Job Info for 0917-12-080

County: MILAM Highway: CR Date: 06/06/2017 (7 years ago) Engineer's Estimate: $540,787 Control Number: 0917-12-080
Project: BR 2012(334) District: BRYAN Time: 82 WORKING DAYS Type: REPLACE EXISTING BRIDGE FACILITY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $540,786.50
ELLIS-MCGINNIS CONSTRUCTION CO.   $447,590.00 1
-17.23% | -$93,196.50
TREVWAY, INC.   $516,502.80 2
-4.49% | -$24,283.70
15.4% | $68,912.80
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.   $528,983.50 3
-2.18% | -$11,803.00
18.18% | $81,393.50
2.42% | $12,480.70
JAMES CONSTRUCTION GROUP, L.L.C.   $542,743.50 4
0.36% | $1,957.00
21.26% | $95,153.50
2.60% | $13,760.00
PIERCE R & B LLC   $567,222.60 5
4.89% | $26,436.10
26.73% | $119,632.60
4.51% | $24,479.10
JAY-REESE CONTRACTORS, INC.   $586,006.75 6
8.36% | $45,220.25
30.92% | $138,416.75
3.31% | $18,784.15
KNIFE RIVER CORPORATION - SOUTH   $593,847.75 7
9.81% | $53,061.25
32.68% | $146,257.75
1.34% | $7,841.00
HODGES AND SON CONSTRUCTION COMPANY, INC.   $601,828.00 8
11.29% | $61,041.50
34.46% | $154,238.00
1.34% | $7,980.25
ANGEL BROTHERS HOLDINGS CORP.   $638,279.00 9
18.03% | $97,492.50
42.6% | $190,689.00
6.06% | $36,451.00
FUQUA CONSTRUCTION CO., INC.   $650,322.22 10
20.25% | $109,535.72
45.29% | $202,732.22
1.89% | $12,043.22
REECE CONSTRUCTION CO., INC.   $673,768.70 11
24.59% | $132,982.20
50.53% | $226,178.70
3.61% | $23,446.48

