Job Info for 0044-06-077

County: MONTAGUE Highway: US 82 Date: 07/09/2024 (4 months ago) Engineer's Estimate: $4,060,608 Control Number: 0044-06-077
Project: STP 2B24(222)HES District: WICHITA FALLS Time: 238 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,060,608.04
SCOUT 5 CONSTRUCTION LLC   $3,283,667.31 1
-19.13% | -$776,940.73
MASSANA CONSTRUCTION INC.   $3,466,168.00 2
-14.64% | -$594,440.04
5.56% | $182,500.69
HJC FARMS, INC.   $3,590,894.16 3
-11.57% | -$469,713.88
9.36% | $307,226.85
3.60% | $124,726.16
SCR CIVIL CONSTRUCTION, LLC   $3,722,228.10 4
-8.33% | -$338,379.94
13.36% | $438,560.79
3.66% | $131,333.94
GRATIOT CONSTRUCTION, LTD.   $3,997,642.58 5
-1.55% | -$62,965.46
21.74% | $713,975.27
7.40% | $275,414.48
ROADWAY SPECIALTIES, INC.   $4,018,948.77 6
-1.03% | -$41,659.27
22.39% | $735,281.46
0.53% | $21,306.19
FNH CONSTRUCTION, LLC   $4,982,334.00 7
22.7% | $921,725.96
51.73% | $1,698,666.69
23.97% | $963,385.23

Bid Items

Items: 14, 0 filtered
MONTAGUE US 82  |  WICHITA FALLS  |  0044-06-077  |  07/09/2024  |  $4,060,608  |  STP 2B24(222)HES  |  HAZARD ELIM & SAFETY  |  238 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SCOUT 5 CONSTRUCTION LLC MASSANA CONSTRUCTION INC. HJC FARMS, INC. SCR CIVIL CONSTRUCTION, LLC GRATIOT CONSTRUCTION, LTD. ROADWAY SPECIALTIES, INC. FNH CONSTRUCTION, LLC
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 1,544.000 $30.000 $120.000 $50.000 $25.000 $31.000 $85.230 $52.400 $50.000
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 165,318.000 $0.170 $0.010 $0.050 $0.170 $0.190 $0.350 $0.470 $1.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 82,659.000 $0.110 $0.010 $0.050 $0.100 $0.100 $0.340 $0.470 $1.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 82,659.000 $0.110 $0.010 $0.050 $0.100 $0.100 $0.340 $0.490 $1.000
168 6001 VEGETATIVE WATERING MG 1,429.000 $35.000 $0.010 $42.000 $25.000 $55.000 $126.410 $126.230 $25.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 3,482.000 $450.000 $640.000 $375.000 $450.000 $551.000 $430.410 $465.400 $550.000
500 6001 MOBILIZATION LS 1.000 $363,419.000 $0.010 $385,514.200 $257,500.000 $144,000.000 $302,272.730 $474,191.200 $500,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 14.000 $4,500.000 $0.010 $7,000.000 $975.000 $3,700.000 $1,250.000 $1,334.320 $8,500.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 3,040.000 $5.000 $2.000 $3.000 $5.750 $4.600 $17.400 $3.640 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 3,040.000 $1.500 $0.010 $1.000 $1.000 $1.150 $3.100 $1.000 $9.000
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 88,682.000 $15.000 $7.000 $12.000 $10.650 $11.340 $13.430 $12.380 $11.500
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 156.000 $3,200.000 $1,375.000 $2,500.000 $4,000.000 $1,950.000 $3,068.180 $2,100.000 $5,000.000
644 6071 RELOCATE SM RD SN SUP&AM TY TWT EA 56.000 $500.000 $450.000 $600.000 $425.000 $610.000 $369.320 $567.860 $1,250.000
6185 6002 TMA (STATIONARY) DAY 211.000 $225.000 $0.010 $110.000 $100.000 $341.000 $1.140 $75.000 $250.000
Totals: $4,060,608.04 $3,283,667.31 $3,466,168.00 $3,590,894.16 $3,722,228.10 $3,997,642.58 $4,018,948.77 $4,982,334.00