Bid Cobra

MONTGOMERY SL 336 (0338-11-056)

Items: 193

County: MONTGOMERY
Length: 2.4800 MILES
Highway: SL 336
District: HOUSTON
Control Number: 0338-11-056
DBE Goal: 8.0%
Project: STP 2025(042)MM
Guaranty: $100,000.00
Time: 481 WORKING DAYS
Engineer's Estimate: $31,110,991.17
Date: 09/06/2024 (1 year ago)
Contract Number: 9243205
Type: WIDEN ROAD - ADD LANES
Project ID: A00121583
Project Description: WIDEN FROM 2-LANE TO 4-LANE DIVIDED ROADWAY
Mail/Deliver Bids To: N/A
ABRAHAM GUZMAN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$31,110,991.17
$20,568,606.42
Over/Under Est: -33.89% -$10,542,384.75
Over/Under Est: -26.5% -$8,244,384.95
Amt Left: 11.17% $2,297,999.80
$22,995,017.40
Over/Under Est: -26.09% -$8,115,973.77
Amt Left: 11.8% $2,426,410.98
Delta: -0.56% -$128,411.18
Over/Under Est: -24.19% -$7,525,942.64
Amt Left: 14.67% $3,016,442.11
Delta: -2.57% -$590,031.13
$24,497,383.59
Over/Under Est: -21.26% -$6,613,607.58
Amt Left: 19.1% $3,928,777.17
Delta: -3.87% -$912,335.06
Over/Under Est: -20.84% -$6,481,976.66
Amt Left: 19.74% $4,060,408.09
Delta: -0.54% -$131,630.92
$25,505,850.96
Over/Under Est: -18.02% -$5,605,140.21
Amt Left: 24% $4,937,244.54
Delta: -3.56% -$876,836.45
Subcontractor Percentage Amount
THIRD COAST SERVICES LLC 7.21% $1,542,549.53
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC 5.39% $1,153,168.10
DURWOOD GREENE CONSTRUCTION CO. 5.39% $1,153,168.10
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 4.00% $855,783.37
M & D FOUNDATION DRILLING INDUSTRIES, INC. 2.55% $545,561.90
PROFESSIONAL TRAFFIC CONTROL LLC 1.47% $314,500.39
WILLOW CITY SIGN & RAIL, INC. 0.88% $188,272.34
BLS SERVICES 0.76% $162,598.84
MESA ROD BUSTERS INC 0.52% $111,251.84
CPAVE, INC. 0.21% $44,928.63
SUPERIOR TRAFFIC CONTROL, LLC 0.16% $34,231.33
MESA ROD BUSTERS INC 0.08% $17,115.67
PRIMATE CONSTRUCTION, LP 0.03% $6,418.38
SCOTT DERR PAINTING CO, LLC 0.01% $2,139.46
Total: 28.66% $6,131,687.88

Bid Items & Bid Tabulations

193 Total 0 of 193
MONTGOMERY  |  SL 336  |  HOUSTON  |  0338-11-056  |  09/06/2024  |  $31,110,991.17  |  STP 2025(042)MM  |  WIDEN ROAD - ADD LANES  |  481 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES CONSTRUCTION GROUP, LLC
GRANITE CONSTRUCTION COMPANY
MC2 CIVIL, LLC
SER CONSTRUCTION PARTNERS, LLC
ISI CONTRACTING, INC.
BRICE CONSTRUCTION AND DESIGN LLC
POSILLICO CIVIL, INC.
