MIDLAND CS (0906-32-059)

Items: 27

County: MIDLAND
Length: N/A
Highway: CS
District: ODESSA
Control Number: 0906-32-059
DBE Goal: N/A
Project: STP 2022(637)HESG
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $206,087.64
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$206,087.64
Over/Under Est: 103.16% $212,600.36
Over/Under Est: 117.61% $242,385.08
Amt Left: 7.11% $29,784.72
Over/Under Est: 120.59% $248,516.36
Amt Left: 8.58% $35,916.00
Delta: -1.37% -$6,131.28

Bid Items & Bid Tabulations

27 Total 0 of 27
MIDLAND  |  CS  |  ODESSA  |  0906-32-059  |  08/03/2022  |  $206,087.64  |  STP 2022(637)HESG  |  HAZARD ELIM & SAFETY  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNH CONSTRUCTION, LLC
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
O. TREVINO CONSTRUCTION, LLC
REMOVING CONC (PAV)
SY 113.000 $6.080 $100.000 $26.250 $100.000
REMOVING CONC (CURB AND GUTTER)
LF 147.000 $5.730 $100.000 $21.000 $50.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 118.000 $14.000 $100.000 $25.200 $50.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 729.000 $7.460 $65.000 $30.450 $50.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 74.000 $9.000 $75.000 $31.500 $90.000
SALV, HAUL & STKPL RCL APH PV (2 TO 4")
SY 641.000 $1.350 $30.000 $29.400 $80.000
PRIME COAT (MC-30)
GAL 15.000 $5.100 $10.000 $26.250 $100.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 641.000 $1.340 $10.000 $29.400 $40.000
CONC PVMT (CONT REINF - CRCP) (7")
SY 527.000 $102.760 $120.000 $198.450 $160.000
CONC PVMT(CRCP)(TRANSITION SLAB)
SY 222.000 $113.700 $200.000 $197.400 $160.000
ADJUSTING MANHOLES
EA 2.000 $1,900.000 $5,000.000 $3,911.250 $1,500.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 5.000 $680.000 $1,200.000 $2,205.000 $1,000.000
MOBILIZATION
LS 1.000 $25,000.000 $40,000.000 $44,460.000 $45,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,400.000 $8,500.000 $10,000.000 $3,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 48.000 $4.330 $18.000 $8.400 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 48.000 $1.300 $9.000 $3.680 $1.000
CONC CURB & GUTTER (TY I)
LF 318.000 $21.800 $75.000 $42.260 $100.000
CONC SIDEWALKS (4")
SY 133.000 $95.000 $85.000 $132.300 $100.000
CURB RAMPS (TY 2)
EA 7.000 $2,000.000 $4,000.000 $5,460.000 $4,000.000
CURB RAMPS (TY 4)
EA 1.000 $2,000.000 $4,000.000 $6,142.500 $4,500.000
ALUMINUM SIGNS (TY G)
SF 10.000 $1,000.000 $100.000 $892.500 $100.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 2.000 $31.000 $100.000 $892.500 $100.000
PREFAB PAV MRK TY B (W)(4")(SLD)
LF 660.000 $6.760 $6.000 $15.750 $20.000
PREFAB PAV MRK TY C (W) (8") (DOT)
LF 92.000 $6.000 $6.000 $16.800 $20.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 168.000 $14.000 $20.000 $17.850 $40.000
D-GR HMA TY-D PG76-22
TON 5.000 $88.000 $1,000.000 $525.000 $1,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 90.000 $30.000 $150.000 $120.750 $150.000
Totals: $206,087.640 $418,688.000 $448,472.720 $454,604.000