Job Info for 0909-22-176

County: MCLENNAN Highway: CR Date: 04/02/2019 (5 years ago) Engineer's Estimate: $942,046 Control Number: 0909-22-176
Project: BR 2018(219) District: WACO Time: 150 WORKING DAYS Type: REPL BR & APPRS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $942,046.20
KNIFE RIVER CORPORATION - SOUTH   $863,437.65 1
-8.34% | -$78,608.55
JAMES CONSTRUCTION GROUP, L.L.C.   $926,611.53 2
-1.64% | -$15,434.67
7.32% | $63,173.88
HODGES AND SON CONSTRUCTION COMPANY, INC.   $986,963.00 3
4.77% | $44,916.80
14.31% | $123,525.35
6.51% | $60,351.47
PIERCE R & B LLC   $999,875.75 4
6.14% | $57,829.55
15.8% | $136,438.10
1.31% | $12,912.75
ELLIS-MCGINNIS CONSTRUCTION CO.   $1,007,076.50 5
6.9% | $65,030.30
16.64% | $143,638.85
0.72% | $7,200.75
PROJECT ALLIED RESOURCES, LLC   $1,038,850.58 6
10.28% | $96,804.38
20.32% | $175,412.93
3.16% | $31,774.08
CDM HOLDINGS, LLC   $1,151,032.15 7
22.18% | $208,985.95
33.31% | $287,594.50
10.80% | $112,181.57
FUQUA CONSTRUCTION CO., INC.   $1,308,267.43 8
38.88% | $366,221.23
51.52% | $444,829.78
13.66% | $157,235.28

