County: MCLENNAN Highway: VA Date: 05/03/2024 (6 months ago) Engineer's Estimate: $3,859,563 Control Number: 0909-00-094
Project: C 909-00-94 District: WACO Time: 60 WORKING DAYS Type: HIGHWAY IMPROVEMENT
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,859,562.55
STRIPE-A-ZONE, LLC   $2,897,993.38 1
-24.91% | -$961,569.17
STRIPE LINES, INC.   $3,160,021.88 2
-18.12% | -$699,540.67
9.04% | $262,028.50
D. I. J. CONSTRUCTION, INC.   $3,175,921.80 3
-17.71% | -$683,640.75
9.59% | $277,928.42
0.50% | $15,899.92
TRP INFRASTRUCTURE SERVICES, LLC   $3,551,865.97 4
-7.97% | -$307,696.58
22.56% | $653,872.59
11.84% | $375,944.17
PAVEMENT MARKINGS INC.   $3,719,139.46 5
-3.64% | -$140,423.09
28.33% | $821,146.08
4.71% | $167,273.49
STRIPING TECHNOLOGY, L.P.   $4,074,371.50 6
5.57% | $214,808.95
40.59% | $1,176,378.12
9.55% | $355,232.04
INTERSTATE BARRICADES & MARKINGS, INC.   $4,237,278.99 7
9.79% | $377,716.44
46.21% | $1,339,285.61
4.00% | $162,907.49
TRAFFIC HIGHWAY MAINTENANCE, LLC   $5,089,012.19 8
31.85% | $1,229,449.64
75.6% | $2,191,018.81
20.10% | $851,733.20

Bid Items

Items: 15, 0 filtered
MCLENNAN VA  |  WACO  |  0909-00-094  |  05/03/2024  |  $3,859,563  |  C 909-00-94  |  HWY IMPRV  |  60 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, LLC STRIPE LINES, INC. D. I. J. CONSTRUCTION, INC. TRP INFRASTRUCTURE SERVICES, LLC PAVEMENT MARKINGS INC. STRIPING TECHNOLOGY, L.P. INTERSTATE BARRICADES & MARKINGS, INC. TRAFFIC HIGHWAY MAINTENANCE, LLC
500 6001 MOBILIZATION LS 1.000 $350,000.000 $10,000.000 $30,000.000 $15,000.000 $15,000.000 $45,000.000 $100,000.000 $250,000.000 $75,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $5,000.000 $1,000.000 $2,000.000 $1,000.000 $500.000 $100.000 $20,000.000 $10,000.000 $7,500.000
666 6018 REFL PAV MRK TY I (W)6"(DOT)(100MIL) LF 1,922.000 $2.000 $1.000 $0.590 $1.000 $1.250 $3.800 $2.000 $2.000 $1.750
666 6033 REFL PAV MRK TY I (W)8"(LNDP)(100MIL) LF 39.000 $2.000 $1.850 $0.800 $5.000 $5.000 $4.200 $10.000 $2.000 $5.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 11,171.000 $1.500 $0.850 $0.800 $0.780 $1.000 $1.800 $1.000 $1.250 $1.300
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 6,968.000 $10.000 $8.250 $6.000 $10.000 $8.500 $11.400 $6.700 $8.000 $8.000
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 15,100.000 $0.700 $0.520 $0.510 $0.520 $0.620 $0.950 $0.750 $0.550 $0.800
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 112,768.000 $0.700 $0.510 $0.510 $0.500 $0.620 $0.750 $0.750 $0.550 $0.710
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 4,100.000 $0.700 $0.520 $0.510 $0.550 $0.620 $0.900 $0.750 $0.550 $0.800
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 112,201.000 $0.700 $0.530 $0.510 $0.510 $0.620 $0.680 $0.750 $0.550 $0.710
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 2,231,044.000 $0.750 $0.640 $0.710 $0.720 $0.810 $0.820 $0.850 $0.890 $1.100
666 6346 REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL) LF 189,682.000 $0.750 $0.680 $0.710 $0.740 $0.850 $0.950 $1.000 $0.890 $1.250
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 1,461,135.000 $0.750 $0.650 $0.710 $0.730 $0.810 $0.840 $0.850 $0.890 $1.100
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 36,620.000 $4.500 $4.900 $4.620 $3.750 $3.500 $2.900 $6.000 $5.000 $5.000
6185 6003 TMA (MOBILE OPERATION) HR 2,028.000 $75.000 $1.000 $10.000 $1.000 $15.000 $22.000 $50.000 $50.000 $125.000
Totals: $3,859,562.55 $2,897,993.38 $3,160,021.88 $3,175,921.80 $3,551,865.97 $3,719,139.46 $4,074,371.50 $4,237,278.99 $5,089,012.19