Job Info for 0006-02-121

County: NOLAN Highway: IH 20 Date: 03/04/2020 (4 years ago) Engineer's Estimate: $17,602,174 Control Number: 0006-02-121
Project: NH 2020(618) District: ABILENE Time: 604 WORKING DAYS Type: OVERLAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $17,602,173.89
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY   $20,032,973.64 1
13.81% | $2,430,799.75
RK HALL, LLC   $20,781,488.59 2
18.06% | $3,179,314.70
3.74% | $748,514.95

Bid Items

Items: 108, 0 filtered
NOLAN IH 20  |  ABILENE  |  0006-02-121  |  03/04/2020  |  $17,602,174  |  NH 2020(618)  |  OVERLAY  |  604 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY RK HALL, LLC
104 6021 REMOVING CONC (CURB) LF 28.000 $25.000 $20.000 $157.260
104 6054 REMOVING CONCRETE(MOW STRIP) LF 23,200.000 $8.000 $12.000 $9.710
105 6030 REMOVING STAB BASE & ASPH PAV (8"-14") SY 3,195.000 $10.000 $4.000 $30.680
110 6001 EXCAVATION (ROADWAY) CY 4,655.000 $13.000 $11.000 $27.660
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 2,756.000 $15.000 $12.000 $15.130
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 22,668.000 $3.000 $2.800 $6.030
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 22,668.000 $0.200 $0.150 $0.160
164 6009 BROADCAST SEED (TEMP) (WARM) SY 11,334.000 $0.300 $0.190 $0.220
164 6011 BROADCAST SEED (TEMP) (COOL) SY 11,334.000 $0.300 $0.190 $0.220
168 6001 VEGETATIVE WATERING MG 453.000 $35.000 $10.000 $42.700
310 6009 PRIME COAT (MC-30) GAL 3,680.000 $6.000 $5.000 $8.210
316 6001 ASPH (MULTI OPTION) GAL 180,904.000 $5.000 $5.000 $4.040
316 6175 AGGR(TY-B GR-4 SAC-B) CY 3,289.000 $125.000 $155.000 $157.790
346 6014 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 TON 37,997.000 $135.000 $200.000 $160.400
351 6013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 32,053.000 $38.000 $35.000 $41.940
354 6005 PLAN & TEXT ASPH CONC PAV(2" TO 4") SY 11,071.000 $1.500 $3.000 $8.310
354 6045 PLANE ASPH CONC PAV (2") SY 331,711.000 $1.400 $2.000 $2.650
416 6015 DRILL SHAFT (NON - REINFORCED) (12 IN) LF 14.000 $100.000 $125.000 $143.750
416 6018 DRILL SHAFT (SIGN MTS) (24 IN) LF 259.000 $200.000 $175.000 $189.750
420 6066 CL C CONC (RAIL FOUNDATION) CY 24.000 $1,000.000 $420.000 $1,725.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 1,286.000 $600.000 $450.000 $661.250
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 156.000 $35.000 $65.000 $11.500
438 6005 CLEANING AND SEALING JOINTS LF 480.000 $20.000 $65.000 $48.300
438 6009 CLEANING EXISTING JOINTS LF 176.000 $12.000 $65.000 $13.800
450 6004 RAIL (TY T221) LF 152.000 $140.000 $180.000 $402.500
451 6005 RETROFIT RAIL (TY T221) LF 488.000 $200.000 $175.000 $419.750
451 6024 RETROFIT RAIL (TY SSTR) LF 2,552.000 $180.000 $160.000 $391.000
454 6007 HEADER TYPE EXPANSION JOINT LF 156.000 $200.000 $150.000 $82.800
464 6017 RC PIPE (CL IV)(18 IN) LF 792.000 $70.000 $160.000 $126.500
465 6126 INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) EA 4.000 $4,000.000 $5,000.000 $6,325.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $1,000.000 $3,300.000 $2,300.000
496 6004 REMOV STR (SET) EA 4.000 $1,200.000 $1,550.000 $1,150.000
496 6007 REMOV STR (PIPE) LF 163.000 $15.000 $50.000 $23.000
500 6001 MOBILIZATION LS 1.000 $1,571,213.000 $2,020,000.000 $1,310,229.820
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 31.000 $10,000.000 $14,000.000 $21,762.300
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 720.000 $50.000 $35.000 $67.140
506 6011 ROCK FILTER DAMS (REMOVE) LF 720.000 $20.000 $14.000 $52.650
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 60.000 $3.600 $20.000 $24.810
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 60.000 $1.700 $4.000 $18.840
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,580.000 $8.000 $6.000 $9.110
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,580.000 $3.000 $2.000 $3.960
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 1,350.000 $110.000 $45.000 $107.010
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 10,770.000 $20.000 $5.000 $14.630
512 6037 PORT CTB (STKPL)(SGL SLP)(TY 1) LF 12,120.000 $15.000 $6.000 $16.620
514 6019 PERM CTB(SGL SLOPE)(TY 1)(42)(HPC) LF 833.000 $140.000 $100.000 $149.500
533 6001 RUMBLE STRIPS (SHOULDER) LF 106,497.000 $0.170 $0.160 $0.180
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 22,300.000 $23.000 $22.000 $21.560
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 32.000 $1,900.000 $2,000.000 $3,431.070
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 24.000 $1,200.000 $1,300.000 $1,523.750
542 6001 REMOVE METAL BEAM GUARD FENCE LF 23,200.000 $2.800 $3.000 $1.730
