NAVARRO IH 45 (0093-01-106)

Items: 37

County: NAVARRO
Length: N/A
Highway: IH 45
District: DALLAS
Control Number: 0093-01-106
DBE Goal: 500.0%
Project: F 2B24(067)
Guaranty: N/A
Time: 125 WORKING DAYS
Engineer's Estimate: $5,985,598.05
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: EMBANKMENT STABILIZATION
Mail/Deliver Bids To: N/A
JUAN PAREDES
ELECIA MOORE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$5,985,598.05
$7,778,331.00
Over/Under Est: 29.95% $1,792,732.95
Over/Under Est: 49.18% $2,943,765.16
Amt Left: 14.8% $1,151,032.21
Over/Under Est: 73.71% $4,412,111.47
Amt Left: 33.68% $2,619,378.52
Delta: -16.44% -$1,468,346.31
Subcontractor Percentage Amount
KELLER NORTH AMERICA, INC. 25.70% $2,144,530.73
Total: 25.70% $2,144,530.73

Bid Items & Bid Tabulations

37 Total 0 of 37
NAVARRO  |  IH 45  |  DALLAS  |  0093-01-106  |  08/01/2024  |  $5,985,598.05  |  F 2B24(067)  |  EMBANKMENT STABILIZATION  |  125 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNH CONSTRUCTION, LLC
MB WESTERN INDUSTRIAL CONTRACTING CO.
ED BELL CONSTRUCTION COMPANY
REMOVING CONC (RETAINING WALLS)
SY 1,188.000 $55.000 $100.000 $75.000 $50.000
REMOVING CONC (FLUME)
SY 1,104.500 $50.000 $100.000 $62.500 $25.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 75,662.000 $25.000 $35.000 $45.000 $40.000
COMPOST MANUF TOPSOIL (4")
SY 9,200.000 $4.000 $10.000 $1.380 $8.000
BLOCK SODDING
SY 9,200.000 $13.000 $10.000 $6.110 $6.500
DRILL SEED (TEMP)(WARM OR COOL)
SY 9,200.000 $0.500 $2.000 $0.460 $0.500
VEGETATIVE WATERING
MG 2,738.000 $25.000 $20.000 $68.380 $3.000
TEMPORARY SPL SHORING
SF 38,940.000 $34.000 $55.000 $54.640 $59.000
CL A CONC (FLUME)
CY 210.500 $1,000.000 $2,000.000 $769.280 $1,365.000
CL B CONC (FLUME)
CY 9.500 $1,000.000 $2,000.000 $769.280 $1,365.000
RETAINING WALL (MSE)
SF 15,184.000 $80.000 $55.000 $115.000 $192.000
RIPRAP (CONC) (CL B) (4")
CY 76.000 $750.000 $550.000 $789.000 $1,365.000
RIPRAP (MOW STRIP)(4 IN)
CY 14.300 $715.000 $550.000 $821.880 $1,365.000
RC PIPE (CL III)(18 IN)
LF 34.000 $100.000 $200.000 $316.920 $150.000
INL(CMP)(PAZD-CZ)(FG)(5FTX5FT-4FTX4FT)
EA 2.000 $9,000.000 $15,000.000 $12,337.330 $30,000.000
MOBILIZATION
LS 1.000 $543,826.550 $700,000.000 $600,000.000 $960,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $10,000.000 $8,500.000 $7,500.000 $31,500.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 356.000 $60.000 $30.000 $78.900 $25.000
ROCK FILTER DAMS (REMOVE)
LF 356.000 $15.000 $15.000 $19.730 $12.500
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 4,678.000 $6.000 $18.000 $5.260 $2.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,678.000 $3.000 $9.000 $1.320 $0.500
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 390.000 $50.000 $100.000 $124.930 $105.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 390.000 $20.000 $20.000 $46.030 $73.500
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $30.000 $50.000 $28.270 $23.650
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,400.000 $2,500.000 $2,498.500 $2,956.010
REMOVE METAL BEAM GUARD FENCE
LF 250.000 $7.000 $5.000 $3.290 $2.750
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $300.000 $500.000 $328.750 $275.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,025.000 $3,500.000 $3,780.630 $3,162.500
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $400.000 $1,500.000 $328.750 $275.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,000.000 $3,000.000 $1,117.750 $1,575.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $11,000.000 $30,000.000 $9,205.000 $12,600.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 3.000 $40.000 $100.000 $78.900 $22.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 3,335.000 $15.000 $10.000 $25.000 $10.000
DRAIN INLET CLEANING
EA 8.000 $1,300.000 $2,500.000 $450.000 $1,250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $18,500.000 $10,000.000 $12,500.000
TMA (STATIONARY)
DAY 140.000 $400.000 $250.000 $200.000 $210.000
TMA (MOBILE OPERATION)
HR 8.000 $60.000 $55.000 $50.000 $210.000
Totals: $5,985,598.050 $7,778,331.000 $8,929,363.214 $10,397,709.520