MONTGOMERY FM 2854 (2744-01-032)

Items: 70

County: MONTGOMERY
Length: N/A
Highway: FM 2854
District: HOUSTON
Control Number: 2744-01-032
DBE Goal: N/A
Project: C 2744-1-32
Guaranty: N/A
Time: 135 WORKING DAYS
Engineer's Estimate: $11,121,060.10
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: BASE REPAIR, OCST, 1.5" HMA LEVEL-UP AND 1.5" HMA
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$11,121,060.10
$10,866,955.64
Over/Under Est: -2.28% -$254,104.46
Over/Under Est: 1.49% $165,637.59
Amt Left: 3.86% $419,742.05
Over/Under Est: 1.51% $167,458.06
Amt Left: 3.88% $421,562.52
Delta: -0.02% -$1,820.47
Over/Under Est: 9.65% $1,072,911.54
Amt Left: 12.21% $1,327,016.00
Delta: -8.02% -$905,453.48
Subcontractor Percentage Amount
BATTERSON, LLP 6.20% $735,128.23
HOUSTON CONST TODAY INC 1.24% $147,025.65
GREEN SAGE SERVICES LLC 1.23% $145,839.96
WILLOW CITY SIGN & RAIL, INC. 0.90% $106,712.16
LONESTAR TRAFFIC SAFETY, LLC 0.13% $15,413.98
SARVICUS LLC 0.05% $5,928.45
Total: 9.75% $1,156,048.43

