 $6.000 $0.410
533 6002 RUMBLE STRIPS (CENTERLINE) LF 12,224.000 $0.250 $0.100 $0.170 $1.000 $6.000 $0.580
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,350.000 $28.000 $28.780 $29.500 $30.500 $35.000 $30.600
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,600.000 $2,651.840 $2,700.000 $2,800.000 $3,000.000 $2,820.000
540 6008 MTL BEAM GD FEN TRANS (T101) EA 4.000 $2,000.000 $1,427.480 $1,500.000 $1,520.000 $2,500.000 $1,518.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,325.000 $4.000 $2.260 $2.300 $2.500 $3.000 $2.400
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 8.000 $275.000 $225.690 $230.000 $240.000 $1,000.000 $240.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $4,000.000 $3,469.960 $3,500.000 $3,700.000 $4,000.000 $4,991.630
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $300.000 $225.690 $230.000 $240.000 $1,200.000 $240.000
662 6049 WK ZN PAV MRK REMOV (REFL) TY I-C LF 1,426.000 $4.000 $1.240 $1.250 $2.400 $6.000 $1.320
662 6051 WK ZN PAV MRK REMOV (REFL) TY II-A-A LF 6,896.000 $4.000 $1.240 $1.250 $2.400 $6.000 $1.320
662 6057 WK ZN PAV MRK REMOV (TRAF BTN) TY W LF 4,202.000 $3.000 $1.240 $1.250 $2.000 $3.000 $1.320
662 6059 WK ZN PAV MRK REMOV (TRAF BTN) TY Y LF 20,537.000 $3.000 $1.240 $1.250 $2.000 $3.000 $1.320
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 851.000 $2.500 $2.200 $1.650 $2.500 $3.000 $4.750
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 1,992.000 $2.500 $2.000 $1.650 $3.000 $1.000 $5.870
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 831.000 $0.750 $1.690 $1.750 $2.400 $3.000 $1.800
666 6171 REFL PAV MRK TY II (W) 6" (BRK) LF 1,158.000 $0.500 $0.730 $0.750 $1.200 $2.000 $0.780
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 1,200.000 $0.500 $0.730 $0.750 $1.200 $2.000 $0.780
666 6208 REFL PAV MRK TY II (Y) 6" (BRK) LF 1,209.000 $0.500 $0.730 $0.750 $1.200 $2.000 $0.780
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 6,034.000 $0.500 $0.620 $0.630 $1.200 $2.000 $0.660
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 2,770.000 $0.750 $0.850 $0.860 $2.000 $2.000 $0.900
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 34,104.000 $0.750 $0.850 $0.860 $1.000 $2.000 $0.900
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 2,553.000 $0.750 $0.850 $0.860 $2.000 $2.000 $0.900
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 36,355.000 $0.750 $0.850 $0.860 $1.000 $2.000 $0.900
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 476.000 $15.000 $18.060 $18.500 $18.000 $33.000 $19.200
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 6.000 $600.000 $648.850 $660.000 $915.000 $1,200.000 $690.000
672 6007 REFL PAV MRKR TY I-C EA 133.000 $5.000 $3.670 $3.750 $8.500 $12.000 $3.900
672 6009 REFL PAV MRKR TY II-A-A EA 514.000 $5.000 $3.670 $3.750 $8.000 $12.000 $3.900
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 9,601.000 $1.250 $1.410 $1.450 $3.000 $1.000 $1.500
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 9,217.000 $160.000 $191.320 $190.000 $172.000 $160.000 $187.290
3077 6075 TACK COAT GAL 8,580.000 $7.000 $4.460 $5.400 $4.500 $11.000 $6.810
6185 6002 TMA (STATIONARY) DAY 117.000 $300.000 $465.380 $290.000 $275.000 $350.000 $442.520
6185 6005 TMA (MOBILE OPERATION) DAY 20.000 $300.000 $903.960 $1,200.000 $325.000 $1,200.000 $938.890
Totals: $3,041,695.00 $3,360,261.39 $3,538,299.19 $3,658,542.30 $3,760,472.50 $3,933,568.59