Job Info for 1400-04-040

County: MONTGOMERY Highway: FM 1774 Date: 08/03/2022 (2 years ago) Engineer's Estimate: $2,662,997 Control Number: 1400-04-040
Project: STP 2022(697)HES District: HOUSTON Time: 260 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Revision

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,662,997.29
THIRD COAST SERVICES LLC   $1,870,035.50 1
-29.78% | -$792,961.79
ALLSTATE SIGNAL & CONSTRUCTION, LLC   $1,914,622.70 2
-28.1% | -$748,374.59
2.38% | $44,587.20
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.   $2,011,325.39 3
-24.47% | -$651,671.90
7.56% | $141,289.89
5.05% | $96,702.69
VACA UNDERGROUND UTILITIES INC   $2,258,166.75 4
-15.2% | -$404,830.54
20.76% | $388,131.25
12.27% | $246,841.36
SICE, INC.   $2,370,263.01 5
-10.99% | -$292,734.28
26.75% | $500,227.51
4.96% | $112,096.26
FLORIDA TRAFFIC CONTROL DEVICES, INC.   $2,383,616.84 6
-10.49% | -$279,380.45
27.46% | $513,581.34
0.56% | $13,353.83
TRAF-TEX, INC.   $2,452,971.80 7
-7.89% | -$210,025.49
31.17% | $582,936.30
2.91% | $69,354.96

Bid Items

Items: 14, 0 filtered
MONTGOMERY FM 1774  |  HOUSTON  |  1400-04-040  |  08/03/2022  |  $2,662,997  |  STP 2022(697)HES  |  HAZARD ELIM & SAFETY  |  260 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate THIRD COAST SERVICES LLC ALLSTATE SIGNAL & CONSTRUCTION, LLC HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. VACA UNDERGROUND UTILITIES INC SICE, INC. FLORIDA TRAFFIC CONTROL DEVICES, INC. TRAF-TEX, INC.
100 6001 PREPARING ROW AC 2.000 $12,000.000 $800.000 $455.000 $2,190.000 $4,500.000 $13,920.430 $4,309.310 $2,281.000
416 6029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 1,920.000 $248.920 $118.000 $186.300 $191.040 $140.000 $192.490 $186.000 $142.000
432 6009 RIPRAP (CONC) (CL B) (4") CY 67.200 $373.030 $1,050.000 $766.000 $708.500 $600.000 $1,671.780 $927.940 $1,341.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 2.800 $550.000 $245.000 $905.000 $708.500 $900.000 $1,780.390 $985.940 $366.000
500 6001 MOBILIZATION LS 1.000 $242,090.660 $185,000.000 $7,300.000 $165,087.210 $75,000.000 $228,145.330 $134,628.510 $63,614.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $7,603.080 $900.000 $1,100.000 $3,284.590 $3,000.000 $8,137.220 $1,159.920 $1,745.000
610 6288 IN RD IL (TY SA) 50T-10 (400W EQ) LED EA 192.000 $4,536.710 $3,980.000 $3,934.500 $4,372.400 $4,500.000 $5,015.340 $5,013.120 $4,680.000
618 6046 CONDT (PVC) (SCH 80) (2") LF 41,675.000 $10.000 $7.100 $7.840 $5.660 $11.500 $5.310 $10.630 $14.000
618 6047 CONDT (PVC) (SCH 80) (2") (BORE) LF 8,180.000 $27.490 $8.000 $12.620 $12.560 $16.000 $9.540 $17.330 $18.650
620 6007 ELEC CONDR (NO.8) BARE LF 49,855.000 $1.350 $1.100 $1.460 $1.010 $1.750 $0.760 $1.020 $1.600
620 6008 ELEC CONDR (NO.8) INSULATED LF 99,710.000 $1.200 $1.150 $1.560 $1.140 $1.800 $0.950 $1.130 $1.680
624 6010 GROUND BOX TY D (162922)W/APRON EA 11.000 $1,082.430 $985.000 $1,013.000 $1,168.750 $1,300.000 $1,439.350 $1,037.880 $899.000
628 6006 ELC SRV TY A 120/240 060(NS)SS(E)GC(O) EA 7.000 $5,429.450 $6,785.000 $4,627.000 $2,599.000 $7,000.000 $7,729.480 $6,256.690 $9,457.000
6185 6002 TMA (STATIONARY) DAY 172.000 $300.000 $125.000 $141.000 $74.750 $130.000 $377.270 $222.040 $245.000
Totals: $2,662,997.29 $1,870,035.50 $1,914,622.70 $2,011,325.39 $2,258,166.75 $2,370,263.02 $2,383,616.85 $2,452,971.80