Job Info for 0380-09-098

County: MIDLAND Highway: BS 349C Date: 12/02/2022 (1 year ago) Engineer's Estimate: $13,839,758 Control Number: 0380-09-098
Project: F 2022(585) District: ODESSA Time: 300 WORKING DAYS Type: REHABILITATE EXISTING ROADWAY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $13,839,757.59
JONES BROS. DIRT & PAVING CONTRACTORS, INC.   $17,997,658.13 1
30.04% | $4,157,900.54
RK HALL, LLC   $19,338,273.62 2
39.73% | $5,498,516.03
7.45% | $1,340,615.49
REECE ALBERT, INC.   $19,735,692.57 3
42.6% | $5,895,934.98
9.66% | $1,738,034.44
2.06% | $397,418.95
Subcontractor Percentage Amount
DESERT PAVING, INC. 18.05% $3,248,577.29
HJC FARMS, INC. 2.67% $480,537.47
DK CONTRACTING, LLC 2.52% $453,540.98
O. TREVINO CONSTRUCTION, LLC 2.38% $428,344.26
DOUBLE A CONTRACTING, L.P. 2.26% $406,747.07
DUSTROL, INC. 1.96% $352,754.10
AARON CONCRETE CONTRACTORS, LLC 1.34% $241,168.62
CONTRACTORS SERVICE, LTD. 1.22% $219,571.43
R.E.B.D. TRUCKING LLC 0.32% $57,592.51
BOLER EQUIPMENT 0.13% $23,396.96
STREET FOUNDATION DRILLING, INC. 0.07% $12,598.36
ROYAL REBAR 0.04% $7,199.06
Total: 32.96% $5,932,028.11

Bid Items

Items: 100, 0 filtered
MIDLAND BS 349C  |  ODESSA  |  0380-09-098  |  12/02/2022  |  $13,839,758  |  F 2022(585)  |  REHAB EXIST ROADWAY  |  300 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate JONES BROS. DIRT & PAVING CONTRACTORS, INC. RK HALL, LLC REECE ALBERT, INC.
104 6011 REMOVING CONC (MEDIANS) SY 1,155.000 $30.000 $90.000 $41.230 $48.090
104 6017 REMOVING CONC (DRIVEWAYS) SY 1,192.000 $25.000 $45.000 $47.470 $48.090
104 6022 REMOVING CONC (CURB AND GUTTER) LF 5,661.000 $8.000 $19.250 $10.610 $11.250
105 6008 REMOVING STAB BASE AND ASPH PAV (6") SY 1,935.000 $4.000 $33.490 $117.470 $5.320
105 6041 REMOVING STAB BASE AND ASPH PAV(8") SY 46,961.000 $5.000 $8.380 $9.310 $8.600
251 6079 REWORK BS MTL (TY D)(SURF)(ORD COMP) SY 48,932.000 $1.000 $1.320 $1.760 $0.940
310 6005 PRIME COAT (AE-P) GAL 9,790.000 $5.000 $4.720 $8.290 $7.100
315 6004 FOG SEAL (CSS-1H) GAL 4,699.000 $4.000 $4.280 $5.890 $7.030
316 6017 ASPH (AC-20-5TR) GAL 17,846.000 $5.500 $4.650 $5.530 $5.390
316 6126 AGGR(TY-PB GR-4 SAC-A) CY 394.000 $245.000 $199.000 $295.520 $360.530
354 6006 PLAN & TEXT ASPH CONC PAV(4" TO 6") SY 90,966.000 $5.000 $5.890 $7.120 $5.960
354 6045 PLANE ASPH CONC PAV (2") SY 10,735.000 $2.500 $16.780 $21.390 $21.270
354 6048 PLANE ASPH CONC PAV (3") SY 52,633.000 $3.000 $3.790 $4.290 $3.850
360 6021 CONC PVMT (JOINTED - CPCD) (11") SY 1,686.000 $100.000 $276.000 $276.000 $438.150
420 6128 CL K CONC (MISC) CY 13.000 $2,200.000 $2,220.000 $1,800.000 $5,155.950
420 6135 CL C CONC (RAIL FOUNDATION)(HPC) CY 384.000 $675.000 $906.000 $2,160.000 $1,089.370
450 6125 RAIL (TY T80PP-TS) LF 575.000 $320.000 $775.000 $450.000 $556.490
451 6008 RETROFIT RAIL (TY T223)(HPC) LF 224.000 $350.000 $360.000 $480.000 $484.000
451 6034 RETROFIT RAIL (TY C223)(HPC) LF 121.000 $350.000 $597.600 $600.000 $532.400
465 6233 INLET (COMP) (TY SIDEWALK BRIDGE) EA 1.000 $17,000.000 $43,200.000 $48,000.000 $52,578.990
479 6001 ADJUSTING MANHOLES EA 85.000 $1,600.000 $3,000.000 $1,870.380 $3,395.990
479 6005 ADJUSTING MANHOLES (WATER VALVE BOX) EA 85.000 $700.000 $1,320.000 $279.520 $1,535.720
479 6010 ADJUSTING MANHOLES (ELECTRIC BOX) EA 7.000 $700.000 $1,800.000 $3,546.470 $3,583.000
500 6001 MOBILIZATION LS 1.000 $1,237,705.240 $1,720,000.000 $1,569,996.980 $1,260,018.140