Bid Items

Items: 46, 0 filtered
MCLENNAN CR  |  WACO  |  0909-22-176  |  04/02/2019  |  $942,046  |  BR 2018(219)  |  REPL BR & APPRS  |  150 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate KNIFE RIVER CORPORATION - SOUTH JAMES CONSTRUCTION GROUP, L.L.C. HODGES AND SON CONSTRUCTION COMPANY, INC. PIERCE R & B LLC ELLIS-MCGINNIS CONSTRUCTION CO. PROJECT ALLIED RESOURCES, LLC CDM HOLDINGS, LLC FUQUA CONSTRUCTION CO., INC.
100 6002 PREPARING ROW STA 8.200 $3,000.000 $1,200.000 $5,000.000 $3,000.000 $1,500.000 $4,400.000 $2,870.000 $0.000 $3,002.964
105 6021 REMOVING STAB BASE AND ASPH PAV (0-4") SY 700.000 $5.000 $3.000 $0.850 $16.000 $6.750 $1.200 $6.300 $0.000 $10.335
110 6001 EXCAVATION (ROADWAY) CY 401.000 $15.000 $15.000 $4.960 $25.000 $18.000 $14.000 $18.500 $0.000 $40.000
110 6002 EXCAVATION (CHANNEL) CY 1,671.000 $15.000 $10.000 $3.450 $15.000 $18.000 $12.000 $16.100 $0.000 $40.000
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 1,042.000 $15.000 $10.000 $14.260 $20.000 $24.000 $12.000 $20.400 $0.000 $30.000
162 6002 BLOCK SODDING SY 2,349.000 $3.000 $3.850 $3.750 $5.000 $4.500 $4.300 $6.300 $0.000 $3.800
164 6009 BROADCAST SEED (TEMP) (WARM) SY 1,175.000 $1.000 $0.500 $0.500 $1.000 $1.100 $1.000 $0.210 $0.000 $0.550
164 6011 BROADCAST SEED (TEMP) (COOL) SY 1,175.000 $1.000 $0.500 $0.500 $1.000 $1.100 $1.000 $0.230 $0.000 $0.550
168 6001 VEGETATIVE WATERING MG 38.600 $20.000 $15.000 $25.490 $1.000 $25.000 $42.000 $2.670 $0.000 $12.555
247 6053 FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS) CY 354.000 $60.000 $65.000 $71.770 $65.000 $62.000 $70.000 $64.000 $0.000 $60.000
310 6027 PRIME COAT(MC-30 OR AE-P) GAL 252.000 $7.000 $7.500 $7.160 $15.000 $13.000 $6.000 $6.000 $0.000 $12.000
316 6022 ASPH (CRS-2) GAL 556.000 $3.000 $3.750 $14.320 $15.000 $16.000 $12.000 $12.000 $0.000 $12.000
316 6397 AGGR(TY-D GR-4 OR TY-L GR-4) CY 10.000 $200.000 $350.000 $178.960 $1,000.000 $1,100.000 $150.000 $150.000 $0.000 $600.000
340 6032 D-GR HMA(SQ) TY-C SAC-B PG64-22 TON 127.000 $140.000 $105.000 $298.270 $200.000 $270.000 $315.000 $250.000 $0.000 $300.000
400 6005 CEM STABIL BKFL CY 75.000 $160.000 $140.000 $141.540 $220.000 $200.000 $200.000 $210.000 $0.000 $140.000
416 6002 DRILL SHAFT (24 IN) LF 546.000 $150.000 $113.000 $109.370 $100.000 $133.050 $175.000 $134.000 $0.000 $200.000
416 6004 DRILL SHAFT (36 IN) LF 216.000 $210.000 $163.000 $162.660 $180.000 $175.040 $255.000 $198.000 $0.000 $260.000
420 6013 CL C CONC (ABUT) CY 53.800 $1,000.000 $950.000 $836.620 $1,000.000 $950.000 $970.000 $1,010.000 $0.000 $1,200.000
420 6029 CL C CONC (CAP) CY 13.800 $1,000.000 $1,350.000 $1,083.790 $1,200.000 $1,150.000 $1,200.000 $1,280.000 $0.000 $1,200.000
420 6037 CL C CONC (COLUMN) CY 10.500 $1,000.000 $1,050.000 $1,502.490 $1,200.000 $1,100.000 $1,150.000 $1,170.000 $0.000 $1,200.000
422 6001 REINF CONC SLAB SF 1,950.000 $18.000 $21.500 $22.440 $22.000 $23.000 $19.900 $18.300 $0.000 $40.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 3,380.000 $15.000 $14.500 $13.430 $16.000 $16.000 $14.400 $18.100 $0.000 $20.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 642.420 $160.000 $190.000 $187.610 $170.000 $185.000 $165.000 $180.000 $0.000 $200.000
425 6035 PRESTR CONC GIRDER (TX28) LF 298.000 $150.000 $174.000 $169.860 $200.000 $180.000 $165.000 $175.000 $0.000 $210.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 995.000 $120.000 $77.000 $98.390 $100.000 $100.000 $95.000 $106.000 $0.000 $120.000
450 6006 RAIL (TY T223) LF 466.000 $110.000 $98.000 $89.400 $110.000 $100.000 $125.000 $120.000 $0.000 $97.127
454 6004 ARMOR JOINT (SEALED) LF 90.000 $90.000 $90.000 $88.340 $75.000 $90.000 $90.000 $78.000 $0.000 $85.619
464 6003 RC PIPE (CL III)(18 IN) LF 20.000 $60.000 $63.000 $67.640 $100.000 $68.000 $50.000 $61.000 $0.000 $50.133
464 6005 RC PIPE (CL III)(24 IN) LF 88.000 $75.000 $73.000 $70.990 $100.000 $85.000 $80.000 $83.000 $0.000 $67.469
466 6130 HEADWALL (CH - PW - S) (DIA= 24 IN) EA 2.000 $5,500.000 $6,000.000 $6,594.780 $5,000.000 $5,000.000 $6,500.000 $6,680.000 $0.000 $4,872.208
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 2.000 $1,000.000 $1,200.000 $874.370 $1,200.000 $800.000 $1,400.000 $962.000 $0.000 $663.468
496 6007 REMOV STR (PIPE) LF 116.000 $20.000 $10.000 $4.010 $40.000 $15.000 $60.000 $12.400 $0.000 $15.817
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $20,000.000 $12,500.000 $20,000.000 $12,000.000 $12,500.000 $15,500.000 $13,500.000 $0.000 $19,024.688
500 6001 MOBILIZATION LS 1.000 $80,000.000 $86,000.000 $86,200.000 $85,000.000 $90,000.000 $90,000.000 $115,000.000 $0.000 $188,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $1,000.000 $500.000 $1,380.000 $1,200.000 $1,750.000 $700.000 $1,630.000 $0.000 $2,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 40.000 $30.000 $36.000 $35.000 $10.000 $32.000 $37.000 $51.000 $0.000 $38.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 40.000 $10.000 $10.000 $10.000 $1.000 $9.000 $10.000 $12.800 $0.000 $12.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,077.000 $3.000 $3.850 $2.750 $3.000 $3.100 $3.500 $3.620 $0.000 $2.800
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,077.000 $1.000 $0.750 $0.750 $1.000 $0.830 $1.400 $0.840 $0.000 $0.800
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 200.000 $23.000 $27.500 $22.000 $30.000 $28.000 $22.000 $27.000 $0.000 $25.462
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 8.000 $900.000 $1,250.000 $890.000 $1,100.000 $1,250.000 $890.000 $1,200.000 $0.000 $1,131.971
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $2,500.000 $2,600.000 $2,450.000 $2,800.000 $2,675.000 $2,450.000 $2,550.000 $0.000 $2,571.394
552 6003 WIRE FENCE (TY C) LF 420.000 $12.000 $9.000 $5.000 $20.000 $10.000 $10.000 $15.700 $0.000 $10.840
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 12.000 $25.000 $29.000 $20.000 $20.000 $30.000 $20.000 $28.000 $0.000 $21.451
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 8.000 $30.000 $46.000 $22.000 $30.000 $50.000 $22.000 $45.000 $0.000 $27.623
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 28.000 $100.000 $50.000 $66.880 $95.000 $124.000 $85.000 $80.000 $0.000 $65.000
Totals: $942,046.20 $863,437.65 $926,611.55 $986,963.00 $999,875.75 $1,007,076.50 $1,038,850.58 $0.00 $1,308,267.48