NOLAN SH 70 (0264-01-045)
Items: 31
County: NOLAN
Length: N/A
Highway: SH 70
District: ABILENE
Control Number: 0264-01-045
DBE Goal: N/A
Project: F 2022(151)
Guaranty: N/A
Time: 235 WORKING DAYS
Engineer's Estimate: $5,482,348.28
Date: 12/01/2021 (4 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,482,348.28 | |||
| $4,823,267.55 |
-12.02%
-$659,080.73
|
|||
| $5,301,858.02 |
-3.29%
-$180,490.26
|
9.92%
$478,590.47
|
||
| $5,426,672.10 |
-1.02%
-$55,676.18
|
12.51%
$603,404.55
|
-2.35%
-$124,814.08
|
|
| $5,940,298.05 |
8.35%
$457,949.77
|
23.16%
$1,117,030.50
|
-9.46%
-$513,625.95
|
|
| $6,098,019.02 |
11.23%
$615,670.74
|
26.43%
$1,274,751.47
|
-2.66%
-$157,720.97
|
|
| $6,605,564.94 |
20.49%
$1,123,216.66
|
36.95%
$1,782,297.39
|
-8.32%
-$507,545.92
|
E
Engineer's Estimate
$5,482,348.28
1
Awarded
$4,823,267.55
Over/Under Est:
-12.02%
-$659,080.73
$5,301,858.02
Over/Under Est:
-3.29%
-$180,490.26
Amt Left:
9.92%
$478,590.47
$5,426,672.10
Over/Under Est:
-1.02%
-$55,676.18
Amt Left:
12.51%
$603,404.55
Delta:
-2.35%
-$124,814.08
$5,940,298.05
Over/Under Est:
8.35%
$457,949.77
Amt Left:
23.16%
$1,117,030.50
Delta:
-9.46%
-$513,625.95
$6,098,019.02
Over/Under Est:
11.23%
$615,670.74
Amt Left:
26.43%
$1,274,751.47
Delta:
-2.66%
-$157,720.97
$6,605,564.94
Over/Under Est:
20.49%
$1,123,216.66
Amt Left:
36.95%
$1,782,297.39
Delta:
-8.32%
-$507,545.92
Bid Items & Bid Tabulations
31
Total
0 of 31