Job Info for 6393-25-001

County: MCLENNAN Highway: FM1860 Date: 01/04/2022 (2 years ago) Engineer's Estimate: $73,887 Control Number: 6393-25-001
Project: RMC - 639325001 District: WACO Time: 35 CALENDAR DAYS Type: CULVERT REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $73,887.00
FULL FORCE DRILLING, LLC   $69,447.00 1
-6.01% | -$4,440.00
TCB CONSTRUCTION, INC   $94,760.70 2
28.25% | $20,873.70
36.45% | $25,313.70
BEAR CREEK CONTRACTING, LLC   $112,440.00 3
52.18% | $38,553.00
61.91% | $42,993.00
18.66% | $17,679.30
CROSS PLUS CONSTRUCTION, LLC   $135,160.00 4
82.93% | $61,273.00
94.62% | $65,713.00
20.21% | $22,720.00

Bid Items

Items: 21, 0 filtered
MCLENNAN FM1860  |  WACO  |  6393-25-001  |  01/04/2022  |  $73,887  |  RMC - 639325001  |  CULVERT REPAIR  |  35 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate FULL FORCE DRILLING, LLC TCB CONSTRUCTION, INC BEAR CREEK CONTRACTING, LLC CROSS PLUS CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 1.000 $1,000.000 $500.000 $5,500.000 $200.000 $5,000.000
110 6001 EXCAVATION (ROADWAY) CY 394.000 $20.000 $12.000 $25.000 $8.000 $35.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 167.000 $20.000 $15.000 $55.000 $40.000 $35.000
150 6001 BLADING STA 1.000 $100.000 $2,209.000 $500.000 $100.000 $1,200.000
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 2,200.000 $0.500 $2.100 $0.350 $0.600 $1.000
168 6001 VEGETATIVE WATERING MG 66.000 $40.000 $18.500 $22.000 $10.000 $1.000
340 6011 D-GR HMA(SQ) TY-B PG64-22 TON 6.000 $100.000 $500.000 $450.000 $491.000 $800.000
400 6005 CEM STABIL BKFL CY 98.000 $150.000 $34.000 $75.000 $250.000 $250.000
401 6001 FLOWABLE BACKFILL CY 43.000 $150.000 $34.000 $199.000 $175.000 $250.000
402 6001 TRENCH EXCAVATION PROTECTION LF 85.000 $20.000 $90.000 $22.000 $6.000 $45.000
464 6003 RC PIPE (CL III)(18 IN) LF 88.000 $100.000 $35.000 $125.000 $85.000 $98.000
466 6128 HEADWALL (CH - PW - S) (DIA= 18 IN) EA 2.000 $4,500.000 $9,080.000 $6,900.000 $17,000.000 $12,000.000
496 6007 REMOV STR (PIPE) LF 88.000 $30.000 $10.000 $20.000 $5.000 $20.000
500 6001 MOBILIZATION LS 1.000 $6,717.000 $800.000 $7,000.000 $10,008.000 $10,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 $3,000.000 $5,000.000 $5,500.000 $7,709.000 $2,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 40.000 $30.000 $50.000 $45.000 $30.000 $20.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 40.000 $8.000 $45.000 $10.000 $3.000 $20.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 100.000 $3.000 $5.000 $9.000 $5.000 $1.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 100.000 $2.000 $5.000 $4.000 $2.000 $1.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 10.000 $60.000 $150.000 $165.000 $119.000 $250.000
6185 6002 TMA (STATIONARY) DAY 10.000 $160.000 $400.000 $281.670 $200.000 $1,200.000
Totals: $73,887.00 $69,447.00 $94,760.70 $112,440.00 $135,160.00