PREPARING ROW
|
STA
|
161.000
|
$315.000
|
$48,250.000
|
$72,500.000
|
$79,830.000
|
|
|
DISPOSAL OF WATER WELLS
|
EA
|
3.000
|
$1,400.000
|
$5,000.000
|
$5,000.000
|
$4,512.850
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
11,985.000
|
$10.000
|
$6.000
|
$9.800
|
$7.270
|
|
|
REMOVING CONC (RETAINING WALLS)
|
SY
|
590.000
|
$32.000
|
$58.000
|
$40.000
|
$44.300
|
|
|
REMOVING STAB BASE AND ASPH PAV (2")
|
SY
|
77,027.000
|
$3.700
|
$1.000
|
$0.850
|
$1.360
|
|
|
REMOVING STAB BASE AND ASPH PAV (3")
|
SY
|
9,976.000
|
$5.200
|
$1.400
|
$1.560
|
$2.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (13")
|
SY
|
133,948.000
|
$6.700
|
$4.400
|
$4.710
|
$8.710
|
|
|
REMOVING STAB BASE AND ASPH PAV (5")
|
SY
|
32,982.000
|
$5.500
|
$1.400
|
$2.020
|
$3.420
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
366,180.000
|
$8.000
|
$9.000
|
$4.000
|
$8.600
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
608,551.000
|
$9.000
|
$12.000
|
$10.000
|
$14.730
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
STA
|
766.500
|
$371.000
|
$300.000
|
$1,480.000
|
$1,998.610
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
150.600
|
$550.000
|
$575.000
|
$580.000
|
$560.000
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
150.600
|
$450.000
|
$415.000
|
$415.000
|
$500.000
|
|
|
VEGETATIVE WATERING
|
MG
|
6,144.000
|
$7.000
|
$15.000
|
$38.800
|
$43.900
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
29,856.000
|
$1.000
|
$1.250
|
$1.250
|
$1.200
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
40,733.000
|
$51.000
|
$40.000
|
$48.100
|
$41.760
|
|
|
LIME (QUICKLIME (DRY))
|
TON
|
6,206.000
|
$182.000
|
$275.000
|
$300.000
|
$317.120
|
|
|
LIME TRT (SUBGRADE)(8")
|
SY
|
338,425.000
|
$3.200
|
$4.000
|
$4.250
|
$5.100
|
|
|
PRIME COAT (MC-30)
|
GAL
|
66,836.000
|
$4.500
|
$6.700
|
$6.600
|
$6.500
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
59,282.000
|
$3.700
|
$6.700
|
$6.600
|
$6.500
|
|
|
AGGR(TY-B GR-3 SAC-B)
|
CY
|
1,130.000
|
$130.000
|
$127.000
|
$126.000
|
$125.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (13")
|
SY
|
167,521.000
|
$65.000
|
$110.000
|
$120.000
|
$109.930
|
|
|
CEM STABIL BKFL
|
CY
|
731.000
|
$210.000
|
$225.000
|
$181.000
|
$164.400
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
28.000
|
$60.000
|
$100.000
|
$115.000
|
$235.590
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
779.000
|
$5.500
|
$5.000
|
$67.000
|
$31.740
|
|
|
TEMPORARY SPL SHORING
|
SF
|
13,716.000
|
$15.000
|
$26.000
|
$36.600
|
$34.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
410.000
|
$150.000
|
$200.000
|
$87.000
|
$96.010
|
|
|
DRILL SHAFT (30 IN)
|
LF
|
644.000
|
$210.000
|
$350.000
|
$325.000
|
$325.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
2,135.000
|
$260.000
|
$375.000
|
$263.000
|
$263.370
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
76.000
|
$370.000
|
$750.000
|
$720.000
|
$799.200
|
|
|
DRILL SHAFT (54 IN)
|
LF
|
384.000
|
$400.000
|
$800.000
|
$660.000
|
$656.380
|
|
|
DRILL SHAFT (60 IN)
|
LF
|
285.000
|
$460.000
|
$900.000
|
$870.000
|
$770.710
|
|
|
DRILL SHAFT (72 IN)
|
LF
|
1,360.000
|
$640.000
|
$1,100.000
|
$1,060.000
|
$973.680
|
|
|
DRILL SHAFT (84 IN)
|
LF
|
280.000
|
$780.000
|
$1,500.000
|
$1,410.000
|
$1,283.350
|
|
|
DRILL SHAFT (NON - REINFORCED) (12 IN)
|
LF
|
28.000
|
$118.000
|
$200.000
|
$152.000
|
$152.210
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
42.000
|
$196.000
|
$300.000
|
$283.000
|
$284.120
|
|
|
DRILL SHAFT (SIGN MTS) (30 IN)
|
LF
|
48.000
|
$270.000
|
$475.000
|
$455.000
|
$456.620
|
|
|
DRILL SHAFT (SIGN MTS) (36 IN)
|
LF
|
210.000
|
$460.000