Bid Items

Items: 29, 0 filtered
MILAM CR  |  BRYAN  |  0917-12-080  |  06/06/2017  |  $540,787  |  BR 2012(334)  |  REPLACE EXIST BRIDGE FACILITY  |  82 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ELLIS-MCGINNIS CONSTRUCTION CO. TREVWAY, INC. A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. JAMES CONSTRUCTION GROUP, L.L.C. PIERCE R & B LLC JAY-REESE CONTRACTORS, INC. KNIFE RIVER CORPORATION - SOUTH HODGES AND SON CONSTRUCTION COMPANY, INC. ANGEL BROTHERS HOLDINGS CORP. FUQUA CONSTRUCTION CO., INC. REECE CONSTRUCTION CO., INC.
100 6002 PREPARING ROW STA 7.000 $2,200.000 $1,900.000 $1,200.000 $2,800.000 $2,500.000 $2,500.000 $400.000 $4,500.000 $3,600.000 $5,200.000 $2,089.420 $4,000.000
110 6001 EXCAVATION (ROADWAY) CY 70.000 $15.000 $12.000 $21.240 $36.000 $50.000 $30.000 $20.000 $80.000 $30.000 $85.000 $35.070 $65.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 275.000 $15.000 $21.000 $25.000 $24.000 $50.000 $35.000 $50.000 $35.000 $40.000 $40.000 $63.700 $65.000
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 695.000 $1.500 $1.000 $3.000 $1.200 $0.940 $1.100 $1.050 $1.500 $4.000 $1.500 $1.900 $1.500
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 348.000 $1.500 $1.000 $3.000 $2.000 $1.600 $1.100 $1.750 $1.500 $2.000 $1.500 $1.900 $1.500
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 348.000 $1.500 $1.000 $3.000 $2.000 $1.600 $1.100 $1.750 $1.500 $2.000 $1.500 $1.900 $1.500
168 6001 VEGETATIVE WATERING MG 21.000 $25.000 $26.000 $25.000 $100.000 $14.000 $70.000 $35.000 $65.000 $1.000 $35.000 $72.630 $200.000
247 6073 FL BS (CMP IN PLC)(TY D GR 1-2) (6") SY 1,570.000 $20.000 $12.000 $19.000 $14.400 $20.000 $18.000 $16.000 $12.000 $30.000 $15.000 $16.240 $20.500
400 6005 CEM STABIL BKFL CY 51.000 $100.000 $180.000 $125.000 $180.000 $180.000 $190.000 $175.000 $150.000 $250.000 $250.000 $183.650 $200.000
416 6002 DRILL SHAFT (24 IN) LF 540.000 $140.000 $170.000 $180.000 $130.000 $120.000 $135.000 $126.000 $140.000 $150.000 $107.000 $174.100 $190.000
420 6013 CL C CONC (ABUT) CY 20.400 $1,000.000 $860.000 $590.000 $810.000 $1,200.000 $1,200.000 $1,600.000 $1,400.000 $1,100.000 $1,300.000 $922.300 $1,460.000
420 6025 CL C CONC (BENT) CY 13.200 $1,200.000 $840.000 $1,000.000 $950.000 $1,500.000 $1,400.000 $2,200.000 $1,800.000 $1,200.000 $1,400.000 $1,528.630 $1,401.000
420 6037 CL C CONC (COLUMN) CY 5.600 $1,200.000 $840.000 $1,850.000 $1,600.000 $1,300.000 $2,100.000 $2,400.000 $1,800.000 $1,600.000 $2,000.000 $3,046.840 $1,880.000
422 6001 REINF CONC SLAB SF 3,900.000 $16.000 $12.300 $21.000 $14.500 $13.000 $20.000 $22.000 $17.760 $20.000 $21.000 $18.720 $24.100
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 742.500 $165.000 $130.000 $150.000 $145.000 $160.000 $167.000 $160.000 $190.000 $170.000 $170.000 $186.160 $215.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 153.000 $120.000 $100.000 $119.000 $200.000 $80.000 $145.000 $90.000 $125.000 $140.000 $160.000 $175.190 $185.000
450 6006 RAIL (TY T223) LF 324.000 $110.000 $94.000 $55.000 $135.000 $80.000 $110.000 $220.000 $125.000 $120.000 $100.000 $126.860 $149.000
454 6004 ARMOR JOINT (SEALED) LF 44.000 $95.000 $90.000 $55.000 $160.000 $90.000 $100.000 $100.000 $100.000 $75.000 $145.000 $88.730 $109.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $25,000.000 $18,000.000 $20,000.000 $23,000.000 $25,000.000 $12,500.000 $19,000.000 $15,000.000 $20,000.000 $30,000.000 $38,114.330 $7,340.000
500 6001 MOBILIZATION LS 1.000 $55,000.000 $35,000.000 $53,000.000 $52,000.000 $58,000.000 $53,000.000 $53,000.000 $58,000.000 $50,000.000 $64,000.000 $70,141.780 $47,020.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $3,000.000 $500.000 $700.000 $2,500.000 $6,000.000 $2,500.000 $300.000 $900.000 $2,000.000 $7,000.000 $1,154.430 $250.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 52.000 $25.000 $38.000 $15.000 $27.000 $40.000 $45.000 $27.000 $38.000 $50.000 $35.000 $44.350 $35.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 52.000 $8.000 $9.000 $10.000 $20.000 $17.300 $15.000 $20.000 $15.000 $20.000 $15.000 $19.010 $15.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,245.000 $3.500 $3.600 $2.000 $2.400 $2.100 $4.000 $2.400 $5.250 $2.000 $3.500 $4.440 $3.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,245.000 $1.200 $1.000 $2.000 $1.000 $0.500 $1.000 $0.600 $1.000 $2.000 $1.000 $1.270 $1.000
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $1,200.000 $1,000.000 $700.000 $880.000 $784.000 $1,080.000 $900.000 $1,500.000 $600.000 $1,500.000 $1,267.230 $1,000.000
544 6004 GDRAIL END TRT(INST)(WOOD POST)(TY I) EA 4.000 $2,150.000 $2,500.000 $2,000.000 $2,500.000 $2,225.000 $2,700.000 $2,600.000 $2,400.000 $2,500.000 $2,500.000 $3,168.080 $2,500.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 4.000 $60.000 $25.000 $5.000 $17.000 $15.000 $30.000 $17.500 $35.000 $50.000 $30.000 $31.680 $25.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 4.000 $60.000 $25.000 $5.000 $17.000 $15.000 $30.000 $17.500 $35.000 $50.000 $30.000 $31.680 $25.000
Totals: $540,786.50 $447,590.00 $516,502.80 $528,983.50 $542,743.50 $567,222.60 $586,006.75 $593,847.75 $601,828.00 $638,279.00 $650,322.23 $673,768.70