PREPARING ROW
STA 137.000 $4,550.000 $14,089.000 $15,000.000 $10,000.000 $15,000.000 $10,540.000 $10,500.000 $6,750.000
REMOV CONC (PAV)
SY 8,290.000 $17.750 $11.670 $15.000 $10.000 $9.900 $16.500 $15.650 $9.000
REMOV CONC (CURB & GUTTER)
LF 2,072.000 $19.750 $14.160 $2.000 $1.000 $15.700 $20.000 $11.460 $3.500
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 4,688.000 $11.000 $6.300 $10.000 $10.000 $12.500 $7.000 $6.450 $4.300
EXCAV (ROADWAY)
CY 70,563.200 $32.000 $7.670 $10.000 $10.000 $13.100 $23.000 $8.560 $9.000
EXCAV (CHANNEL)
CY 10,700.000 $29.000 $21.510 $15.000 $10.000 $17.400 $25.000 $17.640 $16.000
EMBANK (FNL)(DC)(TY C)
CY 38,093.700 $45.000 $6.860 $10.000 $6.000 $22.000 $20.000 $13.200 $9.000
EMBANK (FNL)(DC)(TY E)(CSBE)
CY 3,921.000 $80.000 $58.140 $55.000 $65.000 $67.100 $25.000 $91.450 $95.000
BLOCK SODDING
SY 144,710.000 $6.200 $3.650 $4.000 $4.500 $5.100 $2.500 $4.250 $4.250
STRAW OR HAY MULCH
SY 144,710.000 $1.500 $0.290 $0.290 $0.350 $0.300 $0.200 $0.200 $0.200
BROADCAST SEED (TEMP_WARM)
SY 36,177.500 $1.800 $0.160 $0.160 $0.200 $0.200 $0.150 $0.200 $0.200
DRILL SEED (TEMP_WARM_COOL)
SY 108,533.000 $0.560 $0.130 $0.130 $0.150 $0.200 $0.090 $0.250 $0.250
FERTILIZER
AC 28.950 $1,890.000 $789.500 $800.000 $900.000 $1,050.000 $547.000 $650.000 $650.000
VEGETATIVE WATERING
TGL 3.720 $46.000 $250.000 $50.000 $200.000 $163.300 $137.000 $46.800 $75.000
WILDFLOWER SEEDING (MIX 1)
AC 6.820 $3,306.000 $2,436.920 $2,600.000 $3,000.000 $7,875.000 $1,688.000 $2,800.000 $2,800.000
LIME (COM OR QK)(SLURRY)
TON 774.000 $375.000 $352.110 $500.000 $340.000 $250.000 $150.000 $383.500 $500.000
LIME TRT (EXIST MATL)(6")
SY 56,458.000 $5.300 $4.870 $12.000 $4.000 $3.100 $3.000 $4.510 $4.500
CEMENT TRT (NEW BASE)(6")
SY 53,491.000 $24.000 $0.150 $20.000 $21.000 $3.000 $6.700 $25.770 $30.000
ASPHALT TRT BASE (GR 4)(PG 70)
TON 2,950.000 $125.000 $129.000 $155.000 $150.000 $133.100 $192.000 $147.000 $132.000
CONC PVMT (CRCP) (11")
SY 46,139.000 $120.000 $81.510 $90.650 $100.000 $85.200 $112.000 $92.350 $115.000
CEM STABIL BKFL
CY 4,352.000 $75.000 $56.060 $60.000 $65.000 $59.400 $60.000 $69.800 $65.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 466.250 $54.000 $56.060 $60.000 $65.000 $59.500 $100.000 $69.130 $65.000
TRENCH EXCAVATION PROTECTION
LF 4,566.000 $4.000 $1.090 $1.000 $1.000 $0.100 $25.000 $1.920 $6.000
DRILL SHAFT (18 IN)
LF 380.000 $182.000 $65.390 $90.000 $110.000 $94.100 $162.000 $69.480 $80.000
DRILL SHAFT (24 IN)
LF 230.000 $255.000 $113.510 $200.000 $200.000 $125.600 $211.000 $132.560 $138.000
DRILL SHAFT (30 IN)
LF 100.000 $295.000 $178.550 $300.000 $330.000 $194.400 $298.000 $216.730 $200.000
DRILL SHAFT (36 IN)
LF 650.000 $345.000 $250.930 $325.000 $370.000 $283.700 $310.000 $272.230 $275.000
DRILL SHAFT (42 IN)
LF 108.000 $455.000 $335.960 $550.000 $500.000 $381.600 $445.000 $342.990 $380.000
DRILL SHAFT (48 IN)
LF 820.000 $590.000 $450.010 $425.000 $650.000 $488.200 $493.000 $454.160 $490.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 260.000 $455.000 $277.270 $300.000 $310.000 $264.600 $195.000 $300.000 $720.000
CL C CONC (ABUT)
CY 84.200 $1,510.000 $1,235.990 $1,000.000 $1,700.000 $1,138.700 $1,674.000 $1,325.950 $1,400.000