|
$525.000
|
$510.000
|
$513.440
|
|
|
DRILL SHAFT (SIGN MTS) (42 IN)
|
LF
|
15.000
|
$490.000
|
$750.000
|
$730.000
|
$736.670
|
|
|
DRILL SHAFT (SIGN MTS) (54 IN)
|
LF
|
140.000
|
$575.000
|
$770.000
|
$770.000
|
$769.140
|
|
|
DRILL SHAFT (HIGH MAST POLE) (60 IN)
|
LF
|
412.000
|
$620.000
|
$900.000
|
$840.000
|
$835.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
262.700
|
$1,400.000
|
$1,200.000
|
$1,360.000
|
$1,301.260
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
104.100
|
$1,400.000
|
$1,500.000
|
$1,770.000
|
$1,660.840
|
|
|
CL C CONC (CAP)(HPC)(MASS)
|
CY
|
1,136.900
|
$1,400.000
|
$1,600.000
|
$1,430.000
|
$1,486.680
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
712.600
|
$1,400.000
|
$1,500.000
|
$1,450.000
|
$1,363.240
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
410.000
|
$359.000
|
$550.000
|
$600.000
|
$574.360
|
|
|
CL F CONC (CAP)(HPC)(MASS)
|
CY
|
236.800
|
$1,200.000
|
$1,600.000
|
$1,780.000
|
$1,330.510
|
|
|
CL F CONC (COLUMN)(HPC)
|
CY
|
109.000
|
$1,200.000
|
$1,400.000
|
$1,980.000
|
$1,713.830
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
187,129.000
|
$19.000
|
$24.500
|
$29.000
|
$29.950
|
|
|
APPROACH SLAB (HPC)
|
CY
|
377.500
|
$800.000
|
$750.000
|
$890.000
|
$838.240
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
2,778.820
|
$135.000
|
$240.000
|
$250.000
|
$230.000
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
16,127.440
|
$155.000
|
$240.000
|
$220.000
|
$218.000
|
|
|
EPOXY WATERPROOF FINISH
|
SF
|
14,301.000
|
$0.500
|
$10.000
|
$10.000
|
$9.770
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
1,346.210
|
$530.000
|
$600.000
|
$670.000
|
$387.950
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
22.000
|
$450.000
|
$600.000
|
$950.000
|
$418.960
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
128.000
|
$100.000
|
$150.000
|
$166.000
|
$183.790
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
251.000
|
$115.000
|
$150.000
|
$184.000
|
$205.260
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
832.000
|
$460.000
|
$600.000
|
$900.000
|
$400.780
|
|
|
ELASTOMERIC BEARING (F9)
|
EA
|
8.000
|
$3,000.000
|
$4,500.000
|
$5,700.000
|
$4,677.720
|
|
|
SLIDING ELASTOMERIC BEARING (ES 6)
|
EA
|
16.000
|
$2,010.000
|
$3,200.000
|
$4,540.000
|
$3,537.000
|
|
|
STR STEEL (PLATE GIRDER)
|
LB
|
1,952,712.000
|
$2.000
|
$2.500
|
$2.400
|
$3.550
|
|
|
RAIL (TY SSTR)
|
LF
|
8,606.000
|
$65.000
|
$75.000
|
$84.000
|
$55.950
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
10,155.200
|
$75.000
|
$75.000
|
$90.000
|
$62.970
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
750.000
|
$120.000
|
$210.000
|
$253.000
|
$203.290
|
|
|
SEALED EXPANSION JOINT (5 IN) (SEJ - M)
|
LF
|
142.000
|
$125.000
|
$210.000
|
$236.000
|
$210.290
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
311.000
|
$200.000
|
$280.000
|
$464.000
|
$251.390
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
1,784.000
|
$300.000
|
$420.000
|
$411.000
|
$398.930
|
|
|
CONC BOX CULV (5 FT X 3 FT)
|
LF
|
1,059.000
|
$320.000
|
$470.000
|
$418.000
|
$433.760
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
60.000
|
$70.000
|
$90.000
|
$145.000
|
$76.580
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,400.000
|
$85.000
|
$95.000
|
$129.000
|
$127.660
|
|
|
RC PIPE (CL IV)(18 IN)
|
LF
|
23.000
|
$80.000
|
$100.000
|
$155.000
|
$75.500
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
60.000
|
$95.000
|
$120.000
|
$182.000
|
$105.110
|
|
|
INL(CMP)(PAZD-CZ)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
1.000
|
$6,500.000
|
$5,000.000
|
$7,400.000
|
$7,894.300
|
|
|
