MCLENNAN US0084 (6342-36-001)

Items: 38

County: MCLENNAN
Length: N/A
Highway: US0084
District: WACO
Control Number: 6342-36-001
DBE Goal: N/A
Project: RMC - 634236001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $812,766.00
Date: 05/08/2019 (7 years ago)
Contract Number: N/A
Type: MBGF, CABLE BARRIER, BRIDGE RAIL REP/INS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$812,766.00
$1,355,400.00
Over/Under Est: 66.76% $542,634.00

Bid Items & Bid Tabulations

38 Total 0 of 38
MCLENNAN  |  US0084  |  WACO  |  6342-36-001  |  05/08/2019  |  $812,766.00  |  RMC - 634236001  |  MBGF, CABLE BARRIER, BRIDGE RAIL REP...  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VANN/ELLI, INC.
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 50.000 $100.000 $500.000
RAIL (HANDRAIL)(DECORATIVE)
LF 30.000 $100.000 $800.000
MOBILIZATION (CALLOUT)
EA 12.000 $4,926.000 $2,500.000
MOBILIZATION (EMERGENCY)
EA 8.000 $1,848.000 $3,000.000
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $25.000 $33.000
TERMINAL ANCHOR SECTION
EA 5.000 $100.000 $600.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $1,500.000 $2,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $950.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $2.500 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $150.000 $500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $150.000 $300.000
GDRAIL END TRT(INSTALL)(HBA POST)
EA 40.000 $2,600.000 $3,500.000
CRASH CUSH ATTEN (DES SOURCE)
EA 5.000 $2,200.000 $20,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 50.000 $30.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $25.000 $50.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 4,500.000 $15.000 $30.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 25.000 $20.000 $50.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 12.000 $15.000 $50.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 200.000 $40.000 $80.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 100.000 $50.000 $90.000
REALIGN POSTS
EA 100.000 $15.000 $25.000
REMOVE & REPLACE BLOCKOUT
EA 1,000.000 $15.000 $25.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 125.000 $2,700.000 $3,500.000
REPAIR RAIL ELEMENT(W - BEAM FURNISHED)
LF 2,000.000 $11.000 $15.000
REPLACE POSTS (TL-4)
EA 200.000 $100.000 $200.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 2.000 $120.000 $1,000.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 5.000 $800.000 $2,000.000
REPLACE CABLE (TL-4)
LF 7,000.000 $2.000 $4.000
POST AND CABLE FENCE (NEW INSTALLATION)
LF 200.000 $5.000 $10.000
POST AND CABLE FENCE (NEW CONC ANCHOR)
EA 5.000 $50.000 $300.000
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 10.000 $40.000 $100.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 700.000 $4.000 $3.000
REMOVE AND REPLACE (TRACC)
EA 5.000 $10,000.000 $20,000.000
REPAIR (ALUMINUM RAIL)
LF 50.000 $75.000 $300.000
REPAIR(STEEL POST W/ CHANNEL IRON RAIL)
LF 150.000 $80.000 $250.000
REPAIR (W-BEAM - T101 RAIL)
LF 250.000 $15.000 $125.000
TMA (STATIONARY)
EA 2.000 $7,500.000 $15,000.000
TMA (STATIONARY)
DAY 20.000 $250.000 $400.000
Totals: $812,766.000 $1,355,400.000