CL C CONC (CAP)
CY 68.300 $1,645.000 $1,402.320 $900.000 $2,400.000 $1,418.100 $2,164.000 $1,645.890 $2,000.000
CL C CONC (COLUMN)
CY 26.200 $2,020.000 $1,843.950 $2,000.000 $1,500.000 $1,087.800 $4,292.000 $1,706.740 $2,000.000
REINF CONC SLAB
SF 17,094.000 $29.000 $20.860 $22.000 $24.500 $23.800 $21.000 $26.580 $28.000
REINF CONC SLAB (SLAB BEAM)
SF 2,568.000 $28.000 $26.080 $40.000 $24.000 $26.600 $35.000 $32.840 $30.000
PRESTR CONC GIRDER (TX40)
LF 2,652.000 $220.000 $189.000 $255.000 $200.000 $193.500 $221.000 $225.740 $250.000
PRESTR CONC SLAB BEAM (4SB15)
LF 386.840 $255.000 $198.960 $350.000 $200.000 $246.300 $230.000 $279.390 $250.000
PRESTR CONC SLAB BEAM (5SB15)
LF 193.420 $270.000 $217.710 $350.000 $200.000 $274.900 $300.000 $356.550 $250.000
RIPRAP (CONC)(4 IN)
CY 24.000 $465.000 $630.220 $1,000.000 $850.000 $561.500 $253.000 $1,226.270 $400.000
RIPRAP (CONC)(CL B)(5 IN)
CY 40.000 $660.000 $533.800 $1,000.000 $650.000 $487.600 $409.000 $597.080 $600.000
RIPRAP (MOW STRIP)(4 IN)
CY 37.000 $735.000 $641.970 $1,000.000 $750.000 $583.800 $430.000 $767.310 $550.000
RIPRAP (STONE TY R)(DRY)(12 IN)
CY 2,395.000 $220.000 $195.000 $1.000 $175.000 $194.000 $194.000 $238.210 $220.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 144.000 $308.000 $350.000 $300.000 $175.000 $194.600 $233.000 $223.290 $296.870
STR STEEL (MISC NON-BRIDGE)
LB 616.000 $22.000 $18.680 $25.000 $20.000 $15.800 $24.800 $20.760 $27.800
RAIL (TY T223)
LF 806.000 $235.000 $62.410 $1.000 $1.000 $108.500 $237.000 $105.400 $320.000
RAIL (TY C1W)
LF 438.000 $383.000 $226.630 $300.000 $250.000 $230.700 $192.000 $351.510 $300.000
RAIL (TY C223)
LF 455.000 $194.000 $111.800 $200.000 $170.000 $156.400 $404.000 $195.860 $375.000
RAIL (TY PR11)
LF 536.000 $200.000 $96.610 $80.000 $110.000 $113.300 $95.000 $115.460 $105.000
RAIL (HANDRAIL)(TY A)
LF 157.000 $271.000 $101.140 $70.000 $110.000 $113.800 $79.000 $106.650 $95.000
RETROFIT RAIL (TY SSTR)
LF 712.000 $312.000 $0.070 $1.000 $1.000 $66.900 $250.000 $201.870 $80.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 67.000 $236.000 $287.360 $300.000 $255.000 $220.800 $274.000 $334.880 $300.000
CONC BOX CULV (4 FT X 3 FT)
LF 211.000 $330.000 $331.740 $500.000 $400.000 $401.500 $450.000 $360.940 $467.250
CONC BOX CULV (9 FT X 6 FT)(EXTEND)
LF 12.000 $2,655.000 $2,051.820 $3,500.000 $2,400.000 $2,464.300 $6,000.000 $5,597.840 $2,500.000
RC PIPE (CL III)(18 IN)
LF 107.000 $100.000 $85.920 $100.000 $120.000 $107.000 $200.000 $96.450 $105.000
RC PIPE (CL III)(24 IN)
LF 3,477.000 $101.000 $180.000 $125.000 $125.000 $121.600 $88.000 $92.270 $110.000
RC PIPE (CL III)(30 IN)
LF 2,262.000 $171.000 $116.290 $140.000 $140.000 $148.300 $146.000 $112.650 $125.000
RC PIPE (CL III)(36 IN)
LF 1,398.000 $135.000 $134.420 $150.000 $160.000 $184.600 $170.000 $149.790 $150.000
RC PIPE (CL III)(42 IN)
LF 211.000 $293.000 $187.690 $200.000 $270.000 $263.500 $400.000 $205.410 $200.000
RC PIPE (CL III)(48 IN)
LF 31.000 $348.000 $258.480 $300.000 $350.000 $274.000 $500.000 $275.240 $310.000
JCTBOX(COMPL)(PJB)(4FTX4FT)
EA 10.000 $9,606.000 $6,087.030 $10,000.000 $5,500.000 $4,348.100 $5,978.000 $5,765.180 $7,300.000