HEADWALL (CH - PW - 0) (DIA= 18 IN)
|
EA
|
1.000
|
$3,200.000
|
$5,000.000
|
$7,300.000
|
$3,126.390
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
|
EA
|
2.000
|
$5,000.000
|
$4,000.000
|
$4,550.000
|
$9,290.910
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
|
EA
|
8.000
|
$7,100.000
|
$5,000.000
|
$6,500.000
|
$9,807.970
|
|
|
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(C)
|
EA
|
2.000
|
$8,500.000
|
$6,500.000
|
$8,000.000
|
$11,994.120
|
|
|
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P)
|
EA
|
1.000
|
$8,000.000
|
$8,500.000
|
$10,900.000
|
$13,524.700
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
8.000
|
$7,200.000
|
$7,000.000
|
$8,700.000
|
$11,585.270
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
|
EA
|
4.000
|
$9,100.000
|
$9,000.000
|
$16,100.000
|
$17,114.990
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (P)
|
EA
|
4.000
|
$9,000.000
|
$9,000.000
|
$9,000.000
|
$11,233.260
|
|
|
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)
|
EA
|
3.000
|
$8,600.000
|
$7,000.000
|
$11,300.000
|
$11,484.940
|
|
|
SET (TY I)(S= 5 FT)(HW= 5 FT)(4:1) (C)
|
EA
|
3.000
|
$11,500.000
|
$8,000.000
|
$14,500.000
|
$14,968.430
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (C)
|
EA
|
1.000
|
$1,900.000
|
$1,100.000
|
$1,500.000
|
$1,606.460
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$1,100.000
|
$3,090.000
|
$1,303.820
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
1.000
|
$1,200.000
|
$1,100.000
|
$3,980.000
|
$1,634.990
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
6.000
|
$1,550.000
|
$1,100.000
|
$4,150.000
|
$1,855.370
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
11.000
|
$2,250.000
|
$1,100.000
|
$4,410.000
|
$2,026.600
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$1,600.000
|
$1,100.000
|
$4,410.000
|
$2,026.600
|
|
|
REMOV STR (INLET)
|
EA
|
2.000
|
$570.000
|
$300.000
|
$1,070.000
|
$1,022.680
|
|
|
REMOV STR (SET)
|
EA
|
51.000
|
$385.000
|
$200.000
|
$453.000
|
$593.310
|
|
|
REMOV STR (WINGWALL)
|
EA
|
14.000
|
$1,200.000
|
$1,100.000
|
$1,740.000
|
$2,520.950
|
|
|
REMOV STR (PIPE)
|
LF
|
1,920.000
|
$23.000
|
$15.000
|
$32.600
|
$18.750
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
1,393.000
|
$66.000
|
$50.000
|
$64.000
|
$38.360
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
4.000
|
$70,000.000
|
$60,000.000
|
$115,000.000
|
$250,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$6,758,280.340
|
$12,875,000.000
|
$12,400,000.000
|
$13,030,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
42.000
|
$8,000.000
|
$30,000.000
|
$31,000.000
|
$109,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
2,424.000
|
$45.000
|
$50.000
|
$44.000
|
$40.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
470.000
|
$52.000
|
$70.000
|
$63.000
|
$70.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
2,894.000
|
$8.000
|
$11.000
|
$10.000
|
$15.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
2,352.000
|
$19.500
|
$25.000
|
$23.800
|
$30.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
2,352.000
|
$6.000
|
$5.000
|
$9.000
|
$15.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
15,977.000
|
$2.500
|
$6.000
|
$5.200
|
$3.750
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
15,977.000
|
$0.620
|
$1.000
|
$1.500
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
616.000
|
$6.000
|
$9.000
|
$8.800
|
$7.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
616.000
|
$1.000
|
$1.000
|
$2.000
|
$1.000
|
|
|
CONSTRUCTING DETOURS (TY 1)
|
SY
|
34,191.000
|
$62.000
|
$110.000
|
$111.000
|
$141.090
|
|
|
CONSTRUCTING DETOURS (TY 2)
|
SY
|
42,083.000
|
$47.000
|
