County: MORRIS Highway: US0067 Date: 09/04/2024 (2 months ago) Engineer's Estimate: $995,529 Control Number: 6464-21-001
Project: BPM - 646421001 District: ATLANTA Time: 90 W Type: BRIDGE PREVENTATIVE MAINTENANCE
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $995,529.07
GARRET SHIELDS INFRASTRUCTURE   $842,650.00 1
-15.36% | -$152,879.07
PATHFIELD INVESTMENTS LLC   $875,845.00 2
-12.02% | -$119,684.07
3.94% | $33,195.00
AAD CONTRACTING INC.   $963,315.00 3
-3.24% | -$32,214.07
14.32% | $120,665.00
9.99% | $87,470.00
ROAD DOCTORS LLC   $1,161,770.00 4
16.7% | $166,240.93
37.87% | $319,120.00
20.60% | $198,455.00

Bid Items

Items: 17, 0 filtered
MORRIS US0067  |  ATLANTA  |  6464-21-001  |  09/04/2024  |  $995,529  |  BPM - 646421001  |  BRIDGE PREVENT MAINT  |  90 W
Item code Description Unit Quantity Engineer's Estimate GARRET SHIELDS INFRASTRUCTURE PATHFIELD INVESTMENTS LLC AAD CONTRACTING INC. ROAD DOCTORS LLC
104 7028 REMOV CONC (WINGWALL) CY 45.000 $925.000 $400.000 $150.000 $100.000 $290.000
110 7002 EXCAV (CHANNEL) CY 1,223.000 $55.000 $70.000 $110.000 $40.000 $60.000
132 7001 EMBANK (FNL)(OC)(TY A) CY 121.000 $75.000 $60.000 $125.000 $120.000 $120.000
403 7001 TEMPORARY SPL SHORING SF 1,260.000 $50.000 $60.000 $10.000 $20.000 $30.000
429 7007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 200.000 $250.000 $250.000 $250.000 $275.000 $150.000
432 7043 RIPRAP (STONE PROTECTION)(18 IN) CY 348.000 $257.000 $300.000 $350.000 $250.000 $250.000
432 7050 BEDDING MATERIAL (6 IN) CY 88.000 $225.000 $100.000 $130.000 $120.000 $350.000
466 7148 WINGWALL (FW - 0) (HW=6 FT) EA 2.000 $18,190.000 $15,000.000 $18,000.000 $30,000.000 $67,000.000
466 7149 WINGWALL (FW - 0) (HW=7 FT) EA 1.000 $21,500.000 $25,000.000 $22,000.000 $33,000.000 $70,000.000
466 7153 WINGWALL (FW - 0) (HW=11 FT) EA 2.000 $47,375.000 $30,000.000 $23,000.000 $40,000.000 $80,000.000
466 7165 WINGWALL (FW - S) (HW=9 FT) EA 2.000 $37,000.000 $30,000.000 $24,000.000 $35,000.000 $75,000.000
466 7166 WINGWALL (FW - S) (HW=10 FT) EA 2.000 $45,000.000 $25,000.000 $25,000.000 $35,000.000 $78,000.000
480 7002 CLEAN EXIST CULVERTS CY 1,501.000 $120.000 $80.000 $100.000 $115.000 $20.000
500 7001 MOBILIZATION LS 1.000 $65,128.070 $90,000.000 $80,000.000 $100,000.000 $120,000.000
502 7004 BARRICADES, SIGNS AND TRAFFIC HANDLING EA 6.000 $6,500.000 $5,000.000 $10,000.000 $10,000.000 $5,000.000
503 7001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 90.000 $220.000 $10.000 $150.000 $400.000 $180.000
505 7001 TMA (STATIONARY) DAY 90.000 $385.000 $300.000 $200.000 $400.000 $100.000
Totals: $995,529.07 $842,650.00 $875,845.00 $963,315.00 $1,161,770.00