INLET (COMPL)(CURB)(TY C)(NONE)(HOU)
EA 2.000 $6,890.000 $4,562.810 $6,000.000 $5,500.000 $4,198.700 $5,823.000 $6,017.680 $8,600.000
INLET (COMPL)(CURB)(TY C)(LEFT)(HOU)
EA 18.000 $8,140.000 $5,931.920 $7,200.000 $6,500.000 $5,401.300 $6,936.000 $7,053.830 $10,000.000
INLET (COMPL)(CURB)(TY C)(RIGHT)(HOU)
EA 14.000 $8,140.000 $5,673.170 $6,800.000 $6,500.000 $5,169.900 $5,616.000 $7,043.390 $10,200.000
INLET (COMPL)(CURB)(TY C)(BOTH)(HOU)
EA 3.000 $9,390.000 $7,560.890 $7,700.000 $8,000.000 $6,268.500 $6,618.000 $8,041.080 $10,500.000
INLET (COMPL)(CURB)(TY C1)(LEFT)(HOU)
EA 1.000 $8,750.000 $7,028.610 $6,500.000 $8,000.000 $6,026.800 $7,537.000 $6,510.910 $8,500.000
INLET (COMPL)(CURB)(TY C1)(RIGHT)(HOU)
EA 3.000 $8,750.000 $6,714.530 $7,300.000 $8,000.000 $6,259.200 $7,784.000 $6,964.150 $10,000.000
INLET (COMPL)(CURB)(TY C1)(BOTH)(HOU)
EA 4.000 $10,000.000 $7,043.460 $8,000.000 $8,000.000 $6,799.600 $7,125.000 $8,237.260 $10,500.000
INLET (COMPL)(TY AD)(HOU)
EA 17.000 $7,265.000 $5,430.510 $6,000.000 $5,000.000 $1,822.900 $6,407.000 $6,382.000 $8,000.000
INLET (COMPL)(TY AAD)(HOU)
EA 3.000 $11,900.000 $5,867.220 $7,700.000 $6,000.000 $6,802.900 $8,534.000 $8,192.420 $10,500.000
MANH (COMPL)(TY A)(HOU)
EA 7.000 $9,762.000 $4,869.520 $10,000.000 $5,000.000 $5,062.200 $5,284.000 $8,343.750 $9,500.000
INLET (COMPL)(ARMOR CURB SLOT)
EA 2.000 $5,270.000 $5,075.870 $8,000.000 $3,200.000 $4,583.000 $8,101.000 $7,383.600 $11,000.000
HEADWALL (CH - FW - 45) (DIA= 42 IN)
EA 3.000 $11,000.000 $20,992.520 $15,000.000 $18,000.000 $12,846.700 $31,066.000 $17,241.030 $25,000.000
HEADWALL (CH - PW - S) (DIA= 42 IN)
EA 1.000 $11,000.000 $21,887.780 $25,000.000 $25,000.000 $33,401.700 $33,915.000 $20,413.040 $33,000.000
HEADWALL (CH - PW - S) (DIA= 48 IN)
EA 2.000 $16,655.000 $22,830.130 $26,000.000 $28,000.000 $37,727.200 $34,661.000 $35,462.860 $36,000.000
WINGWALL (FW - S) (HW=4 FT)
EA 2.000 $11,360.000 $11,296.520 $15,000.000 $20,000.000 $19,216.200 $31,066.000 $16,049.510 $19,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $1,945.000 $17,157.870 $20,000.000 $22,000.000 $24,733.700 $44,208.000 $22,818.870 $33,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $38,355.000 $28,442.660 $30,000.000 $25,000.000 $42,476.100 $44,208.000 $35,058.530 $50,000.000
WINGWALL (PW-1)(HW=9 FT)(MOD)
EA 1.000 $25,000.000 $40,167.110 $65,000.000 $75,000.000 $85,757.500 $44,208.000 $60,655.860 $75,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 16.000 $1,962.000 $1,600.400 $2,000.000 $1,600.000 $1,556.600 $2,460.000 $2,158.580 $2,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 8.000 $2,198.000 $2,119.380 $25,000.000 $1,800.000 $2,179.500 $2,999.000 $2,485.920 $2,500.000
REMOV STR (INLET)
EA 6.000 $960.000 $985.770 $750.000 $500.000 $428.100 $670.000 $973.450 $500.000
REMOV STR (MANHOLE)
EA 7.000 $875.000 $765.160 $750.000 $500.000 $428.100 $1,005.000 $960.810 $500.000
REMOV STR (SET)
EA 6.000 $830.000 $492.890 $500.000 $400.000 $124.100 $1,005.000 $943.530 $500.000
REMOV STR (PIPE)
LF 313.000 $57.000 $23.760 $40.000 $20.000 $13.600 $32.120 $42.050 $16.000
MOBILIZATION