$70.000
|
$76.000
|
$79.700
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
23,670.000
|
$35.000
|
$100.000
|
$106.000
|
$93.960
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
79,581.000
|
$5.000
|
$6.000
|
$7.600
|
$4.320
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
23,670.000
|
$7.000
|
$7.000
|
$7.800
|
$4.880
|
|
|
PTB(REMOVE)(SSCB OR CSB)(TY1)OR(STL)
|
LF
|
502.000
|
$10.000
|
$22.000
|
$12.900
|
$9.820
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
13,275.000
|
$65.000
|
$90.000
|
$112.000
|
$82.670
|
|
|
PERM CTB (TRAN SSCB TO SSTR) (MOD)
|
LF
|
30.000
|
$315.000
|
$420.000
|
$560.000
|
$332.210
|
|
|
DRIVEWAYS (CONC)
|
SY
|
213.000
|
$76.000
|
$90.000
|
$106.000
|
$142.480
|
|
|
DRIVEWAYS (ACP)
|
SY
|
484.000
|
$40.000
|
$75.000
|
$74.000
|
$74.570
|
|
|
RUMBLE STRIPS (SHOULDER) CONCRETE
|
LF
|
22,354.000
|
$0.400
|
$0.200
|
$0.830
|
$0.600
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,100.000
|
$26.000
|
$25.000
|
$23.000
|
$28.750
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
19.000
|
$2,000.000
|
$1,800.000
|
$1,730.000
|
$2,475.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
11.000
|
$1,230.000
|
$1,400.000
|
$1,350.000
|
$1,750.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
10,126.000
|
$2.500
|
$2.000
|
$2.000
|
$3.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
16.000
|
$210.000
|
$255.000
|
$250.000
|
$300.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
5.000
|
$214.000
|
$255.000
|
$250.000
|
$300.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
12.000
|
$220.000
|
$255.000
|
$250.000
|
$300.000
|
|
|
CABLE BARRIER SYSTEM (TL-4)
|
LF
|
124.000
|
$11.000
|
$75.000
|
$15.000
|
$20.000
|
|
|
CABLE BARRIER TERMINAL SECTION (TL-4)
|
EA
|
2.000
|
$2,910.000
|
$12,000.000
|
$3,500.000
|
$5,000.000
|
|
|
REMOVE CABLE BARRIER
|
LF
|
12,545.000
|
$2.000
|
$6.000
|
$4.000
|
$3.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
31.000
|
$2,910.000
|
$3,000.000
|
$2,900.000
|
$3,700.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
19.000
|
$275.000
|
$255.000
|
$250.000
|
$300.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
58.000
|
$1,526.000
|
$900.000
|
$1,600.000
|
$2,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
25.000
|
$1,000.000
|
$950.000
|
$1,280.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
20.000
|
$7,878.000
|
$12,000.000
|
$7,800.000
|
$7,500.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
1.000
|
$230.000
|
$235.000
|
$350.000
|
$95.000
|
|
|
REMOVE RD IL ASM (TRANS-BASE)
|
EA
|
47.000
|
$835.000
|
$350.000
|
$350.000
|
$350.000
|
|
|
IN RD IL (TY SA) 40T-8 (250W EQ) LED
|
EA
|
59.000
|
$3,800.000
|
$5,500.000
|
$5,400.000
|
$5,400.000
|
|
|
IN RD IL (TY ST) 40B-8 (250W EQ) LED
|
EA
|
7.000
|
$3,900.000
|
$5,600.000
|
$5,600.000
|
$5,630.000
|
|
|
IN RD IL (TY SA) 50T-12-12(400W EQ)LED
|
EA
|
18.000
|
$5,500.000
|
$8,600.000
|
$8,500.000
|
$8,530.000
|
|
|
HI MST IL POLE (150 FT)( 80 MPH)
|
EA
|
5.000
|
$43,000.000
|
$72,000.000
|
$72,000.000
|
$72,000.000
|
|
|
HI MST IL POLE (175 FT)( 80 MPH)
|
EA
|
7.000
|
$42,000.000
|
$68,000.000
|
$68,000.000
|
$67,650.000
|
|
|
LED HI MST IL ASM (6 FIXT)(SYM)(TY S)
|
EA
|
2.000
|
$24,000.000
|
$39,000.000
|
$39,000.000
|
$39,000.000
|
|
|
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
|
EA
|
1.000
|
$24,000.000
|
$35,000.000
|
$35,200.000
|
$35,225.000
|
|
|
LED HI MST IL ASM (6 FIXT) (ASYM)(TY B)
|
EA
|
2.000
|
$24,000.000
|
$35,000.000
|
$34,700.000
|
$34,675.000
|
|
|
LED HI MST IL ASM (6 FIXT) (ASYM)(TY C)
|
EA
|
1.000
|
$24,000.000
|
$36,000.000
|
$35,900.000
|
$35,850.000
|
|
|