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 27.000 $220.000 $300.000 $230.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 30.000 $300.000 $300.000 $230.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 34.000 $2,800.000 $3,000.000 $2,958.950
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 37.000 $280.000 $300.000 $230.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 25.000 $2,800.000 $2,500.000 $3,421.210
545 6004 CRASH CUSH ATTEN (STKPL) EA 25.000 $2,200.000 $1,500.000 $3,421.210
545 6005 CRASH CUSH ATTEN (REMOVE) EA 3.000 $1,100.000 $1,000.000 $2,221.750
545 6013 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) EA 3.000 $20,000.000 $24,000.000 $27,025.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 3.000 $11,000.000 $8,600.000 $15,871.320
636 6001 ALUMINUM SIGNS (TY A) SF 25.000 $30.000 $30.000 $33.350
636 6002 ALUMINUM SIGNS (TY G) SF 2,324.000 $30.000 $30.000 $33.350
636 6009 REPLACE EXISTING ALUMINUM SIGNS(TY O) SF 504.000 $30.000 $30.000 $33.350
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 20.000 $500.000 $750.000 $833.750
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 21.000 $650.000 $855.000 $977.500
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 6.000 $900.000 $880.000 $1,006.250
644 6008 IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL) EA 1.000 $700.000 $1,060.000 $1,207.500
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 3.000 $900.000 $1,000.000 $1,167.250
644 6051 IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL) EA 13.000 $1,610.000 $2,000.000 $2,156.250
644 6064 IN BRIDGE MNT CLEARANCE SGN ASSM(TY N) EA 8.000 $2,500.000 $3,500.000 $4,025.000
644 6076 REMOVE SM RD SN SUP&AM EA 63.000 $120.000 $100.000 $144.230
644 6077 REMOVE BRDG MNT CLEARANCE SIGN ASSM EA 8.000 $500.000 $500.000 $575.000
647 6001 INSTALL LRSS (STRUCT STEEL) LB 10,555.000 $6.000 $10.000 $6.900
647 6003 REMOVE LRSA EA 19.000 $950.000 $1,100.000 $1,150.000
658 6010 INSTL DEL ASSM (D-SW)SZ 2(WC)GND EA 30.000 $80.000 $80.000 $86.250
658 6013 INSTL DEL ASSM (D-SW)SZ (BRF)CTB EA 46.000 $40.000 $30.000 $46.000
658 6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB EA 34.000 $40.000 $30.000 $46.000
658 6040 INSTL DEL ASSM (D-DW)SZ 2(WC)GND EA 270.000 $80.000 $76.000 $86.250
658 6047 INSTL OM ASSM (OM-2Y)(WC)GND EA 36.000 $80.000 $76.000 $86.250
658 6063 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR) EA 160.000 $40.000 $35.000 $40.250
658 6065 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BR) EA 67.000 $40.000 $36.000 $40.250
658 6067 INSTL DEL ASSM (D-DW)SZ 1(BRF)GF2 EA 42.000 $40.000 $36.000 $40.250
662 6060 WK ZN PAV MRK REMOV (W)4"(BRK) LF 20,439.000 $0.600 $1.500 $1.960
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 111,794.000 $0.600 $1.000 $0.990
662 6072 WK ZN PAV MRK REMOV (W)12"(LNDP) LF 1,476.000 $3.000 $6.000 $3.450
662 6073 WK ZN PAV MRK REMOV (W)12"(SLD) LF 4,037.000 $3.700 $5.000 $3.450
662 6082 WK ZN PAV MRK REMOV (W)(ENTR GORE) EA 12.000 $780.000 $1,550.000 $1,150.000
662 6083 WK ZN PAV MRK REMOV (W)(EXIT GORE) EA 13.000 $780.000 $1,550.000 $1,150.000
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 117,473.000 $0.600 $1.000 $1.010
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 12,272.000 $1.500 $1.000 $2.180
666 6006 REFL PAV MRK TY I (W)4"(DOT)(100MIL) LF 11,174.000 $3.000 $1.500 $0.530
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 10,677.000 $2.400 $1.000 $1.060
666 6039 REFL PAV MRK TY I (W)12"(LNDP)(100MIL) LF 1,356.000 $6.000 $3.000 $1.730
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 6,185.000 $6.000 $3.000 $1.730
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 18,720.000 $0.750 $0.500 $0.530
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 77,453.000 $0.600 $0.550 $0.530
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 87,069.000 $0.600 $0.550 $0.530
668 6084 PREFAB PAV MRK TY C (W) (NUMBER) EA 12.000 $800.000 $177.000 $575.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 27.000 $60.000 $102.000 $57.500
672 6010 REFL PAV MRKR TY II-C-R EA 2,005.000 $6.600 $7.000 $3.740
3077 6001 SP MIXES SP-B PG64-22 TON 15,965.000 $135.000 $130.000 $141.400
3077 6052 SP MIXES SP-D SAC-A PG70-22 TON 617.000 $135.000 $150.000 $224.200
3077 6075 TACK COAT GAL 5,483.000 $4.000 $5.000 $19.200
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $15,000.000 $10,000.000 $17,680.180
6055 6001 TMSP RADAR SPEED CONTROL MONITOR EA 2.000 $10,000.000 $10,000.000 $11,946.070
6185 6002 TMA (STATIONARY) DAY 2,150.000 $250.000 $50.000 $277.950
6185 6005 TMA (MOBILE OPERATION) DAY 90.000 $400.000 $50.000 $517.190
6302 6005 TEMP Q-DETECT SYS EA 2.000 $80,000.000 $150,000.000 $55,918.750
6302 6006 TEMP Q-DETECT SYS (RELOCATE) EA 10.000 $1,000.000 $2,000.000 $1,150.000
Totals: $17,602,173.89 $20,032,973.64 $20,781,488.59