LS 1.000 $3,283,497.000 $2,050,000.000 $2,200,000.000 $2,240,000.000 $2,300,000.000 $2,400,000.000 $2,400,000.000 $2,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 23.000 $13,000.000 $10,005.050 $8,000.000 $15,000.000 $11,461.000 $9,347.000 $7,389.490 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 10.000 $13,400.000 $2.160 $7,500.000 $15,000.000 $12,568.500 $2,231.000 $18,862.350 $12,000.000
TMA (STATIONARY)
DAY 5.000 $600.000 $302.300 $425.000 $300.000 $551.600 $1,473.000 $395.130 $250.000
TMA (MOBILE OPERATION)
DAY 55.000 $260.000 $649.870 $1,200.000 $650.000 $933.800 $968.000 $692.790 $380.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,612.000 $62.000 $43.800 $50.000 $45.000 $94.500 $30.350 $40.000 $40.020
ROCK FILTER DAMS (REMOVE)
LF 1,612.000 $15.000 $14.720 $18.000 $15.000 $14.000 $10.200 $20.000 $20.010
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 770.000 $37.000 $31.000 $45.000 $33.000 $27.000 $21.480 $35.000 $35.020
CONSTRUCTION EXITS (REMOVE)
SY 770.000 $8.850 $12.170 $10.000 $13.000 $4.900 $8.430 $20.000 $20.010
TEMP SEDMT CONT FENCE (INSTALL)
LF 17,290.000 $4.000 $3.310 $5.000 $3.500 $3.300 $2.290 $3.500 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 17,290.000 $1.450 $1.060 $1.000 $1.000 $1.100 $0.730 $1.500 $1.500
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,410.000 $6.400 $6.830 $10.000 $8.000 $6.200 $4.730 $7.500 $7.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,410.000 $1.750 $1.760 $1.500 $2.000 $3.600 $1.220 $2.000 $2.000
CONSTRUCTING DETOURS
SY 5,994.000 $124.000 $147.480 $1.000 $1.000 $156.100 $166.000 $158.200 $137.500
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,140.000 $45.000 $13.000 $50.000 $80.000 $30.000 $9.350 $63.350 $17.350
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 3,100.000 $48.000 $12.790 $70.000 $75.000 $30.000 $8.580 $52.420 $20.330
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 360.000 $56.000 $15.590 $65.000 $75.000 $30.000 $8.580 $54.990 $21.120
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 2,090.000 $8.000 $15.210 $3.000 $9.000 $12.500 $11.560 $11.200 $7.890
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 2,260.000 $10.000 $15.670 $3.000 $9.000 $11.600 $11.390 $9.760 $7.300
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 320.000 $9.750 $14.380 $3.000 $9.000 $12.400 $15.140 $14.140 $7.730
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,520.000 $11.750 $12.350 $10.000 $15.000 $13.400 $7.080 $10.850 $12.150
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 3,100.000 $13.000 $12.110 $8.000 $15.000 $11.700 $8.780 $8.760 $10.700
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 360.000 $18.000 $14.750 $8.000 $15.000 $13.000 $8.740 $16.050 $10.700
PORT CTB (FURN & INST)(TL-3 LPCB)
LF 840.000 $106.000 $111.270 $70.000 $150.000 $107.700 $149.590 $124.530 $123.310
PORT CTB (REMOVE) (TL-3 LPCB)
LF 840.000 $28.000 $13.490 $7.000 $15.000 $10.000 $3.000 $11.010 $12.140
CONC CURB (MONO) (TY II)
LF 27,463.000 $9.800 $4.060 $4.000 $5.000 $3.500 $16.300 $3.640 $8.220
CONC CURB (SLOTTED)
LF 51.000 $31.000 $3.520 $10.000 $30.000 $20.600 $122.000 $3.640 $12.690
CONC SIDEWALKS (6")
SY 14,794.000 $113.000 $53.120 $50.000 $63.000 $60.000 $53.000 $81.470 $80.000