LED HI MST IL AM(6 FIXT)ASYM(TY A)SHLD
|
EA
|
3.000
|
$24,000.000
|
$39,000.000
|
$38,400.000
|
$38,385.000
|
|
|
LED HI MST IL AM(6 FIXT)ASYM(TY B)SHLD
|
EA
|
1.000
|
$24,000.000
|
$36,000.000
|
$35,700.000
|
$35,700.000
|
|
|
LED HI MST IL AM(6 FIXT)ASYM(TY C)SHLD
|
EA
|
1.000
|
$24,000.000
|
$36,000.000
|
$36,000.000
|
$36,000.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
27,010.000
|
$13.000
|
$6.000
|
$6.000
|
$6.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
4,460.000
|
$30.000
|
$28.000
|
$28.000
|
$28.000
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
27,735.000
|
$1.400
|
$1.700
|
$1.700
|
$1.700
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
60,400.000
|
$1.600
|
$1.900
|
$1.900
|
$1.900
|
|
|
ELEC CONDR (NO.4) BARE
|
LF
|
4,475.000
|
$2.500
|
$4.250
|
$4.300
|
$4.300
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
9,630.000
|
$4.500
|
$4.550
|
$4.500
|
$4.500
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
88.000
|
$1,100.000
|
$1,550.000
|
$1,550.000
|
$1,550.000
|
|
|
ELC SRV TY A 120/240 060(NS)AL(E)SP(O)
|
EA
|
5.000
|
$6,000.000
|
$9,000.000
|
$9,000.000
|
$9,000.000
|
|
|
ELC SRV TY D 120/240 060(NS)AL(N)SP(O)
|
EA
|
5.000
|
$6,000.000
|
$7,500.000
|
$7,500.000
|
$7,500.000
|
|
|
ELC SRV TY D 120/240 070(NS)AL(N)SP(O)
|
EA
|
3.000
|
$6,000.000
|
$7,500.000
|
$7,500.000
|
$7,500.000
|
|
|
ELC SRV TY A 240/480 100(SS)AL(E)SP(O)
|
EA
|
2.000
|
$6,000.000
|
$9,000.000
|
$9,000.000
|
$9,000.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
110.000
|
$55.000
|
$45.000
|
$44.600
|
$44.800
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
614.500
|
$30.000
|
$42.000
|
$42.000
|
$42.210
|
|
|
ALUMINUM SIGNS (TY O)
|
SF
|
3,898.000
|
$29.000
|
$38.000
|
$37.500
|
$37.650
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
93.000
|
$840.000
|
$800.000
|
$950.000
|
$872.440
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
34.000
|
$835.000
|
$945.000
|
$1,100.000
|
$1,028.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
18.000
|
$710.000
|
$1,125.000
|
$1,300.000
|
$1,243.390
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
21.000
|
$1,050.000
|
$1,180.000
|
$1,350.000
|
$1,284.730
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
12.000
|
$1,150.000
|
$1,280.000
|
$1,480.000
|
$1,397.860
|
|
|
IN SM RD SN SUP&AM TYTWT(1)UA(P)
|
EA
|
4.000
|
$650.000
|
$310.000
|
$700.000
|
$337.230
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
2.000
|
$2,300.000
|
$5,350.000
|
$3,600.000
|
$5,413.440
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
5.000
|
$2,300.000
|
$5,350.000
|
$3,600.000
|
$5,413.440
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
2.000
|
$640.000
|
$750.000
|
$800.000
|
$818.050
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
174.000
|
$95.000
|
$150.000
|
$125.000
|
$91.910
|
|
|
IN SRSS & AM (RAIL)(90 MPH)(T MOUNT)
|
EA
|
16.000
|
$4,350.000
|
$8,600.000
|
$8,600.000
|
$8,660.490
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
2,922.620
|
$6.000
|
$9.550
|
$9.600
|
$9.590
|
|
|
REMOVE LRSA
|
EA
|
19.000
|
$225.000
|
$1,600.000
|
$1,600.000
|
$1,608.300
|
|
|
INS OH SN SUP(25 FT CANT)
|
EA
|
1.000
|
$13,500.000
|
$38,000.000
|
$38,100.000
|
$38,254.300
|
|
|
INS OH SN SUP(30 FT BAL TEE)
|
EA
|
3.000
|
$33,000.000
|
$65,000.000
|
$40,000.000
|
$65,000.000
|
|
|
INS OH SN SUP(35 FT CANT)
|
EA
|
3.000
|
$25,000.000
|
$45,000.000
|
$45,300.000
|
$45,509.430
|
|
|
INS OH SN SUP(40 FT CANT)
|
EA
|
4.000
|
$45,000.000
|
$57,000.000
|
$57,000.000
|
$57,178.520
|
|
|
INS OH SN SUP(55 FT BRDG)
|
EA
|
1.000
|
$50,000.000
|
$53,000.000
|
$53,000.000
|
$53,322.650
|
|
|
INS OH SN SUP(90 FT BRDG)
