Job Info for 2744-01-032

County: MONTGOMERY Highway: FM 2854 Date: 08/04/2022 (2 years ago) Engineer's Estimate: $11,121,060 Control Number: 2744-01-032
Project: C 2744-1-32 District: HOUSTON Time: 135 WORKING DAYS Type: BASE REPAIR, OCST, 1.5" HMA LEVEL-UP AND 1.5" HMA
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Rev 1 | Rev 2 | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $11,121,060.10
TEXAS MATERIALS GROUP, INC.   $10,866,955.64 1
-2.28% | -$254,104.46
JAMES CONSTRUCTION GROUP, LLC   $11,286,697.69 2
1.49% | $165,637.59
3.86% | $419,742.05
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC   $11,288,518.16 3
1.51% | $167,458.06
3.88% | $421,562.52
0.02% | $1,820.47
DURWOOD GREENE CONSTRUCTION CO.   $12,193,971.64 4
9.65% | $1,072,911.54
12.21% | $1,327,016.00
8.02% | $905,453.48
Subcontractor Percentage Amount
BATTERSON, LLP 6.76% $734,606.20
HOUSTON CONST TODAY INC 1.35% $146,703.90
GREEN SAGE SERVICES LLC 1.34% $145,617.21
WILLOW CITY SIGN & RAIL, INC. 0.98% $106,496.17
LONESTAR TRAFFIC SAFETY, LLC 0.14% $15,213.74
SARVICUS LLC 0.05% $5,433.48
Total: 10.62% $1,154,070.70

