MONTGOMERY FM 1314 (1986-01-072)
Items: 13
County: MONTGOMERY
Length: N/A
Highway: FM 1314
District: HOUSTON
Control Number: 1986-01-072
DBE Goal: 0.0%
Project: STP 2B24(357)HES
Guaranty: N/A
Time: 264 WORKING DAYS
Engineer's Estimate: $2,007,352.07
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Informational
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,007,352.07 | |||
| $1,309,535.96 |
-34.76%
-$697,816.11
|
|||
| $1,977,658.91 |
-1.48%
-$29,693.16
|
51.02%
$668,122.95
|
||
| $2,028,543.51 |
1.06%
$21,191.44
|
54.91%
$719,007.55
|
-2.57%
-$50,884.60
|
|
| $2,095,232.67 |
4.38%
$87,880.60
|
60%
$785,696.71
|
-3.29%
-$66,689.16
|
|
| $2,428,424.62 |
20.98%
$421,072.55
|
85.44%
$1,118,888.66
|
-15.90%
-$333,191.95
|
E
Engineer's Estimate
$2,007,352.07
1
Rejected
$1,309,535.96
Over/Under Est:
-34.76%
-$697,816.11
$1,977,658.91
Over/Under Est:
-1.48%
-$29,693.16
Amt Left:
51.02%
$668,122.95
$2,028,543.51
Over/Under Est:
1.06%
$21,191.44
Amt Left:
54.91%
$719,007.55
Delta:
-2.57%
-$50,884.60
$2,095,232.67
Over/Under Est:
4.38%
$87,880.60
Amt Left:
60%
$785,696.71
Delta:
-3.29%
-$66,689.16
$2,428,424.62
Over/Under Est:
20.98%
$421,072.55
Amt Left:
85.44%
$1,118,888.66
Delta:
-15.90%
-$333,191.95
Bid Items & Bid Tabulations
13
Total
0 of 13