|
EA
|
1.000
|
$60,000.000
|
$89,000.000
|
$90,000.000
|
$90,257.840
|
|
|
INS OH SN SUP(100 FT BRDG)
|
EA
|
1.000
|
$80,000.000
|
$100,000.000
|
$100,000.000
|
$100,861.480
|
|
|
INS OH SN SUP(110 FT BRDG)
|
EA
|
2.000
|
$85,000.000
|
$117,000.000
|
$117,000.000
|
$117,527.980
|
|
|
REMOVE OVERHD SIGN SUP
|
EA
|
3.000
|
$5,800.000
|
$13,000.000
|
$13,500.000
|
$13,597.020
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
|
EA
|
105.000
|
$115.000
|
$44.000
|
$95.000
|
$95.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
|
EA
|
28.000
|
$60.000
|
$45.000
|
$95.000
|
$95.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BR)
|
EA
|
17.000
|
$65.000
|
$45.000
|
$95.000
|
$45.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
111.000
|
$45.000
|
$39.000
|
$45.000
|
$45.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
25.000
|
$24.000
|
$40.000
|
$45.000
|
$95.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 2(WC)GND
|
EA
|
38.000
|
$103.000
|
$44.000
|
$95.000
|
$45.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
79.000
|
$45.000
|
$39.000
|
$45.000
|
$45.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
|
EA
|
134.000
|
$20.000
|
$41.000
|
$45.000
|
$95.000
|
|
|
INSTL DEL ASSM (D-DW)SZ 2(WC)GND
|
EA
|
138.000
|
$124.000
|
$45.000
|
$95.000
|
$95.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
38.000
|
$85.000
|
$48.000
|
$95.000
|
$38.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
42.000
|
$41.000
|
$29.000
|
$38.500
|
$38.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
24.000
|
$33.000
|
$30.000
|
$38.500
|
$38.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
|
EA
|
3.000
|
$30.000
|
$30.000
|
$38.500
|
$38.500
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
77.000
|
$41.000
|
$30.000
|
$38.500
|
$38.500
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
|
EA
|
4.000
|
$55.000
|
$30.000
|
$45.000
|
$45.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
6,220.000
|
$1.500
|
$1.300
|
$1.600
|
$1.100
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
6,608.000
|
$2.000
|
$1.300
|
$1.600
|
$1.140
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
280.000
|
$2.000
|
$1.750
|
$1.700
|
$1.140
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
300.000
|
$1.500
|
$1.000
|
$1.000
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
4,441.000
|
$1.000
|
$1.000
|
$1.130
|
$1.130
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
1,463.000
|
$3.150
|
$3.000
|
$3.000
|
$3.000
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
2,493.000
|
$0.200
|
$0.350
|
$0.350
|
$0.350
|
|
REFL PAV MRK TY II (W) 4" (DOT)
|
LF
|
431.000
|
$1.500
|
$1.000
|
$1.000
|
$1.000
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
69,185.000
|
$0.150
|
$0.350
|
$0.350
|
$0.350
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
1,011.000
|
$0.500
|
$0.700
|
$0.700
|
$0.700
|
|
REFL PAV MRK TY II (W) 18" (YLD TRI)
|
EA
|
21.000
|
$23.000
|
$25.000
|
$25.000
|
$25.000
|
|
REFL PAV MRK TY II (Y) 4" (BRK)
|
LF
|
1,033.000
|
$0.200
|
$0.350
|
$0.350
|
$0.350
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
97,683.000
|
$0.200
|
$0.350
|
$0.350
|
$0.350
|
|
|
PAVEMENT SEALER 12"
|
LF
|
836.000
|
$0.600
|
$1.000
|
$1.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
1,200.000
|
$0.500
|
$1.000
|
$1.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
74,205.000
|
$0.450
|
$0.550
|
$0.560
|
$0.560
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
4,403.000
|
$0.500
|
$0.550
|
$0.550
|
$0.550
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
46,550.000
|
$0.450
|
$0.550
|
$0.550
|
$0.550