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $15,000.000 $25,000.000 $30,678.660 $23,993.070
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 630.000 $6.500 $6.700 $10.100 $12.820
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 630.000 $1.500 $4.400 $3.920 $6.340
512 6009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) LF 2,960.000 $50.000 $110.400 $110.400 $44.630
512 6010 PORT CTB (FUR & INST)(LOW PROF)(TY 2) LF 80.000 $50.000 $110.400 $110.400 $45.940
512 6057 PORT CTB (REMOVE)(LOW PROF)(TY 1) LF 2,960.000 $12.000 $18.000 $18.000 $14.100
512 6058 PORT CTB (REMOVE)(LOW PROF)(TY 2) LF 80.000 $14.000 $18.000 $18.000 $15.550
514 6001 PERM CTB (SGL SLOPE) (TY 1) (42 ) LF 695.000 $125.000 $192.000 $132.000 $166.550
529 6008 CONC CURB & GUTTER (TY II) LF 2,000.000 $40.000 $54.000 $102.000 $89.630
530 6025 DRIVEWAYS (CONC) (FAST TRACK) SY 4,037.000 $95.000 $286.800 $198.000 $219.000
531 6001 CONC SIDEWALKS (4") SY 4,360.000 $90.000 $168.000 $120.000 $154.820
531 6004 CURB RAMPS (TY 1) EA 21.000 $3,000.000 $6,300.000 $2,400.000 $5,155.180
531 6005 CURB RAMPS (TY 2) EA 4.000 $2,600.000 $6,480.000 $3,000.000 $6,695.720
531 6006 CURB RAMPS (TY 3) EA 1.000 $2,600.000 $6,720.000 $3,120.000 $12,356.700
531 6010 CURB RAMPS (TY 7) EA 20.000 $2,700.000 $6,480.000 $3,240.000 $5,315.690
531 6013 CURB RAMPS (TY 10) EA 15.000 $2,900.000 $6,480.000 $3,360.000 $5,556.690
531 6016 CURB RAMPS (TY 21) EA 3.000 $2,800.000 $7,440.000 $4,800.000 $6,902.980
536 6002 CONC MEDIAN SY 1,078.000 $120.000 $300.000 $200.020 $199.910
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $3,000.000 $3,420.000 $3,420.000 $3,815.860
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,800.000 $1,860.000 $1,860.000 $2,075.290
542 6001 REMOVE METAL BEAM GUARD FENCE LF 349.000 $4.000 $3.600 $3.600 $4.020
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 2.000 $350.000 $360.000 $360.000 $401.670
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $3,900.000 $4,140.000 $4,140.000 $4,619.200
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $450.000 $360.000 $360.000 $401.670
545 6007 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) EA 2.000 $30,000.000 $49,800.000 $49,800.000 $71,761.170
560 6004 MAILBOX INSTALL-S (TWG-POST) TY 2 EA 41.000 $275.000 $327.600 $327.600 $401.670
560 6005 MAILBOX INSTALL-D (TWG-POST) TY 2 EA 2.000 $350.000 $422.400 $422.400 $468.620
636 6007 REPLACE EXISTING ALUMINUM SIGNS(TY A) SF 240.000 $50.000 $51.600 $51.600 $38.160
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 142.000 $900.000 $984.000 $984.000 $1,251.870
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 7.000 $850.000 $1,116.000 $1,116.000 $1,372.370
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 3.000 $1,350.000 $1,434.000 $1,434.000 $1,666.930
644 6012 IN SM RD SN SUP&AM TY10BWG(1)SB(T) EA 3.000 $1,000.000 $1,167.600 $1,167.600 $1,472.790
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 7.000 $1,100.000 $1,216.800 $1,216.800 $1,439.320
644 6031 IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT) EA 3.000 $1,700.000 $1,620.000 $1,620.000 $1,874.460
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 7.000 $1,600.000 $1,699.200 $1,699.200 $1,874.460
644 6034 IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT) EA 1.000 $1,400.000 $1,902.000 $1,902.000 $2,075.290
644 6036 IN SM RD SN SUP&AM TYS80(1)SA(U-BM) EA 1.000 $1,600.000 $1,885.200 $1,885.200 $1,981.570
