Job Info for 1574-01-018

County: MORRIS Highway: FM 161 Date: 04/05/2024 (7 months ago) Engineer's Estimate: $3,914,751 Control Number: 1574-01-018
Project: C 1574-1-18 District: ATLANTA Time: 193 WORKING DAYS Type: WIDEN ROAD - ADD SHOULDERS
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,914,750.50
A. K. GILLIS & SONS, LLC   $3,791,092.27 1
-3.16% | -$123,658.23
EAST TEXAS BRIDGE, INC.   $4,497,775.25 2
14.89% | $583,024.75
18.64% | $706,682.98
Subcontractor Percentage Amount
BAHENA CONSTRUCTION CO.,INC. 14.12% $535,302.23
WITHERS CONSTRUCTION, LLC 4.20% $159,225.88
STRIPING TECHNOLOGY, L.P. 3.23% $122,452.28
DUSTIN ALLEN, INC. 2.39% $90,607.11
SOUTHWEST ENVIRONMENT SERVICES LLC 1.16% $43,976.67
PANOLA SIGN & BARRICADE, INC. 0.72% $27,295.86
SOUTHERN CROSS CONTRACTORS, LLC 0.39% $14,785.26
J. H. ODEN CONTRACTING COMPANY 0.25% $9,477.73
Total: 26.46% $1,003,123.02

