MILAM FM 908 (2087-01-021)
Items: 53
County: MILAM
Length: N/A
Highway: FM 908
District: BRYAN
Control Number: 2087-01-021
DBE Goal: N/A
Project: BR 2021(027)
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $1,280,586.60
Date: 10/01/2020 (5 years ago)
Contract Number: N/A
Type: BR - BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,280,586.60 | |||
| $1,185,695.65 |
-7.41%
-$94,890.95
|
|||
| $1,277,890.38 |
-0.21%
-$2,696.22
|
7.78%
$92,194.73
|
||
| $1,315,539.45 |
2.73%
$34,952.85
|
10.95%
$129,843.80
|
-2.95%
-$37,649.07
|
|
| $1,428,086.00 |
11.52%
$147,499.40
|
20.44%
$242,390.35
|
-8.56%
-$112,546.55
|
|
| $1,462,202.17 |
14.18%
$181,615.57
|
23.32%
$276,506.52
|
-2.39%
-$34,116.17
|
|
| $1,513,564.69 |
18.19%
$232,978.09
|
27.65%
$327,869.04
|
-3.51%
-$51,362.52
|
|
| $1,747,890.02 |
36.49%
$467,303.42
|
47.41%
$562,194.37
|
-15.48%
-$234,325.33
|
|
| $1,990,548.71 |
55.44%
$709,962.11
|
67.88%
$804,853.06
|
-13.88%
-$242,658.69
|
E
Engineer's Estimate
$1,280,586.60
1
Awarded
$1,185,695.65
Over/Under Est:
-7.41%
-$94,890.95
$1,277,890.38
Over/Under Est:
-0.21%
-$2,696.22
Amt Left:
7.78%
$92,194.73
$1,315,539.45
Over/Under Est:
2.73%
$34,952.85
Amt Left:
10.95%
$129,843.80
Delta:
-2.95%
-$37,649.07
$1,428,086.00
Over/Under Est:
11.52%
$147,499.40
Amt Left:
20.44%
$242,390.35
Delta:
-8.56%
-$112,546.55
$1,462,202.17
Over/Under Est:
14.18%
$181,615.57
Amt Left:
23.32%
$276,506.52
Delta:
-2.39%
-$34,116.17
$1,513,564.69
Over/Under Est:
18.19%
$232,978.09
Amt Left:
27.65%
$327,869.04
Delta:
-3.51%
-$51,362.52
$1,747,890.02
Over/Under Est:
36.49%
$467,303.42
Amt Left:
47.41%
$562,194.37
Delta:
-15.48%
-$234,325.33
$1,990,548.71
Over/Under Est:
55.44%
$709,962.11
Amt Left:
67.88%
$804,853.06
Delta:
-13.88%
-$242,658.69
Bid Items & Bid Tabulations
53
Total
0 of 53