CURB RAMPS (TY 1)
EA 33.000 $2,440.000 $2,186.000 $2,000.000 $2,500.000 $3,010.700 $1,594.000 $3,022.900 $2,231.500
CURB RAMPS (TY 7)
EA 4.000 $3,178.000 $2,193.450 $1,500.000 $2,500.000 $3,115.900 $1,490.000 $3,022.900 $2,133.010
CURB RAMPS (TY 20)
EA 4.000 $2,600.000 $2,622.030 $2,000.000 $4,000.000 $3,388.400 $2,148.000 $3,022.900 $2,632.760
CURB RAMPS (TY 22)
EA 4.000 $3,790.000 $2,707.420 $2,500.000 $7,000.000 $5,670.100 $2,979.000 $3,022.900 $2,633.140
MTL W-BEAM GD FEN (TIM POST)
LF 325.000 $31.000 $25.500 $27.220 $30.000 $23.400 $28.100 $25.500 $25.200
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,240.000 $2,150.000 $2,295.400 $2,400.000 $1,868.000 $3,405.000 $2,150.000 $2,088.260
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,580.000 $1,575.000 $1,681.520 $1,600.000 $1,545.600 $2,001.000 $1,575.000 $1,188.780
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,610.000 $3,150.000 $3,363.030 $3,500.000 $3,332.700 $3,492.000 $3,150.000 $2,924.610
CRASH CUSH ATTEN (MOVE & RESET)
EA 19.000 $3,011.000 $1,250.000 $1,292.510 $1,500.000 $3,255.000 $1,372.000 $1,250.000 $1,462.300
CRASH CUSH ATTEN (STKPL)
EA 18.000 $1,124.000 $900.000 $930.610 $1,000.000 $2,205.000 $548.000 $900.000 $704.850
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,100.000 $900.000 $930.610 $1,000.000 $1,890.000 $548.000 $900.000 $704.850
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $9,120.000 $8,500.000 $8,812.270 $9,000.000 $10,657.500 $7,687.000 $8,500.000 $7,995.330
CONDT (PVC) (SCH 80) (2")
LF 11,800.000 $20.000 $14.490 $14.640 $15.000 $8.600 $10.190 $12.750 $16.840
CONDT (PVC) (SCH 80) (2") (BORE)
LF 2,180.000 $34.000 $16.150 $16.310 $17.000 $13.600 $11.360 $13.750 $27.370
CONDT (PVC) (SCH 80) (3")
LF 1,405.000 $30.000 $18.090 $18.270 $19.000 $14.400 $12.720 $17.250 $23.160
CONDT (PVC) (SCH 80) (3") (BORE)
LF 1,660.000 $40.000 $23.420 $23.660 $24.000 $14.700 $16.470 $18.250 $30.530
CONDT (RM) (2")
LF 650.000 $42.000 $47.540 $48.020 $50.000 $29.900 $33.440 $53.750 $37.370
ELEC CONDR (NO.6) BARE
LF 3,060.000 $2.500 $1.670 $1.690 $2.000 $1.300 $1.170 $2.150 $2.110
ELEC CONDR (NO.4) BARE
LF 945.000 $3.000 $2.710 $2.740 $3.000 $2.400 $1.910 $2.800 $3.160
ELEC CONDR (NO.4) INSULATED
LF 1,880.000 $3.250 $2.900 $2.930 $3.200 $2.500 $2.040 $2.950 $3.680
TRAY CABLE (4 CONDR) (12 AWG)
LF 10,480.000 $3.150 $3.200 $3.230 $3.500 $2.000 $2.250 $3.250 $3.680
GROUND BOX TY D (162922)W/APRON
EA 38.000 $1,765.000 $1,114.330 $1,125.590 $1,200.000 $1,141.900 $784.000 $1,245.000 $1,684.380
GROUND BOX TY 2 (243636)W/APRON
EA 21.000 $5,000.000 $3,622.100 $3,658.690 $4,000.000 $5,851.000 $2,548.000 $4,750.000 $5,053.130
ELC SRV TY D 120/240 060(NS)SS(E)SP(U)
EA 3.000 $11,000.000 $7,070.520 $7,141.940 $7,500.000 $12,224.300 $4,973.000 $8,950.000 $9,074.580
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 34.000 $558.000 $445.000 $468.910 $500.000 $486.200 $335.000 $445.000 $599.650
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 16.000 $650.000 $635.000 $669.130 $700.000 $651.000 $406.000 $635.000 $852.130
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $715.000 $650.000 $684.930 $700.000 $671.000 $500.000 $650.000 $915.260
