County: NACOGDOCHES Highway: FM0343 Date: 05/28/2024 (5 months ago) Engineer's Estimate: $230,000 Control Number: 6467-80-001
Project: MMC - 646780001 District: LUFKIN Time: 180 CALENDAR DAYS Type: HOT MIX/SP, TY C & D/NACOGDOCHES
Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $230,000.00
LONGVIEW ASPHALT, INC.   $233,300.00 1
1.43% | $3,300.00
TEXAS MATERIALS GROUP, INC.   $254,050.00 2
10.46% | $24,050.00
8.89% | $20,750.00

Bid Items

Items: 3, 0 filtered
NACOGDOCHES FM0343  |  LUFKIN  |  6467-80-001  |  05/28/2024  |  $230,000  |  MMC - 646780001  |  HOT MIX/SP, TY C & D/NACOGDOCHES  |  180 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate LONGVIEW ASPHALT, INC. TEXAS MATERIALS GROUP, INC.
8006 6016 SP TY C PG 76-22 (PICKUP) TON 1,000.000 $120.000 $119.900 $135.000
8011 6001 D-GR HMA(SQ) TY D PG 64-22 (PICKUP) TON 500.000 $110.000 $113.900 $119.050
8011 6016 D-GR HMA(SQ)TY C PG 64-22 (PICKUP) TON 500.000 $110.000 $112.900 $119.050
Totals: $230,000.00 $233,300.00 $254,050.00