644 6064 IN BRIDGE MNT CLEARANCE SGN ASSM(TY N) EA 2.000 $2,500.000 $3,924.000 $3,924.000 $5,020.870
644 6066 IN SM RD SN SUP&AM (RAIL MOUNT) EA 7.000 $3,800.000 $6,933.600 $6,933.600 $8,669.360
644 6075 RELOCATE SM RD SN SUP&AM(SIGN ONLY) EA 39.000 $400.000 $483.600 $483.600 $669.450
644 6076 REMOVE SM RD SN SUP&AM EA 178.000 $180.000 $330.000 $276.620 $167.360
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 12,870.000 $0.300 $0.190 $0.190 $0.210
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 389,186.000 $0.250 $0.180 $0.180 $0.200
662 6010 WK ZN PAV MRK NON-REMOV (W)8"(DOT) LF 1,103.000 $0.750 $0.960 $0.960 $1.070
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 3,973.000 $0.600 $0.480 $0.480 $0.540
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 14,972.000 $5.000 $2.160 $2.160 $2.410
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 6,800.000 $0.300 $0.190 $0.190 $0.210
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 417,404.000 $0.250 $0.180 $0.180 $0.200
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 8,507.000 $1.500 $2.000 $6.460 $2.330
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 10,528.000 $1.500 $2.000 $5.520 $2.360
666 6030 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 615.000 $2.200 $2.160 $2.160 $2.410
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 4,873.000 $1.100 $1.080 $1.080 $1.210
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 12,300.000 $0.500 $0.780 $0.780 $0.870
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 6,800.000 $0.500 $0.780 $0.780 $0.870
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 40,845.000 $0.500 $0.760 $0.760 $0.840
668 6005 PREFAB PAV MRK TY B (W)(4")(BRK)CNTST LF 540.000 $20.000 $15.600 $15.600 $17.410
668 6043 PREFAB PAV MRK TY B (Y)(4")(SLD) LF 2,116.000 $8.000 $13.200 $13.200 $14.730
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 7,488.000 $15.000 $14.400 $14.400 $16.070
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 34.000 $250.000 $330.000 $330.000 $368.200
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 19.000 $35.000 $24.000 $24.000 $26.780
672 6007 REFL PAV MRKR TY I-C EA 903.000 $4.500 $4.800 $4.800 $5.360
672 6009 REFL PAV MRKR TY II-A-A EA 1,290.000 $4.000 $4.800 $4.800 $5.360
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 75,711.000 $0.500 $1.000 $1.000 $0.640
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 546.000 $3.500 $1.800 $1.800 $2.010
678 6001 PAV SURF PREP FOR MRK (4") LF 2,656.000 $0.250 $0.660 $0.660 $0.740
3000 6003 CAM (ASPHALT) PG(76-22) TON 632.000 $150.000 $955.000 $1,158.760 $1,071.120
3000 6004 CAM (AGGREGATE) TON 7,665.000 $150.000 $125.000 $142.340 $138.350
3077 6007 SP MIXES SP-B SAC-B PG70-22 TON 15,594.000 $125.000 $111.000 $135.760 $149.370
3077 6075 TACK COAT GAL 4,729.000 $4.500 $3.700 $9.300 $2.970
3080 6021 STONE-MTRX-ASPH SMAR-F SAC-A TON 22,185.000 $185.000 $185.000 $217.760 $249.120
3080 6029 TACK COAT GAL 15,307.000 $4.500 $3.700 $5.700 $2.900
3084 6001 BONDING COURSE GAL 19,098.000 $5.500 $4.580 $6.650 $2.900
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $17,500.000 $19,250.000 $21,579.920 $26,813.100
6185 6002 TMA (STATIONARY) DAY 620.000 $200.000 $165.000 $446.760 $482.000
6185 6005 TMA (MOBILE OPERATION) DAY 116.000 $450.000 $935.000 $631.380 $983.770
6408 6001 FLOOD GAUGE ASSEMBLY EA 2.000 $500.000 $483.600 $483.600 $1,338.900
Totals: $13,839,757.59 $17,997,658.13 $19,338,273.62 $19,735,692.57