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 2.000 $1,275.000 $1,150.000 $1,211.800 $1,200.000 $1,076.300 $929.000 $1,150.000 $1,336.060
REMOVE SM RD SN SUP&AM
EA 34.000 $133.000 $95.000 $100.110 $100.000 $78.800 $28.460 $95.000 $78.900
WK ZN PAV MRK REMOV (W)6"(DOT)
LF 1,432.000 $2.300 $1.500 $1.520 $1.600 $3.600 $1.570 $1.300 $1.300
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 41,478.000 $1.350 $1.100 $1.110 $1.200 $1.200 $1.150 $1.300 $1.300
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 5,590.000 $1.810 $1.600 $1.620 $1.700 $3.800 $1.680 $1.700 $1.700
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 896.000 $11.550 $11.000 $11.110 $11.500 $8.700 $11.530 $5.100 $5.100
WK ZN PAV MRK REMOV (W)6"(BKN W/MRKR)
LF 4,074.000 $0.700 $1.850 $1.870 $2.000 $2.400 $1.940 $1.900 $1.900
WK ZN PAV MRK REMOV (W)(ARROW)
EA 116.000 $220.500 $225.000 $227.270 $250.000 $335.000 $236.000 $180.000 $180.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 46.000 $291.000 $280.000 $282.830 $300.000 $496.700 $293.000 $300.000 $300.000
WK ZN PAV MRK REMOV (W)36"(YLD TRI)
EA 6.000 $65.000 $70.000 $70.710 $75.000 $122.900 $73.000 $54.000 $54.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 47,040.000 $0.880 $1.100 $1.110 $1.200 $1.200 $1.150 $1.300 $1.300
RE PM TY III (W)(6")(SLD)
LF 8,398.000 $0.950 $1.030 $1.040 $1.100 $0.900 $1.080 $0.970 $0.970
RE PM TY III (W)(6")(BRK)
LF 6,784.000 $1.000 $1.050 $1.060 $1.100 $1.200 $1.100 $0.970 $0.970
RE PM TY III (W)(8")(SLD)
LF 8,192.000 $1.600 $1.650 $1.670 $1.750 $3.400 $1.730 $1.300 $1.300
RE PM TY III (W)(24")(SLD)
LF 2,412.000 $8.800 $10.000 $10.100 $11.000 $11.600 $10.480 $3.900 $3.900
RE PM TY III (Y)(6")(SLD)
LF 26,733.000 $1.100 $1.030 $1.040 $1.100 $0.900 $1.080 $0.970 $0.970
RE PM TY III (W)(ARROW)
EA 37.000 $300.000 $220.000 $222.220 $250.000 $204.800 $231.000 $155.000 $155.000
RE PM TY III (W)(WORD)
EA 34.000 $332.000 $310.000 $313.130 $350.000 $244.700 $325.000 $170.000 $170.000
RE PM TY III (W)(36" YLD TRI)
EA 63.000 $91.000 $70.000 $70.710 $75.000 $68.300 $73.000 $70.000 $70.000
RE PM TY III (BLK)(6")(SHADOW)
LF 6,996.000 $1.300 $1.100 $1.110 $1.200 $1.200 $1.150 $0.900 $0.900
REFL PAV MRKR TY I-C
EA 724.000 $8.150 $6.000 $6.060 $6.500 $8.200 $6.290 $6.000 $6.000
REFL PAV MRKR TY II-A-A
EA 31.000 $6.950 $6.000 $6.060 $6.500 $8.200 $6.290 $6.000 $6.000
ELIM EXT PM & MRKS (4")
LF 58,399.000 $0.800 $0.400 $0.400 $0.400 $1.100 $0.420 $1.000 $1.000
ELIM EXT PM & MRKS (8")
LF 2,103.000 $0.950 $0.800 $0.810 $0.800 $2.100 $0.840 $2.000 $2.000
ELIM EXT PM & MRKS (24")
LF 2,548.000 $2.300 $3.000 $3.030 $3.000 $2.600 $3.140 $6.000 $6.000
INSTALL HWY TRF SIG (SYSTEM)
EA 3.000 $32,850.000 $23,933.530 $24,175.280 $26,000.000 $34,395.900 $16,834.000 $32,515.000 $30,592.490
REMOVING TRAFFIC SIGNALS
EA 3.000 $8,760.000 $2,133.800 $2,155.350 $2,500.000 $10,909.100 $1,501.000 $5,175.000 $4,274.100
TEMP TRAF SIGNALS
EA 3.000 $75,005.000 $15,363.390 $15,518.580 $20,000.000 $71,210.300 $10,806.000 $35,500.000 $73,480.920
VEH SIG SEC (12")LED(GRN)
EA 38.000 $365.000 $209.670 $211.790 $250.000 $294.000 $147.000 $300.000 $315.820
VEH SIG SEC (12")LED(GRN ARW)
