Show Job Controls
Bid Cobra

MONTGOMERY FM 1314 (1986-01-072)

Items: 13

County: MONTGOMERY
Length: N/A
Highway: FM 1314
District: HOUSTON
Control Number: 1986-01-072
DBE Goal: 0.0%
Project: STP 2B24(357)HES
Guaranty: N/A
Time: 264 WORKING DAYS
Engineer's Estimate: $2,007,352.07
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,007,352.07
1
Rejected
$1,309,535.96
Over/Under Est: -34.76% -$697,816.11
$1,977,658.91
Over/Under Est: -1.48% -$29,693.16
Amt Left: 51.02% $668,122.95
Over/Under Est: 1.06% $21,191.44
Amt Left: 54.91% $719,007.55
Delta: -2.57% -$50,884.60
Over/Under Est: 4.38% $87,880.60
Amt Left: 60% $785,696.71
Delta: -3.29% -$66,689.16
Over/Under Est: 20.98% $421,072.55
Amt Left: 85.44% $1,118,888.66
Delta: -15.90% -$333,191.95

Bid Items & Bid Tabulations

13 Total 0 of 13
MONTGOMERY  |  FM 1314  |  HOUSTON  |  1986-01-072  |  08/02/2024  |  $2,007,352.07  |  STP 2B24(357)HES  |  HAZARD ELIM & SAFETY  |  264 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SICE, INC.
TRAF-TEX, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
THIRD COAST SERVICES LLC
ALLSTATE SIGNAL & CONSTRUCTION, LLC
MOBILIZATION
LS 1.000 $182,486.640 $127,361.799 $45,058.000 $135,973.670 $209,523.260 $23,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $12,861.760 $5,489.980 $1,960.000 $2,029.080 $1,116.880 $1,469.000
CONDT (PVC) (SCH 80) (3")
LF 28,775.000 $20.650 $9.792 $23.820 $18.900 $20.850 $34.560
CONDT (PVC) (SCH 80) (3") (BORE)
LF 12,555.000 $27.750 $16.400 $53.000 $61.000 $49.380 $66.810
CONDT (RM) (3")
LF 455.000 $63.850 $73.442 $80.000 $124.120 $59.230 $58.340
ELEC CONDR (NO.14) INSULATED
LF 41,355.000 $1.150 $0.708 $1.250 $1.170 $0.670 $1.250
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
LF 615.000 $2.450 $11.578 $10.100 $9.350 $12.680 $10.980
FIBER OPTIC CBL (SNGLE-MODE)(36 FIBER)
LF 43,240.000 $3.750 $1.676 $1.360 $1.370 $2.680 $1.730
FO SPLICE ENCLOSURE (TYPE 2)
EA 12.000 $1,790.500 $911.860 $1,497.440 $624.240 $1,097.100 $1,370.000
FIBER OPTIC FUSION SPLICE
EA 144.000 $52.750 $76.989 $32.170 $62.090 $203.480 $84.270
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 12.000 $1,950.000 $938.233 $513.000 $547.740 $1,312.390 $1,550.000
JUNCTION BOX (INSTALL)
EA 4.000 $625.000 $2,197.986 $2,121.000 $1,459.510 $1,851.820 $2,350.000
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 79.000 $4,500.000 $5,206.609 $4,508.000 $4,400.660 $5,085.060 $4,168.960
Totals: $2,007,352.070 $1,309,535.986 $1,977,658.910 $2,028,543.510 $2,095,232.670 $2,428,424.620