Bid Items & Bid Tabulations

70 Total 0 of 70
MONTGOMERY  |  FM 2854  |  HOUSTON  |  2744-01-032  |  08/04/2022  |  $11,121,060.10  |  C 2744-1-32  |  BASE REPAIR, OCST, 1.5" HMA LEVEL-UP...  |  135 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
JAMES CONSTRUCTION GROUP, LLC
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
DURWOOD GREENE CONSTRUCTION CO.
PREPARING ROW
STA 71.000 $5,000.000 $2,040.000 $100.000 $116.720 $1,000.000
REMOVING STAB BASE & ASPH PAV (12")
SY 780.000 $45.000 $9.150 $16.000 $3.510 $55.000
EXCAVATION (ROADWAY)
CY 3,556.000 $10.000 $62.710 $6.250 $16.440 $45.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 85.000 $18.500 $56.000 $13.250 $36.290 $40.000
BACKFILL (TY A)
STA 745.000 $210.000 $660.000 $800.000 $763.720 $700.000
BLOCK SODDING
SY 21,355.000 $4.800 $4.400 $4.900 $6.740 $4.000
FERTILIZER
AC 4.400 $1,150.000 $850.000 $1,000.000 $1,405.750 $1,000.000
VEGETATIVE WATERING
MG 530.000 $21.750 $84.000 $20.600 $35.100 $40.000
LIME TRT (EXST MATL) (6")
SY 4,274.000 $6.500 $11.750 $22.500 $9.040 $15.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 30.000 $220.000 $304.500 $431.000 $340.890 $500.000
CEMENT
TON 30.000 $320.000 $324.500 $247.000 $392.860 $500.000
CEMENT TREAT (EXIST MATL) (6")
SY 4,274.000 $4.000 $6.500 $14.000 $9.040 $15.000
ASPHALT STAB BASE (GR 2)(PG 64)
TON 4,654.000 $127.800 $106.850 $106.000 $96.560 $120.000
SALV, HAUL & STKPL RCL APH PV (4 TO 6")
SY 780.000 $15.000 $8.000 $90.000 $17.560 $16.000
ASPH (MULTI OPTION)
GAL 99,432.000 $4.250 $4.400 $4.900 $4.910 $4.500
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
CY 2,390.000 $135.000 $173.650 $150.150 $185.660 $190.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 15,296.000 $40.000 $65.310 $70.000 $74.000 $40.000
PLANE ASPH CONC PAV(2" TO 4")
SY 4,397.000 $6.750 $6.850 $9.500 $3.880 $4.500
PLANE ASPH CONC PAV (2")
SY 335,822.000 $3.000 $3.170 $2.350 $2.630 $3.000
MOBILIZATION
LS 1.000 $1,162,857.250 $409,000.000 $565,000.000 $562,695.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $6,000.000 $1,021.670 $30,000.000 $29,859.900 $4,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 13,253.000 $2.500 $2.550 $3.760 $3.920 $2.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 13,253.000 $0.500 $1.100 $0.830 $1.170 $1.000
INTERSECTIONS (ACP)
SY 7,586.000 $50.000 $23.650 $20.000 $22.720 $35.000
DRIVEWAYS (ACP)
SY 17,508.000 $35.000 $20.000 $20.250 $21.410 $35.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 5.000 $265.000 $305.000 $305.000 $357.290 $375.000
ALUMINUM SIGNS (TY A)
SF 144.000 $35.000 $24.500 $24.500 $28.700 $27.000
ALUMINUM SIGNS (TY O)
SF 82.600 $30.000 $45.000 $42.000 $52.720 $28.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 84.000 $700.000 $430.000 $430.000 $503.730 $475.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 63.000 $800.000 $600.000 $600.000 $702.870 $720.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $800.000 $695.000 $695.000 $814.160 $900.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P-EXAL)
EA 2.000 $2,100.000 $1,075.000 $1,075.000 $1,259.310 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 12.000 $1,000.000 $805.000 $805.000 $943.020 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 2.000 $1,025.000 $1,100.000 $1,100.000 $1,288.600 $1,400.000
REMOVE SM RD SN SUP&AM
EA 146.000 $105.000 $60.000 $60.000 $70.290 $100.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 1.000 $150.000 $45.000 $45.000 $52.720 $150.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 5,433.000 $0.300 $0.290 $0.290 $0.340 $0.300
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 451,995.000 $0.300 $0.290 $0.290 $0.340 $0.300
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 31,167.000 $0.500 $0.330 $0.330 $0.390 $0.350
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 1,230.000 $3.000 $2.000 $2.000 $2.340 $2.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 3,798.000 $3.000 $4.000 $4.000 $4.690 $4.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 198.000 $80.000 $85.000 $85.000 $99.570 $85.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 180.000 $83.000 $85.000 $85.000 $99.570 $85.000
WK ZN PV MK NON-REM (Y)(4")BKN W/MRKR
LF 37,383.000 $1.500 $0.550 $0.550 $0.640 $0.550
WK ZN PV MK NON-REM (Y)(4")SLD W/MRKR
LF 366,483.000 $1.500 $0.550 $0.550 $0.640 $0.550
REFL PAV MRK TY I (W)8"(BRK)(100MIL)
LF 409.000 $2.000 $1.250 $1.250 $1.460 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 10,389.000 $1.200 $0.950 $0.950 $1.110 $0.950
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,266.000 $7.000 $6.000 $6.000 $7.030 $6.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 11,050.000 $5.900 $6.000 $6.000 $7.030 $6.000
PAVEMENT SEALER 6"
LF 8,805.000 $0.160 $0.250 $0.250 $0.290 $0.250
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,811.000 $0.600 $0.590 $0.590 $0.690 $0.590
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 150,665.000 $0.500 $0.500 $0.500 $0.590 $0.500
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 12,461.000 $0.500 $0.500 $0.500 $0.590 $0.500
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 122,161.000 $0.500 $0.500 $0.500 $0.590 $0.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 66.000 $225.000 $220.000 $220.000 $257.720 $220.000
PREFAB PAV MRK TY C (W) (WORD)
EA 60.000 $250.000 $250.000 $250.000 $292.860 $250.000
REFL PAV MRKR TY I-C
EA 533.000 $5.000 $5.000 $5.000 $5.860 $5.000
REFL PAV MRKR TY II-A-A
EA 4,141.000 $4.500 $5.000 $5.000 $5.860 $5.000
PAV SURF PREP FOR MRK (6")
LF 294,092.000 $0.050 $0.050 $0.050 $0.060 $0.050
PAV SURF PREP FOR MRK (8")
LF 10,798.000 $0.150 $0.100 $0.100 $0.120 $0.100
PAV SURF PREP FOR MRK (24")
LF 12,316.000 $1.000 $1.000 $1.000 $1.170 $1.000
PAV SURF PREP FOR MRK (ARROW)
EA 66.000 $22.000 $10.000 $10.000 $11.710 $10.000
PAV SURF PREP FOR MRK (WORD)
EA 60.000 $20.000 $10.000 $10.000 $11.710 $10.000
D-GR HMA TY-D SAC-A PG70-22
TON 34,201.000 $107.000 $125.000 $134.000 $126.000 $155.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 936.000 $140.000 $144.080 $180.000 $178.560 $155.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 110.000 $130.000 $115.000 $169.000 $95.870 $100.000
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 722.000 $1.250 $10.500 $10.000 $11.710 $10.000
MULTIPOLYMER PAV MRK (Y)(6")(BRK)
LF 90.000 $1.000 $10.500 $10.000 $11.710 $10.000
TMA (STATIONARY)
DAY 100.000 $250.000 $406.000 $228.000 $301.860 $175.000
TMA (MOBILE OPERATION)
HR 56.000 $75.000 $83.000 $58.000 $29.290 $50.000
Totals: $11,121,060.100 $10,866,955.640 $11,286,697.690 $11,288,518.162 $12,193,971.640