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
26,821.000
|
$0.500
|
$0.800
|
$0.810
|
$0.810
|
|
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
|
LF
|
156.000
|
$3.500
|
$3.000
|
$3.000
|
$3.000
|
|
PLOWABLE REFL PAV MRKR TY II-C-R
|
EA
|
1,063.000
|
$44.000
|
$70.000
|
$70.000
|
$70.000
|
|
REFL PAV MRKR TY I-R
|
EA
|
56.000
|
$7.500
|
$10.000
|
$10.000
|
$10.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
111.000
|
$3.800
|
$5.000
|
$5.000
|
$5.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
327.000
|
$5.000
|
$5.000
|
$5.000
|
$5.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
14,008.000
|
$0.350
|
$1.000
|
$1.000
|
$1.000
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
681.000
|
$0.800
|
$2.000
|
$2.000
|
$2.000
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
300.000
|
$1.500
|
$7.000
|
$7.000
|
$7.000
|
|
|
ELIM EXT PAV MRK & MRKS (18")(YLD TRI)
|
EA
|
4.000
|
$30.000
|
$10.000
|
$10.000
|
$10.000
|
|
|
ELIM EXT PAV MRK & MRKRS(PLOWABLE RPMS)
|
EA
|
105.000
|
$1.250
|
$50.000
|
$50.000
|
$50.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
97,913.000
|
$0.100
|
$0.100
|
$0.100
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (7")
|
LF
|
8,250.000
|
$0.050
|
$0.200
|
$0.200
|
$0.200
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
7,427.000
|
$0.200
|
$0.200
|
$0.200
|
$0.200
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
5,282.000
|
$0.500
|
$0.500
|
$0.500
|
$0.500
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
315.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
6.000
|
$30.000
|
$55.000
|
$55.000
|
$55.000
|
|
|
PAV SURF PREP FOR MRK (DBL ARROW)
|
EA
|
2.000
|
$50.000
|
$75.000
|
$75.000
|
$75.000
|
|
|
PAV SURF PREP FOR MRK (NUMBER)
|
EA
|
4.000
|
$52.000
|
$75.000
|
$75.000
|
$75.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
6.000
|
$32.000
|
$65.000
|
$65.000
|
$65.000
|
|
|
PAV SURF PREP FOR MRK (18")(YLD TRI)
|
EA
|
24.000
|
$15.000
|
$5.000
|
$5.000
|
$5.000
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
40.000
|
$26.000
|
$10.000
|
$10.000
|
$10.000
|
|
|
NO. OF WORKING DAYS
|
$/D
|
12,589.000
|
$893.000
|
$799.000
|
$638.000
|
$638.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
42,194.000
|
$75.000
|
$134.000
|
$135.000
|
$134.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
31,053.000
|
$95.000
|
$148.000
|
$149.000
|
$148.000
|
|
|
TACK COAT
|
GAL
|
522.000
|
$2.800
|
$20.000
|
$20.200
|
$20.000
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
8.000
|
$4,000.000
|
$5,000.000
|
$6,200.000
|
$5,250.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$8,161.000
|
$20,000.000
|
$17,000.000
|
$22,425.300
|
|
|
CCTV FIELD EQUIPMENT (DIGITAL)
|
EA
|
6.000
|
$7,000.000
|
$16,000.000
|
$15,200.000
|
$15,235.000
|
|
|
CCTV MOUNT (POLE)
|
EA
|
6.000
|
$750.000
|
$3,000.000
|
$3,000.000
|
$3,000.000
|
|
|
INSTALL DMS (POLE MTD CABINET)
|
EA
|
3.000
|
$15,000.000
|
$47,000.000
|
$46,900.000
|
$46,850.000
|
|
MULTIPOLYMER PAV MRK (W)(4")(SLD)
|
LF
|
41,352.000
|
$0.500
|
$0.650
|
$0.660
|
$0.660
|
|
MULTIPOLYMER PAV MRK (W)(4")(BRK)
|
LF
|
8,250.000
|
$1.000
|
$0.700
|
$0.720
|
$0.720
|
|
MULTIPOLYMER PAV MRK (W)(4")(DOT)
|
LF
|
651.000
|
$2.000
|
$1.950
|
$1.930
|
$1.930
|
|
MULTIPOLYMER PAV MRK (W)(8")(SLD)
|
LF
|
6,416.000
|
$1.500
|
$1.800
|
$1.820
|
$1.820
|
|
MULTIPOLYMER PAV MRK (W)(12")(SLD)
|
LF
|
3,492.000
|
$2.650
|
$4.000
|
$4.020
|
$4.020
|
|
MULTIPOLYMER PAV MRK (W)(12")(LNDP)
|
LF
|
954.000
|
$2.750
|
$4.400
|
$4.400
|
$4.400
|
|
MULTIPOLYMER PAV MRK (W)(24")(SLD)
|
LF
|
315.000
|
$6.500
|
$11.000
|
$11.000
|
$11.000
|
|
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