Bid Items

Items: 73, 0 filtered
MORRIS FM 161  |  ATLANTA  |  1574-01-018  |  04/05/2024  |  $3,914,751  |  C 1574-1-18  |  WIDEN ROAD - ADD SHOULDERS  |  193 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate A. K. GILLIS & SONS, LLC EAST TEXAS BRIDGE, INC.
100 6002 PREPARING ROW STA 110.000 $3,500.000 $1,700.000 $7,400.000
112 6001 SUBGRADE WIDENING (ORD COMP) STA 156.300 $475.000 $293.280 $575.000
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 2,071.000 $85.000 $15.000 $32.000
134 6002 BACKFILL (TY B) STA 156.300 $300.000 $293.280 $485.000
150 6001 BLADING STA 190.300 $250.000 $401.270 $400.000
247 6231 FL BS (CMP IN PLACE)(TY A GR 1-2)(10") SY 8,682.000 $40.000 $92.450 $50.000
310 6009 PRIME COAT (MC-30) GAL 2,923.000 $9.000 $7.310 $7.000
316 6017 ASPH (AC-20-5TR) GAL 23,243.000 $9.750 $5.260 $6.750
316 6126 AGGR(TY-PB GR-4 SAC-A) CY 492.000 $230.000 $242.830 $275.000
400 6007 CUT & RESTORE CONC PAVING SY 34.000 $245.000 $200.000 $300.000
400 6008 CUT & RESTORE ASPH PAVING SY 800.000 $150.000 $100.000 $90.000
402 6001 TRENCH EXCAVATION PROTECTION LF 80.000 $25.000 $25.000 $50.000
403 6001 TEMPORARY SPL SHORING SF 3,760.000 $85.000 $35.000 $60.000
420 6001 CL A CONC (SEAL) CY 16.000 $100.000 $500.000 $1,000.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 60.000 $160.000 $175.000 $375.000
432 6001 RIPRAP (CONC)(4 IN) CY 147.000 $500.000 $625.000 $1,000.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 120.000 $175.000 $319.000 $200.000
432 6039 BEDDING MATERIAL (6 IN) CY 60.000 $170.000 $313.000 $200.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 246.000 $600.000 $650.000 $750.000
450 6018 RAIL (TY T631) LF 225.000 $104.000 $89.000 $120.000
462 6063 CONC BOX CULV (8 FT X 4 FT)(EXTEND) LF 73.000 $740.000 $1,400.000 $2,000.000
462 6093 CONC BOX CULV (5 FT X 6 FT) (EXTEND) LF 12.000 $1,200.000 $1,200.000 $2,000.000
464 6003 RC PIPE (CL III)(18 IN) LF 20.000 $75.000 $70.000 $80.000
464 6005 RC PIPE (CL III)(24 IN) LF 919.000 $110.000 $90.000 $100.000
466 6181 WINGWALL (PW - 1) (HW=6 FT) EA 4.000 $30,000.000 $28,000.000 $27,500.000
466 6183 WINGWALL (PW - 1) (HW=8 FT) EA 2.000 $30,000.000 $38,000.000 $15,000.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 8.000 $1,500.000 $900.000 $1,000.000
467 6388 SET (TY II) (24 IN) (RCP) (3: 1) (C) EA 2.000 $1,500.000 $1,250.000 $1,200.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 20.000 $2,000.000 $1,400.000 $1,400.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 123.000 $1,800.000 $1,500.000 $1,400.000
496 6006 REMOV STR (HEADWALL) EA 20.000 $2,000.000 $1,250.000 $1,500.000
496 6007 REMOV STR (PIPE) LF 135.000 $30.000 $15.000 $25.000
500 6001 MOBILIZATION LS 1.000 $329,000.000 $484,067.000 $435,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $3,500.000 $9,000.000 $15,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 135.000 $40.000 $75.000 $65.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 135.000 $10.000 $15.000 $15.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 160.000 $35.000 $5.000 $6.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 160.000 $2.250 $3.000 $2.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 6.000 $8,000.000 $3,000.000 $10,000.000
512 6072 PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL) LF 840.000 $25.000 $111.000 $100.000
512 6076 PTB (REMOVE)(SGL SLP)(TY 1) OR (STL) LF 840.000 $30.000 $27.000 $25.000
530 6009 TURNOUTS (SURF TREAT) SY 335.000 $75.000 $150.000 $75.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,262.500 $26.000 $24.000 $26.000
540 6033 MTL BM GD FEN (LONG SPAN SYSTEM) EA 4.000 $1,300.000 $1,200.000 $1,500.000
544 6004 GDRAIL END TRT(INST)(WOOD POST)(TY I) EA 12.000 $2,800.000 $2,900.000 $3,200.000
545 6002 CRASH CUSH ATTEN (DES SOURCE) EA 2.000 $2,500.000 $3,500.000 $3,500.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $2,000.000 $2,500.000 $2,500.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $1,000.000 $1,500.000 $1,000.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 7.000 $775.000 $710.000 $750.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 2.000 $1,000.000 $1,006.000 $1,100.000
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 1.000 $925.000 $1,163.000 $850.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 2.000 $1,100.000 $989.000 $900.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 35.000 $525.000 $434.000 $550.000
644 6061 IN SM RD SN SUP&AM TYTWT(1)WS(T) EA 1.000 $775.000 $631.000 $650.000
644 6071 RELOCATE SM RD SN SUP&AM TY TWT EA 53.000 $450.000 $342.000 $575.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 20.000 $25.000 $52.950 $55.000
662 6050 WK ZN PAV MRK REMOV (REFL) TY II-A-A EA 240.000 $6.000 $5.000 $5.500
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 5,800.000 $2.000 $1.500 $1.650
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 40.000 $15.000 $10.000 $11.000
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 9,600.000 $2.000 $1.500 $1.650
662 6110 WK ZN PAV MRK SHT TERM (TAB)TY Y EA 405.000 $1.250 $2.350 $5.500
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,537.000 $1.000 $2.350 $3.000
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 32.000 $13.000 $15.000 $17.000
672 6009 REFL PAV MRKR TY II-A-A EA 405.000 $4.000 $5.000 $5.500
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 2,200.000 $0.500 $1.000 $1.100
4171 6001 INSTALL BRIDGE IDENTIFICATION NUMBERS EA 4.000 $1,000.000 $1,000.000 $2,000.000
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 6,652.000 $15.000 $4.000 $4.500
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 3,328.000 $15.000 $4.000 $4.500
6149 6004 REFL PAV MRK AWT (W) 6" (SLD) (100MIL) LF 33,710.000 $2.250 $0.850 $1.000
6149 6010 REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) LF 27,370.000 $2.500 $0.850 $1.000
6149 6011 REFL PAV MRK AWT (Y) 6" (BRK) (100MIL) LF 1,440.000 $2.500 $1.000 $1.100
6185 6002 TMA (STATIONARY) DAY 173.000 $350.000 $250.000 $300.000
6185 6005 TMA (MOBILE OPERATION) DAY 40.000 $300.000 $250.000 $300.000
Totals: $3,914,750.50 $3,791,092.28 $4,497,775.25