EA 13.000 $3,669.000 $209.710 $211.830 $250.000 $311.100 $147.000 $300.000 $315.820
VEH SIG SEC (12")LED(YEL)
EA 38.000 $380.000 $209.670 $211.790 $250.000 $298.300 $147.000 $300.000 $315.820
VEH SIG SEC (12")LED(YEL ARW)
EA 6.000 $370.000 $209.670 $211.790 $250.000 $298.300 $147.000 $300.000 $315.820
VEH SIG SEC (12")LED(RED)
EA 38.000 $375.000 $209.670 $211.790 $250.000 $294.000 $147.000 $300.000 $315.820
VEH SIG SEC (12")LED(RED ARW)
EA 12.000 $370.000 $209.670 $211.790 $250.000 $298.300 $147.000 $300.000 $315.820
PED SIG SEC (LED)(COUNTDOWN)
EA 40.000 $395.000 $591.580 $597.560 $700.000 $899.600 $416.000 $715.000 $694.810
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 31.000 $225.000 $140.150 $141.570 $150.000 $186.200 $99.000 $225.000 $294.770
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
EA 13.000 $255.000 $179.210 $181.020 $200.000 $262.800 $126.000 $250.000 $278.970
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 9,295.000 $2.050 $1.700 $1.720 $2.000 $1.500 $1.200 $2.000 $1.840
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 10,510.000 $2.600 $2.190 $2.210 $2.500 $2.100 $1.540 $2.250 $2.630
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 9,755.000 $3.600 $2.840 $2.870 $3.000 $3.400 $2.000 $3.000 $3.420
INS TRF SIG PL AM(S)1 ARM(32')LUM&ILSN
EA 4.000 $14,255.000 $14,571.070 $14,718.250 $16,000.000 $17,449.700 $10,249.000 $14,250.000 $16,685.850
INS TRF SIG PL AM(S)1 ARM(36')LUM&ILSN
EA 1.000 $23,735.000 $14,876.040 $15,026.300 $17,000.000 $18,771.500 $10,463.000 $14,500.000 $17,001.670
INS TRF SIG PL AM(S)1 ARM(40')LUM&ILSN
EA 10.000 $15,700.000 $15,962.720 $16,123.960 $18,000.000 $19,426.100 $11,227.000 $15,375.000 $18,275.480
INS TRF SIG PL AM(S)1 ARM(44')LUM&ILSN
EA 3.000 $19,035.000 $16,316.520 $16,481.330 $20,000.000 $20,143.200 $11,476.000 $15,725.000 $18,717.630
PED POLE ASSEMBLY
EA 29.000 $3,275.000 $2,241.450 $2,264.090 $2,500.000 $3,236.900 $1,577.000 $2,075.000 $3,500.340
PED DETECT PUSH BUTTON (APS)
EA 36.000 $1,245.000 $869.070 $877.850 $1,000.000 $1,396.400 $611.000 $725.000 $936.930
PED DETECTOR CONTROLLER UNIT
EA 3.000 $3,905.000 $3,232.770 $3,265.420 $3,500.000 $2,704.100 $2,274.000 $3,750.000 $3,737.210
IRRIG SYS OPERATION AND REPAIR
MO 0.250 $2,115.000 $50,000.000 $20,000.000 $20,000.000 $42,000.000 $3,824.000 $35,000.000 $4,800.000
ILSN (6 D)
EA 16.000 $3,885.000 $2,784.470 $2,812.600 $3,000.000 $4,379.000 $1,958.000 $3,575.000 $3,621.410
ILSN (8D)
EA 2.000 $3,825.000 $2,784.460 $2,812.590 $3,000.000 $5,247.200 $1,958.000 $4,075.000 $4,305.690
BBU SYSTEM (EXTERNAL BATTERY CABINET)
EA 3.000 $10,045.000 $7,914.450 $7,994.390 $9,000.000 $9,472.600 $5,567.000 $8,275.000 $8,716.650
RVDS (PRESENCE DETECTION ONLY)
EA 18.000 $9,725.000 $9,387.540 $9,482.360 $11,000.000 $10,651.600 $6,603.000 $8,975.000 $10,106.260
RVDS (ADVANCE DETENTION ONLY)
EA 6.000 $9,815.000 $10,528.240 $10,634.590 $12,000.000 $12,262.600 $7,405.000 $10,075.000 $11,306.380
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 13,845.000 $6.550 $2.770 $6.000 $3.000 $1.900 $1.950 $4.550 $2.110
Totals: $31,110,991.170 $20,568,606.469 $22,866,606.220 $22,995,017.400 $23,585,048.551 $24,497,383.595 $24,629,014.544 $25,505,850.960