County: MCLENNAN Highway: US 84 Date: 06/06/2024 (5 months ago) Engineer's Estimate: $266,713 Control Number: 0055-15-081
Project: STP 2B24(135)VRU District: WACO Time: 45 WORKING DAYS Type: INSTALL RAISED MEDIAN
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $266,713.00
ENCINO LANDSCAPE, INC.   $299,986.38 1
12.48% | $33,273.38
RISE UP CONSTRUCTION LLC   $464,740.00 2
74.25% | $198,027.00
54.92% | $164,753.62
DIGG COMMERCIAL, LLC   $566,638.00 3
112.45% | $299,925.00
88.89% | $266,651.62
21.93% | $101,898.00

Bid Items

Items: 33, 0 filtered
MCLENNAN US 84  |  WACO  |  0055-15-081  |  06/06/2024  |  $266,713  |  STP 2B24(135)VRU  |  INSTL RAISED MEDIAN  |  45 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ENCINO LANDSCAPE, INC. RISE UP CONSTRUCTION LLC DIGG COMMERCIAL, LLC
104 6001 REMOVING CONC (PAV) SY 1,256.000 $10.000 $10.000 $59.000 $27.000
104 6011 REMOVING CONC (MEDIANS) SY 235.000 $25.000 $20.000 $45.000 $81.000
104 6021 REMOVING CONC (CURB) LF 1,196.000 $10.000 $15.000 $23.000 $16.000
105 6065 REMOVING STAB BASE AND ASPH PAV (1") SY 1,584.000 $1.500 $10.000 $12.000 $8.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 179.000 $20.000 $60.000 $44.000 $64.000
360 6003 CONC PVMT (CONT REINF - CRCP) (9") SY 271.000 $73.000 $175.780 $399.000 $135.000
400 6011 SAND BACKFILL CY 103.000 $45.000 $60.000 $45.000 $70.000
432 6001 RIPRAP (CONC)(4 IN) CY 103.000 $600.000 $500.000 $400.000 $800.000
500 6001 MOBILIZATION LS 1.000 $25,000.000 $30,000.000 $25,000.000 $90,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $2,500.000 $2,000.000 $3,500.000 $10,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 600.000 $3.900 $2.000 $1.000 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 600.000 $0.720 $1.000 $1.000 $2.000
529 6005 CONC CURB (MONO) (TY II) LF 206.000 $25.000 $25.000 $35.000 $23.000
529 6008 CONC CURB & GUTTER (TY II) LF 1,367.000 $35.000 $30.000 $35.000 $50.000
644 6012 IN SM RD SN SUP&AM TY10BWG(1)SB(T) EA 2.000 $950.000 $500.000 $1,200.000 $900.000
644 6076 REMOVE SM RD SN SUP&AM EA 1.000 $125.000 $100.000 $234.000 $155.000
668 6070 PREFAB PAV MRK TY C (W) (8") (DOT) LF 50.000 $5.000 $2.000 $14.000 $10.000
668 6072 PREFAB PAV MRK TY C (W) (8") (SLD) LF 170.000 $4.400 $5.000 $14.000 $6.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 2.000 $250.000 $500.000 $555.000 $273.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 $300.000 $500.000 $555.000 $332.000
672 6010 REFL PAV MRKR TY II-C-R EA 8.000 $5.000 $50.000 $13.000 $50.000
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 290.000 $0.900 $2.000 $12.000 $3.000
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 1.000 $120.000 $50.000 $125.000 $84.000
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 1.000 $120.000 $50.000 $124.000 $87.000
678 6004 PAV SURF PREP FOR MRK (8") LF 220.000 $0.150 $10.000 $12.000 $3.000
678 6009 PAV SURF PREP FOR MRK (ARROW) EA 2.000 $30.000 $50.000 $654.000 $42.000
678 6016 PAV SURF PREP FOR MRK (WORD) EA 2.000 $35.000 $50.000 $678.000 $47.000
690 6001 REMOVAL OF CONDUIT LF 210.000 $9.000 $10.000 $12.000 $3.000
690 6006 REMOVAL OF GROUND BOXES EA 2.000 $300.000 $200.000 $1,222.000 $120.000
690 6009 REMOVAL OF CABLES LF 210.000 $1.000 $5.000 $2.000 $1.000
3076 6071 D-GR HMA TY-D PG 64-22 (EXEMPT) TON 88.000 $350.000 $200.000 $300.000 $300.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 45.000 $90.000 $150.000 $124.000 $600.000
6185 6002 TMA (STATIONARY) DAY 45.000 $300.000 $300.000 $567.000 $1,900.000
Totals: $266,713.00 $299,986.38 $464,740.00 $566,638.00