|
LF
|
14,211.000
|
$1.000
|
$0.700
|
$0.660
|
$0.660
|
|
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
|
LF
|
8,250.000
|
$0.700
|
$0.700
|
$0.720
|
$0.720
|
|
MULTIYPOLYMER PAV MRK (W) (ARROW)
|
EA
|
6.000
|
$155.000
|
$400.000
|
$402.000
|
$401.500
|
|
MULTIPOLYMER PAV MRK (W) (DBL ARROW)
|
EA
|
2.000
|
$284.000
|
$500.000
|
$495.000
|
$495.000
|
|
MULTIPOLYMER PAV MRK (W) (WORD)
|
EA
|
6.000
|
$244.000
|
$470.000
|
$462.000
|
$462.000
|
|
MULTIPOLYMER PAV MRK (W) 36" YLD TRI
|
EA
|
40.000
|
$30.000
|
$130.000
|
$132.000
|
$132.000
|
|
MULTIPOLYMER PAV MRK (W) (NUMBER)
|
EA
|
4.000
|
$325.000
|
$170.000
|
$171.000
|
$170.500
|
|
MULTIPOLYMER PAV MRK (W)(18")(YLD TRI)
|
EA
|
24.000
|
$25.000
|
$105.000
|
$105.000
|
$104.500
|
|
|
ITS POLE (50 FT)(90 MPH)
|
EA
|
4.000
|
$15,000.000
|
$19,000.000
|
$18,600.000
|
$18,600.000
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 2)
|
EA
|
6.000
|
$6,000.000
|
$7,200.000
|
$7,200.000
|
$7,200.000
|
|
|
TMA (STATIONARY)
|
DAY
|
3,660.000
|
$150.000
|
$360.000
|
$200.000
|
$150.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
98.000
|
$180.000
|
$560.000
|
$700.000
|
$857.720
|
|
|
TEMP Q-DETECT SYS
|
EA
|
3.000
|
$15,000.000
|
$200,000.000
|
$179,000.000
|
$178,765.250
|
|
|
TEMP Q-DETECT SYS (RELOCATE)
|
EA
|
1.000
|
$390.000
|
$1,199.970
|
$2,580.000
|
$2,575.000
|
|
|
REC REFL PAV MRKR TY II-A-A
|
EA
|
551.000
|
$33.000
|
$45.000
|
$45.000
|
$45.000
|
|
|
INSTALLATION OF CELLULAR MODEM
|
EA
|
8.000
|
$700.000
|
$2,300.000
|
$2,260.000
|
$2,260.000
|
|
|
SWR(SELECT BEDDING)
|
CY
|
785.000
|
$14.000
|
$29.000
|
$48.600
|
$75.000
|
|
|
SAN SWR MAIN STEEL CASING PIPE (BORE)
|
LF
|
400.000
|
$325.000
|
$370.000
|
$440.000
|
$400.000
|
|
|
TRENCH EXCAVATION SAFETY & SUPPORT
|
LF
|
2,548.000
|
$2.200
|
$5.000
|
$7.700
|
$3.000
|
|
|
SAN SWR (8")HDPE(ASTM D2837) ALL DEPTHS
|
LF
|
2,148.000
|
$85.000
|
$75.000
|
$85.000
|
$50.000
|
|
|
ABAND/FILL EXIST SAN SWR PIPE (8 IN)
|
LF
|
100.000
|
$15.000
|
$22.000
|
$80.000
|
$20.000
|
|
|
FM CONNECTION (FORCED MAIN)
|
EA
|
2.000
|
$4,520.000
|
$12,000.000
|
$4,300.000
|
$4,000.000
|
|
|
CONST SURV & STAKING (WATER & WW MAINS)
|
LF
|
4,596.000
|
$10.000
|
$2.000
|
$1.350
|
$5.000
|
|
|
WATER MAIN (PVC) (C-900) (4")
|
LF
|
3,826.000
|
$75.000
|
$40.000
|
$47.400
|
$30.000
|
|
|
GROUTING OF ABANDONED WATER MAINS
|
LF
|
100.000
|
$15.000
|
$25.000
|
$75.000
|
$100.000
|
|
|
CASING (STEEL) (10 IN) (BORED)
|
LF
|
319.000
|
$400.000
|
$220.000
|
$440.000
|
$300.000
|
|
|
CASING (STEEL) (16 IN) (BORED)
|
LF
|
707.000
|
$650.000
|
$320.000
|
$440.000
|
$500.000
|
|
|
10"X4" TAPPING SLEEVE AND VALVE
|
EA
|
1.000
|
$2,500.000
|
$6,500.000
|
$8,900.000
|
$5,000.000
|
|
|
4" GATE VALVE AND BOX
|
EA
|
7.000
|
$1,250.000
|
$2,500.000
|
$2,720.000
|
$1,000.000
|
|
|
10" DR-18 C900 PVC WATER LINE
|
LF
|
770.000
|
$90.000
|
$90.000
|
$105.000
|
$50.000
|
|
|
10" GATE VALVE AND BOX
|
EA
|
2.000
|
$2,500.000
|
$5,000.000
|
$4,720.000
|
$1,200.000
|
|
|
1" COMBINATION AIR RELEASE VALVE
|
EA
|
2.000
|
$3,500.000
|
$6,000.000
|
$7,300.000
|
$1,200.000
|
|
|
TRENCH, EMBED & BACKFILL (WATER)
|
LF
|
3,570.000
|
$15.000
|
$4.000
|
$8.800
|
$5.000
|
|
|
TRENCH SAFETY (WATER)
|
LF
|
3,570.000
|
$5.000
|
$5.000
|
$5.500
|
$5.000
|
|
|
2" FLUSH VALVE
|
EA
|
2.000
|
$2,000.000
|
$4,000.000
|
$6,000.000
|
$500.000
|
|
|
CUT & PLUG EXISTING 3" WATER LINES
|
EA
|
4.000
|
$1,000.000
|
$800.000
|
$1,550.000
|
$750.000
|
|
|
CONNECTING TO EXIST 3" & 10" WATER LINE
|
EA
|
4.000
|
$5,000.000
|
$2,000.000
|
$1,100.000
|
$750.000
|
|
Totals: |
$85,689,549.400
|
$127,043,010.191
|
$130,511,003.312
|
$140,450,481.999
|