Items: 33

County: MCLENNAN
Length: N/A
Highway: US 84
District: WACO
Control Number: 0055-15-081
DBE Goal: 0.0%
Project: STP 2B24(135)VRU
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $266,713.00
Date: 06/06/2024 (1 year ago)
Contract Number: N/A
Type: INSTALL RAISED MEDIAN
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$266,713.00
$299,986.38
Over/Under Est: 12.48% $33,273.38
Over/Under Est: 74.25% $198,027.00
Amt Left: 54.92% $164,753.62
Over/Under Est: 112.45% $299,925.00
Amt Left: 88.89% $266,651.62
Delta: -21.93% -$101,898.00

Bid Items & Bid Tabulations

33 Total 0 of 33
MCLENNAN  |  US 84  |  WACO  |  0055-15-081  |  06/06/2024  |  $266,713.00  |  STP 2B24(135)VRU  |  INSTL RAISED MEDIAN  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ENCINO LANDSCAPE, INC.
RISE UP CONSTRUCTION LLC
DIGG COMMERCIAL, LLC
REMOVING CONC (PAV)
SY 1,256.000 $10.000 $10.000 $59.000 $27.000
REMOVING CONC (MEDIANS)
SY 235.000 $25.000 $20.000 $45.000 $81.000
REMOVING CONC (CURB)
LF 1,196.000 $10.000 $15.000 $23.000 $16.000
REMOVING STAB BASE AND ASPH PAV (1")
SY 1,584.000 $1.500 $10.000 $12.000 $8.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 179.000 $20.000 $60.000 $44.000 $64.000
CONC PVMT (CONT REINF - CRCP) (9")
SY 271.000 $73.000 $175.780 $399.000 $135.000
SAND BACKFILL
CY 103.000 $45.000 $60.000 $45.000 $70.000
RIPRAP (CONC)(4 IN)
CY 103.000 $600.000 $500.000 $400.000 $800.000
MOBILIZATION
LS 1.000 $25,000.000 $30,000.000 $25,000.000 $90,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $2,000.000 $3,500.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 600.000 $3.900 $2.000 $1.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 600.000 $0.720 $1.000 $1.000 $2.000
CONC CURB (MONO) (TY II)
LF 206.000 $25.000 $25.000 $35.000 $23.000
CONC CURB & GUTTER (TY II)
LF 1,367.000 $35.000 $30.000 $35.000 $50.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 2.000 $950.000 $500.000 $1,200.000 $900.000
REMOVE SM RD SN SUP&AM
EA 1.000 $125.000 $100.000 $234.000 $155.000
PREFAB PAV MRK TY C (W) (8") (DOT)
LF 50.000 $5.000 $2.000 $14.000 $10.000
PREFAB PAV MRK TY C (W) (8") (SLD)
LF 170.000 $4.400 $5.000 $14.000 $6.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $250.000 $500.000 $555.000 $273.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $300.000 $500.000 $555.000 $332.000
REFL PAV MRKR TY II-C-R
EA 8.000 $5.000 $50.000 $13.000 $50.000
ELIM EXT PAV MRK & MRKS (8")
LF 290.000 $0.900 $2.000 $12.000 $3.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 1.000 $120.000 $50.000 $125.000 $84.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 1.000 $120.000 $50.000 $124.000 $87.000
PAV SURF PREP FOR MRK (8")
LF 220.000 $0.150 $10.000 $12.000 $3.000
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $30.000 $50.000 $654.000 $42.000
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $35.000 $50.000 $678.000 $47.000
REMOVAL OF CONDUIT
LF 210.000 $9.000 $10.000 $12.000 $3.000
REMOVAL OF GROUND BOXES
EA 2.000 $300.000 $200.000 $1,222.000 $120.000
REMOVAL OF CABLES
LF 210.000 $1.000 $5.000 $2.000 $1.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 88.000 $350.000 $200.000 $300.000 $300.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 45.000 $90.000 $150.000 $124.000 $600.000
TMA (STATIONARY)
DAY 45.000 $300.000 $300.000 $567.000 $1,900.000
Totals: $266,713.000 $299,986.380 $464,740.000 $566,638.000