Bid Items

Items: 70, 0 filtered
MONTGOMERY FM 2854  |  HOUSTON  |  2744-01-032  |  08/04/2022  |  $11,121,060  |  C 2744-1-32  |  BASE REPAIR, OCST, 1.5" HMA LEVEL-UP AND 1.5" HMA  |  135 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TEXAS MATERIALS GROUP, INC. JAMES CONSTRUCTION GROUP, LLC VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC DURWOOD GREENE CONSTRUCTION CO.
100 6002 PREPARING ROW STA 71.000 $5,000.000 $2,040.000 $100.000 $116.720 $1,000.000
105 6020 REMOVING STAB BASE & ASPH PAV (12") SY 780.000 $45.000 $9.150 $16.000 $3.510 $55.000
110 6001 EXCAVATION (ROADWAY) CY 3,556.000 $10.000 $62.710 $6.250 $16.440 $45.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 85.000 $18.500 $56.000 $13.250 $36.290 $40.000
134 6001 BACKFILL (TY A) STA 745.000 $210.000 $660.000 $800.000 $763.720 $700.000
162 6002 BLOCK SODDING SY 21,355.000 $4.800 $4.400 $4.900 $6.740 $4.000
166 6001 FERTILIZER AC 4.400 $1,150.000 $850.000 $1,000.000 $1,405.750 $1,000.000
168 6001 VEGETATIVE WATERING MG 530.000 $21.750 $84.000 $20.600 $35.100 $40.000
260 6006 LIME TRT (EXST MATL) (6") SY 4,274.000 $6.500 $11.750 $22.500 $9.040 $15.000
260 6012 LIME(HYD,COM OR QK)(SLRY)OR QK(DRY) TON 30.000 $220.000 $304.500 $431.000 $340.890 $500.000
275 6001 CEMENT TON 30.000 $320.000 $324.500 $247.000 $392.860 $500.000
275 6002 CEMENT TREAT (EXIST MATL) (6") SY 4,274.000 $4.000 $6.500 $14.000 $9.040 $15.000
292 6002 ASPHALT STAB BASE (GR 2)(PG 64) TON 4,654.000 $127.800 $106.850 $106.000 $96.560 $120.000
305 6004 SALV, HAUL & STKPL RCL APH PV (4 TO 6") SY 780.000 $15.000 $8.000 $90.000 $17.560 $16.000
316 6001 ASPH (MULTI OPTION) GAL 99,432.000 $4.250 $4.400 $4.900 $4.910 $4.500
316 6434 AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B) CY 2,390.000 $135.000 $173.650 $150.150 $185.660 $190.000
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 15,296.000 $40.000 $65.310 $70.000 $74.000 $40.000
354 6024 PLANE ASPH CONC PAV(2" TO 4") SY 4,397.000 $6.750 $6.850 $9.500 $3.880 $4.500
354 6045 PLANE ASPH CONC PAV (2") SY 335,822.000 $3.000 $3.170 $2.350 $2.630 $3.000
500 6001 MOBILIZATION LS 1.000 $1,162,857.250 $409,000.000 $565,000.000 $562,695.000 $700,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $6,000.000 $1,021.670 $30,000.000 $29,859.900 $4,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 13,253.000 $2.500 $2.550 $3.760 $3.920 $2.750
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 13,253.000 $0.500 $1.100 $0.830 $1.170 $1.000
530 6002 INTERSECTIONS (ACP) SY 7,586.000 $50.000 $23.650 $20.000 $22.720 $35.000
530 6005 DRIVEWAYS (ACP) SY 17,508.000 $35.000 $20.000 $20.250 $21.410 $35.000
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 5.000 $265.000 $305.000 $305.000 $357.290 $375.000
636 6001 ALUMINUM SIGNS (TY A) SF 144.000 $35.000 $24.500 $24.500 $28.700 $27.000
636 6003 ALUMINUM SIGNS (TY O) SF 82.600 $30.000 $45.000 $42.000 $52.720 $28.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 84.000 $700.000 $430.000 $430.000 $503.730 $475.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 63.000 $800.000 $600.000 $600.000 $702.870 $720.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 2.000 $800.000 $695.000 $695.000 $814.160 $900.000
644 6018 IN SM RD SN SUP&AM TY10BWG(2)SA(P-EXAL) EA 2.000 $2,100.000 $1,075.000 $1,075.000 $1,259.310 $1,500.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 12.000 $1,000.000 $805.000 $805.000 $943.020 $1,000.000
644 6036 IN SM RD SN SUP&AM TYS80(1)SA(U-BM) EA 2.000 $1,025.000 $1,100.000 $1,100.000 $1,288.600 $1,400.000
644 6076 REMOVE SM RD SN SUP&AM EA 146.000 $105.000 $60.000 $60.000 $70.290 $100.000
644 6078 REMOVE SM RD SN SUP&AM (SIGN ONLY) EA 1.000 $150.000 $45.000 $45.000 $52.720 $150.000
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 5,433.000 $0.300 $0.290 $0.290 $0.340 $0.300
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 451,995.000 $0.300 $0.290 $0.290 $0.340 $0.300
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 31,167.000 $0.500 $0.330 $0.330 $0.390 $0.350
662 6014 WK ZN PAV MRK NON-REMOV (W)12"(SLD) LF 1,230.000 $3.000 $2.000 $2.000 $2.340 $2.000
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 3,798.000 $3.000 $4.000 $4.000 $4.690 $4.000
662 6017 WK ZN PAV MRK NON-REMOV (W)(ARROW) EA 198.000 $80.000 $85.000 $85.000 $99.570 $85.000
662 6029 WK ZN PAV MRK NON-REMOV(W)(WORD) EA 180.000 $83.000 $85.000 $85.000 $99.570 $85.000
662 6044 WK ZN PV MK NON-REM (Y)(4")BKN W/MRKR LF 37,383.000 $1.500 $0.550 $0.550 $0.640 $0.550
662 6045 WK ZN PV MK NON-REM (Y)(4")SLD W/MRKR LF 366,483.000 $1.500 $0.550 $0.550 $0.640 $0.550
666 6027 REFL PAV MRK TY I (W)8"(BRK)(100MIL) LF 409.000 $2.000 $1.250 $1.250 $1.460 $1.250
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 10,389.000 $1.200 $0.950 $0.950 $1.110 $0.950
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 1,266.000 $7.000 $6.000 $6.000 $7.030 $6.000
666 6147 REFL PAV MRK TY I (Y)24"(SLD)(100MIL) LF 11,050.000 $5.900 $6.000 $6.000 $7.030 $6.000
666 6225 PAVEMENT SEALER 6" LF 8,805.000 $0.160 $0.250 $0.250 $0.290 $0.250
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 1,811.000 $0.600 $0.590 $0.590 $0.690 $0.590
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 150,665.000 $0.500 $0.500 $0.500 $0.590 $0.500
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 12,461.000 $0.500 $0.500 $0.500 $0.590 $0.500
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 122,161.000 $0.500 $0.500 $0.500 $0.590 $0.500
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 66.000 $225.000 $220.000 $220.000 $257.720 $220.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 60.000 $250.000 $250.000 $250.000 $292.860 $250.000
672 6007 REFL PAV MRKR TY I-C EA 533.000 $5.000 $5.000 $5.000 $5.860 $5.000
672 6009 REFL PAV MRKR TY II-A-A EA 4,141.000 $4.500 $5.000 $5.000 $5.860 $5.000
678 6002 PAV SURF PREP FOR MRK (6") LF 294,092.000 $0.050 $0.050 $0.050 $0.060 $0.050
678 6004 PAV SURF PREP FOR MRK (8") LF 10,798.000 $0.150 $0.100 $0.100 $0.120 $0.100
678 6008 PAV SURF PREP FOR MRK (24") LF 12,316.000 $1.000 $1.000 $1.000 $1.170 $1.000
678 6009 PAV SURF PREP FOR MRK (ARROW) EA 66.000 $22.000 $10.000 $10.000 $11.710 $10.000
678 6016 PAV SURF PREP FOR MRK (WORD) EA 60.000 $20.000 $10.000 $10.000 $11.710 $10.000
3076 6041 D-GR HMA TY-D SAC-A PG70-22 TON 34,201.000 $107.000 $125.000 $134.000 $126.000 $155.000
3076 6043 D-GR HMA TY-D PG70-22 (LEVEL-UP) TON 936.000 $140.000 $144.080 $180.000 $178.560 $155.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 110.000 $130.000 $115.000 $169.000 $95.870 $100.000
6038 6004 MULTIPOLYMER PAV MRK (W)(6")(SLD) LF 722.000 $1.250 $10.500 $10.000 $11.710 $10.000
6038 6018 MULTIPOLYMER PAV MRK (Y)(6")(BRK) LF 90.000 $1.000 $10.500 $10.000 $11.710 $10.000
6185 6002 TMA (STATIONARY) DAY 100.000 $250.000 $406.000 $228.000 $301.860 $175.000
6185 6003 TMA (MOBILE OPERATION) HR 56.000 $75.000 $83.000 $58.000 $29.290 $50.000
Totals: $11,121,060.10 $10,866,955.64 $11,286,697.69 $11,288,518.16 $12,193,971.64