County: NAVARRO Highway: FM1129 Date: 05/04/2022 (2 years ago) Engineer's Estimate: $971,751 Control Number: 6394-31-001
Project: RMC - 639431001 District: DALLAS Time: 365 CALENDAR DAYS Type: FLEXIBLE PAVEMENT STRUCTURE REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $971,750.75
RAYFORD'S TRUCK & TRACTOR   $1,256,342.00 1
29.29% | $284,591.25
D. L. LENNON INCORPORATED - CONTRACTOR   $1,270,177.00 2
30.71% | $298,426.25
1.1% | $13,835.00
A. K. GILLIS & SONS, LLC   $1,419,353.97 3
46.06% | $447,603.22
12.98% | $163,011.97
11.74% | $149,176.97
KNIFE RIVER CORPORATION - SOUTH   $2,151,612.70 4
121.42% | $1,179,861.95
71.26% | $895,270.70
51.59% | $732,258.73

Bid Items

Items: 12, 0 filtered
NAVARRO FM1129  |  DALLAS  |  6394-31-001  |  05/04/2022  |  $971,751  |  RMC - 639431001  |  FLEXIBLE PAVMT STRUCT REPAIR  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate RAYFORD'S TRUCK & TRACTOR D. L. LENNON INCORPORATED - CONTRACTOR A. K. GILLIS & SONS, LLC KNIFE RIVER CORPORATION - SOUTH
134 6002 BACKFILL (TY B) STA 154.000 $90.000 $100.000 $27.000 $45.000 $255.000
351 6045 FLEXIBLE PAV STR REPAIR 12"-TYPICAL B SY 100.000 $50.000 $115.000 $233.000 $131.770 $444.000
351 6052 FLEXIBLE PAV STR REPAIR 12"-TYPICAL E SY 16,500.000 $40.000 $58.000 $48.600 $58.930 $96.600
354 6004 PLAN & TEXT ASPH CONC PAV(0" TO 4") SY 9,243.000 $2.250 $4.000 $7.000 $5.790 $8.000
500 6001 MOBILIZATION LS 1.000 $89,712.000 $50,000.000 $64,860.000 $53,407.000 $108,145.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $1,500.000 $1,000.000 $14,000.000 $15,000.000 $2,415.000
672 6009 REFL PAV MRKR TY II-A-A EA 538.000 $3.500 $10.000 $8.000 $20.000 $38.500
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 1,190.000 $110.000 $140.000 $195.000 $195.000 $205.150
3077 6075 TACK COAT GAL 868.000 $1.750 $5.000 $3.000 $1.000 $6.650
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 20.000 $60.000 $150.000 $200.000 $200.000 $385.000
6185 6002 TMA (STATIONARY) DAY 78.000 $520.000 $25.000 $150.000 $150.000 $10.000
6185 6005 TMA (MOBILE OPERATION) DAY 4.000 $80.000 $50.000 $150.000 $150.000 $800.000
Totals: $971,750.75 $1,256,342.00 $1,270,177.00 $1,419,353.97 $2,151,612.70